background image
A GUIDE FOR VILLAGE CARPENTERS
ON
HOW TO BUILT SAFER SHELTERS (HOUSES)
background image
HOW TO BUILD A SAFER SHELTER
A Guide for Households on how to build a shelter that will provide greater protection from future severe weather
conditions.
INTRODUCTION
The people in Ayeyarwaddy and Yangon Districts are beginning to recover from the devastation caused by last year’s
cyclone Nargis. Now, many shelters are being repaired, upgraded and reconstructed. How should these shelters be
built to better protect the families against the strong winds, heavy rains and high floods? UN-HABITAT, in collaboration
with other agencies in the shelter Cluster, have identified the following ten main points to incorporate and ensure that
every new shelter will better resist severe weather conditions and provide higher levels of protection.
ƒ
Build your house on stilts on the highest spot or your plot:
ƒ
Face the shorter side of a ‘rectangular type’ shelter towards where the strong winds normally blow from.
ƒ
Construct a roof with a steep slope (minimum 30 degrees), to reduce risk of being blown off.
ƒ
Limit the projection of the roof on all sides to maximum 18 inches.
ƒ
Fix the cover of the roof firmly to the frame of the roof.
ƒ
Fix rafters, purlins, tie beams and post plates firmly to the posts.
ƒ
Anchor the strong posts with solid footings to the ground.
ƒ
Strengthen your shelters against the winds with braces on each side.
ƒ
Maintain  the important parts of your shelter regularly.
ƒ
Re-tighten and repair your shelter before the monsoon starts.
These rules apply to all types of shelters, whether building with bamboo and fixing with ropes or if constructing with
palm trunks or timber joined by nuts and bolts. These rules do not only apply to constructions after cyclone Nargis,
but to any shelter construction you and your village members engage in from now on.
This Guide explains the special features, techniques and recommendations and shows how they can easy be
applied for any safe construction. Read the guide, discuss with your community, seek advice from carpenters and
build a safer shelter.
A shelter that is built using the methods described in this booklet will provide increased protection from wind and rain
and flood, and will enable you to sleep at night in the knowledge that you are in a strong and safer shelter.
David Evans, UN-HABITAT
background image
THE VILLAGE CARPENTERS GUIDE
Contents
Page.
Introduction
1
Chapter 1. General points for a Carpenter
3
1.1 Role of a carpenter
3
1.2 DRR requirements
3
1.3 ABC Principle
5
1.4 How to check the stability of an existing shelter
6
1.5 Shelter upgrading
7
Chapter 2. Construction Materials
9
Chapter 3. Tests to check resistance of shelters
14
Chapter 4. Construction Guidelines
17
Main Points to consider to build a safer shelter
29
Published by:
UN-HABITAT, Myanmar, April 2009
Prepared by:
Garmini Gunasekera, Chief Technical Trainer,
and the UN-HABITAT Training Team, Pya Pon
On base of the UN-HABITAT DRR Training Cycle
background image
A vuide for Villaeg Carpenters
4
Construction of new shelters and improvements of the stability of exis-ting
shelters are two important community activities, especially after the Cyclone
Nargis which destroyed a large number of shelters. As the shelters in the
delta region are mainly made out of timber or bamboo, the role of the Vil-
lage Carpenter
 is very important. Their services and advice are sought by
almost all families in order to build new shelters or to improve existing shel-
ters. Especially in the delta area, which is prone to seasonal rains, storms
and floods, the carpenter, has an important role to play: to improve the exist-
ing shelters and to construct new shel-ters in such a way that the can better
resist to the elements. While re-sistance to cyclones of the magnitude of
Nargis is beyond the scope of the village carpenter, he should be in a posi-
tion to advise households if their shelters can withstand the usual rains, storms
and floods - or how the shelters can be improved to better protect the fami-
lies in the rainy season and eventually, if required, build a new, more resis-
tant shelter.
This Guide offers an opportunity for Village Carpenters to acquire ad-ditional
skills and knowledge. The Guide includes the necessary tech-nical informa-
tion and guides the carpenter methodically through the total process of making
shelters more resistant to natural elements, using materials available in the
region, either by simple upgrading activities or by constructing of new shel-
ters.
The guide is not necessarily meant for reading from start to end. It may
serve as a source of reference for particular shelter construction or repair
activity envisaged in relation to a given shelter.
Carpenters who are thorough with the contents of this Guide will also be in a
position to act as advisors to householders and village com-mittees en-
gaged in shelter construction. These carpenters will contri-bute in an essen-
tial manner to the village efforts to be prepared for the forces of nature
during the rainy season in the delta region.
These skilled carpenters are invited to share skills and knowledge acquired
through the guide with their colleagues and other facilitators.
background image
5
A vuide for Villaeg Carpenters
A entre shelter in DRR compliance
background image
A vuide for Villaeg Carpenters
6
Chapter 1.
General points on shelter construction
1.1 The role of a carpenter
Provide four services.
A carpenter is called upon to provide four
services:
-
Advise households how they can make
their shelters safer.
-
Improve shelters resistance before rain
season.
-
Upgrade the safety and quality of ex-
isting
shelters
-
Build new shelters
1.2 Disaster Risk
Reduction (DRR)
Compliance
In order to reduce the risks of loss
of lives, livelihood and assets
cau-sed by heavy rains, strong
storms and high floods, the car-
penters have to observe some
main points and follow impor-
tant technical guidelines when
they upgrade any existing shel-
ter or build new safe houses.
In technical words this means:
DRR compliance of a shelter is its ability
to retain its original characteristics
after being subjected to natural
elements and continue to pro-
vide safe shelter to its occu-
pants and assets.
background image
7
A vuide for Villaeg Carpenters
Points to observe
Build on higher/safer ground
Short face of the house to wind-
ward direction
Roof pitch – minimum 30 degree
Roof projection – not more than
18" from all sides
Roof cover firmly fixed to rafter,
and purlin
Rafters, purlins, tie beams and
post plates have to be securely
fixed to posts
Provide bracings.
Posts firmly anchored to ground
Maintain/repair regularly
Repair/upgrade before monsoon
Disaster Risk Reduction
More safety from floods
More stability against winds.
Proper roof drainage.
Prevents roof blowing away
Prevents roof blowing away
Keeps roof cover intact against wind
forces
Prevents structural failure
Makes structure wind resistant
Prevents the posts (and even the
entire shelter) to tilt, sway or be
blown away
Extends the durability of shelter
Ensures that shelter remains resis-
tant and safe.
background image
A vuide for Villaeg Carpenters
8
1.3 ABC Principle
The general requirements in shelter construction in regard of DRR compli-
ance is summarized in a simple abbreviation: the ABC Principle.
A = Anchoring
Every part of the structure must
be tied back to some secure point
which is capable of resisting all
applied forces.
B = Bracing
Every part of the structure must
be held rigid so that it cannot tilt,
slide or rotate.
C =Continuity Every part of the
structure must be properly con-
nected to every other member.
ykHMurf; (3)tcsKyfwef;rsm;
abmifwGiff wyfqifxm;ykH
 gwfykH
(2)aocsmpGmukwfcsdwfxm;aom
wdkifESihfqihf
rlvD jzihf wyfqifxm;ykH
background image
9
A vuide for Villaeg Carpenters
1.4 How to check the stability of an existing shelter
Prior to planning any repair work or eventually a new construction to replace
an existing shelter, check the shelter for stability.
The stability of a shelter can be assessed by four checks, which are made
best when the household owner is assisted by the Village Carpenter.
- Is the majority of post bases decayed?
- Is the shelter tilted more than 5 degrees?
- Is the roof sagging?
- Are bracings provided?
A sagging roof
¿
                                             Tilted shelter 
¿
Braces
¿
Decayed posts
¿
background image
A vuide for Villaeg Carpenters
10
1.5 Shelter upgrading
Existing shelters shall be upgraded to better resist and thus better protect
the families against heavy rains, strong storms and high floods. Shelter up-
grading work involves:
 Remarks
Rearrange or replace roof cover and top mat.
To ensure good anchoring, weak posts should
be totally or partially replaced. Temporary sup-
porting is required while the posts are replaced.
Rafters and purlins should be replaced prior to
work on roof cover. When beams have to be
replaced, the structure should be temporarily
supported.
Additional braces make the shelter frame more
rigid and resistant to winds. It also helps to
straighten tilted structures.
Clean both top and bottom. Re-nail/re-rope
loose slats. Replace decayed parts.
Clean both internal and external faces. Provide
additional braces if required. Re-nail loose parts.
Paint with preservatives.
Check all frame joints. Tighten bolts & nuts.
Drive loose nails. Use new nails if required. Re-
rope if ropes are used.
 Upgrading
Repair or replace
roof cover and top
mat
Replace weak posts
Replace weak
beams, rafters, pur-
lins
Introduce or add
bracings
Repair floor deck
Repair wall cladding
Tighten loose joints
background image
11
A vuide for Villaeg Carpenters
Carpenters repairing a shelter 
¿
Check all structural members. Ensure that all
are properly anchored to resist all applied
loads.
Before purchasing new material consider pos-
sibility of re-using available or salvaged mate-
rial. Keep dismantled good material properly
stacked for future use.
Provide safe anchor-
ing
Re-use available/sal-
vaged material
Upgrading
                                  Remarks
background image
A vuide for Villaeg Carpenters
12
Chapter 2.
Construction Materials
The choice of construction material to be made in careful consideration of:
a. Availability
b.  Suitability
c. Quality
d.  Cost
Characteristics and
suitability of some major
construction materials.
Sawn Timber
Used as:
Posts, beams, joists,
bracings
Rafters, purlins
Floor boards
Wall cladding
Valance & Barge Boards
Characteristics
Variety of grades ranging
from strong to weak and
durable to non-durable.
Gives a neat finish
Available in many common
sizes
Many species have resis
tance to termite/pest attack
Easy to work. Can be as
sembled with conventional
timber joints. Can be nailed
or bolted
High cost
Consider required strength
and durability for intended
use
Sawn timber post & Joist joint with nuts & bolts
¿
Halving joint 
¿
Sawn timber post and
joist joint
.
¾
background image
13
A vuide for Villaeg Carpenters
Bamboo
Posts, Beams, Joists
Rafters and Purlins
Characteristics:
Low cost
Susceptible to ter
mite/pest attack
Strong for most loca
tions of the structure
For main structure  dif
ficult since proper
jointing is complicated.
Round section of bamboo makes
anchoring difficult.
Splits easily.
Very good for rafters, purlins.
Bamboo is split and used for floor deck and wall cladding
Toddy Palm :
Posts, beams, joists,
bracings
Rafters, purlins
Characteristics:
Strong and durable
Hard outer layer/soft inner
layer
Resistant termite/pest at
tack
No neat finish since the
trunk is split and not sawn
Adequate stocks available
Difficult to work.
Can be nailed or bolted
Relatively low cost
Ensure that the soft core part of
the trunk is completely removed.
Toddy Palm
¿
Now used fixing method
¿
Improved method of fixing
bamboo joints
¿
background image
A vuide for Villaeg Carpenters
14
Jungle Wood.
Posts, Beams, Joists
Rafters and Purlins
Characteristics:
Relatively low cost strong
structural material.
Some species are very durable.
Round and usually tapering in
section.
Can be used for most locations
of the structure.
Jointed with bolts & nuts, nails or
roping
Select larger diameter trunks from du-
rable species
Jungle wood joint between post and joist.
¾
Nipa palm thatch
Used for roof cover and sometimes for wall cladding.
Characteristics
Freely available; but seasonal.
Requires preparation prior to covering.
Provides a thick waterproof cover if properly laid.
Requires firm fixing to rafters/purlins to avoid blowing away due to
wind.
Low cost.
Rainwater harvesting is difficult
Nipa palm covered roof 
¿
background image
15
A vuide for Villaeg Carpenters
Sawn timber planks
Floor deck
Doors & Windows
Valance – and Barge boards
Characteristics:
High cost.
Gives a neat and waterproof,
even finish
Strong
Split bamboo
Used for floor deck
Characteristics
Most common type of floor in
the delta
A well conversant material.
Low cost
Does not provide an even floor
surface
Installation is simple
Purchase large diameter bamboo for
floor deck work.
Roof with CGI-sheets
¿
Sawn tim-
ber planks
¾
house with Bamboo floor mat 
¾
CGI Sheet
Roof cover
Cladding
Characteristics
High cost.
Ready for use.
May pause safety hazard if not
properly fixed.
Liable to corrode.
Light weight.
Easy to lay
Specifications:
CGI sheets 30 or 32 gauge are suitable for normal shelter roofs
background image
A vuide for Villaeg Carpenters
16
Arricanut strips (split trunks)
Used for floor deck
Characteristics:
Split arricanut trunks.
Low cost.
Not an even floor surface.
Nailing or tying with strings
Weaved bamboo mat
for wall
Most common wall cladding in
shelters in the delta area.
Quality of mat depends on the
thickness of veneers.
Weaved in different designs
For strength and durability,
select mats weaved from
thick strips.
¿
½
Different bamboo mats designs
background image
17
A vuide for Villaeg Carpenters
Chapter 3: Tests to check resistance of shelter
construction
The following three tests
shall prove on site if the
constructions is done
properly done so that the
shelter will resists to the
natural forces.
Bending of column
posts
Will the post resist
against strong winds?To
test the ability of column
posts to resist high
winds.If a post firmly bur-
ied in ground if pulled by
02 people (average
force of 130 kg) returns
back to its original posi-
tion, it can be consid-
ered to withstand normal
wind forces.
Resistance for uplift-
ing of post footings
Are
the post footings well
anchored in the
ground?Using rope and
cross bar two people will
pull out a post footing
buried in soil. If the force
exerted by the two
people cannot move the
footing, it is safe from
uplifting. If it comes
loose the area around is
not compacted properly
and should be re-com-
pacted.
¿
background image
A vuide for Villaeg Carpenters
18
Testing soil at the bottom
of post footings
Is the soil hard and com-
pacted enough to place
footings/posts?
Hold a 5 kg crow bar 3
feet  above ground, di-
rectly above the pit, with
its pointed end down-
wards. Drop it freely on
bottom.
If the penetration of the
crowbar is less than 6",
the soil is hard enough for
placing the footing. If not
it should be improved by
consolidation or new fill-
ing.
Entire shelter under construction
¿
¿
background image
19
A vuide for Villaeg Carpenters
Chapter 4:   Construction guidelines
A good carpenter has to produce a safe, strong shelter with good finish.
This can only be
achieved when these
good work practices are
applied:
1) Site preparation
A typical shelter site may
require all or only some
of the following activities:
·
Clearing
·
Leveling
·
Providing access
to site
·
Allocation of space
for material storage
·
Water supply
·
Waste disposal
·
Fencing
2) Setting out
In timber- and bamboo construction se
tting out is to mark the lo-
cation of cente
rs of all posts on ground.
1. Select shelter location
site.
2. Use wooden pegs and
strings for drawing lines.
3. Set out base line.
4. Set out right angles
(3:4:5)
5. Set out other lines per-
pendicular to base line.
6. Complete the rect-
angle/s.
7. For accuracy: measure
diagonals
Sketch of men prepar-
ing a 
site
¿
Center line net-
work.
background image
A vuide for Villaeg Carpenters
20
3) Excavation for posts
Mark location of column posts at each intersection of setting out lines.
From the centre mark width of the pit.
Excavate using auger or crow bar and shovel Stack excavated material away
from opening Excavate to required depth Bottoms of all pits should be at
the same level. Use water level for leveling depth of excavation.
4) Preparation of posts
Before erecting posts
they prepare them to
receive floor joists,
post plates, ridge plate
and tie beams.
This is done by provid-
ing chases at appropri-
ate heights to accom-
modate joists and
posts. Provision of
chases makes the joint
secure and share the
load.
Give attention to pro-
vide proper roof slope
in cutting chases for
ridge plate.
2 ay 
x
2 ay
okdYr[kwf
3 ay
3 ay
¿
(u) ajrrmtwGuf tkwfjrpf
¿
Chase cut out on post to receive post plate
background image
21
A vuide for Villaeg Carpenters
5) Erection of posts
Prepared posts can be erected in the excavated pits at proper locations.
After erecting, the posts should be plumbed and held firmly in position with
temporary props.
Compaction of the base of the post is not after erection, but postponed
until the main structure is assembled. This provides room for any adjust-
ments during fabrication.
Posts held in position with temporary supports
¿
background image
A vuide for Villaeg Carpenters
22
6) Mounting joists of the frame
At floor level: (a) Cross joists; (b) Long joists, (c) Floor joists
At roof level: (d) post plates, (e) tie beams and (f) ridge plate
The joists are placed in pre-prepared slots (chases) and fixed using bolts &
nuts, nails or ropes (mainly if bamboo is used).
“gwfyHk (29)
wdkifESifh wvdkif;
Murf;cif;&efqifhrsm;,ufray:qifhxm;ykH
wdkifESifhwvdkif;^EGm;qufyHk
¿
wvdkif;^EGm;? ,u®ESifh qifhwdkYudk
wdkifwGif rlvDpGJí zm;wHk;cHxm;yHk
wdkifxdef;wef;ESifh tcsKyfwef;udk
background image
23
A vuide for Villaeg Carpenters
(7) 'dkif;wyfqifjcif;
•  
'dkif;rsm;udkoifhawmfaomqifajcavsmjzifh wyfqif&rnf/
tenf;qHk;qifajcavsmrSm(30) 'D*&Djzpfonf/ wpfenf; tm;jzifhqdkaomf
cef;zGifhtus,f(24)aywGif acgiftjrifh(7)ay? cef;zGifhtus,fay(20)wGif
acgiftjrifh (6)ay? cef;zGifhtus,f(18)aywGif acgiftjrifh(5ay 6vufr)?
cef;zGifhtus,f(16)aywGif acgiftjrifh(5)ay&Sd&rnf/ wdkifrsm; jyifqifpOfuyif
t
r
d
k
;
\
q
i
f
a
j
c
a
v
s
m
u
d
k
pOf;pm;NyD;jzpf&m'dkif;\txufydkif;udkacgif&Sd'dkif;csKyfwef;ay:wGifwif&ef
xpf xm;NyD;jzpfonf/
•  
'dkif;rsm;\txufydkif;udk'dkif;csKyfwef;ay:wGif
wifíatmufydkif;udkwdkifxdef;wef;jzpfonfh a,mufay:wGif wif&onf/
aqmufvkyfa&;enf;pepfESifhtoHk;jyKaomypönf;ay:rlwnfí rlvDpkyfjcif;?
oH½dkufjcif;jyKvkyf&onf/ rsm;aom tm;jzifhoH½dkufonf/ 0g;toHk;jyKygu
BudK;jzifhcsnfaESmif&onf/ 'dkif;rsm;udk  owfrSwfxm;aom
qifajcavsm&ap&ef trdk;ay:rwifrDajray:wGifwdkif;xGmítxpfjyKvkyf&onf/
vdktyfygu acgiftjrifhwpf0ufwGif opfom;tcsKyfwef; udkxpfí
u e f Y v e f h j z w f u m ' d k i f ; u d k c s K y f í w y f q i f a y ; & o n f /
vdktyfyguaxmufwef;xnfhay;&onf/ odkYrSom'dkif;onf usa&mufrnfh
z dt m ; 0 e f u d k c H E d k i f N y D ; u m ; x G u f o G m ; j c i f ; r S u m u G, f E d k i f o n f /
tcsKyfwef;rsm;udk xuf0ufxpfí oHpJG&rnf/
“gwfyHk (33)
yxr’dkif;wpfpHkwifaeyHk
'kdif; rsm; ukd wifaeyHk 
¿
background image
A vuide for Villaeg Carpenters
24
(8) acgifrdk;jrm;wef;rsm; wyfqifjcif;
jrm;wef;rsmudk'dkif;ay:wGif uefYvefYjzwfumoH½dkufíjzpfap?
BudK;jzifhcsnfaESmifíjzpfapwyfqif&onf/ avjyif; wdkufaom tcg
trdk;vGifhrxGufoGm;ap&efrQm;wef;udk 'D*&D(90) wpfqpfcsdK;vdrfxm;aom
oHrPdoHjym;(tmvdef)jzifh 'dkif;ESifh 0uftl pkyfxm;&onf/
“gwfyHk (35)
‘dkif;\tcsKyfwef;rsm;
 “gwfyHk (34)
‘dkif;tm;vHk;wyfqifNyD;yHk
“gwfykH (36)
o H r P d o H j y m ; j z i h f
rQm;wef;ESihf’dkif;csdwfwG,faeykH
'dkif;tm;vHk; wyfqifNyD;yHk 
¿
'dkif;csKKyfwef;rsm;
¿
oHrPdjym;jzifh jrm;wef;ESifh 'dkif;ukd
csdwfwG,fxm;yHk 
¿
background image
25
A vuide for Villaeg Carpenters
(9) trdk;rdk;jcif;
oufu,frdk;
oufu,frdk;&ef 'dkif;rsm;ay:wGifqDbl;qJGrsm;wifí oHESifh½dkuf&onf/
qDbl;qJGay:wGif tjcif0g;rsm;udk(9vufr)rS (12vufr)jcm;pDNyD;
csnfaESmifxm;um oufu,fyspfrsm;wifírdk;&onf/ trdk;atmufbufpwifí
oufu,fyspfrsm;udk tjcif0g;ay:wGifwifumESD;jzifh
cdkifNrJpGmcsnfaESmifxm;&onf/ acgifudkoufu,fjzifhomzHk;tkyfí
tHk;qHBudK;(odkYr[kwf) yvyfpwpfBudK;jzifh cdkifNrJatmifcsnfaESmif&onf/
"edrdk;
•  
"edyspfrsm;udk trdk;atmufbufrSpwifrdk;&onf/
oufu,frdk;ouJhodkYyifrdk;&onf/ trdk;rdk;&mwGif ESD;jzifhtjcifudk
wpfywfywfNyD; "edyspf&Sd"edwHjzifhñSyfí&pfacGcsnfaESmif&onf/
oufu,frdk;xm;aomaetdrf
¿
oufu,frdk;atmufbufjrif&yHk
¿
background image
A vuide for Villaeg Carpenters
26
oGyfjym;
    oGyfjym;rdk;&mwGif twef;vdkufxyf&mü tenf;qHk; 6 vufr xyf&rnf/
ab;wdkufxyfvQif 1 ajrmif;rS 2 ajrmif;xyf&rnf/
  atmufqHk;wef;udkrdk;&mwGif ajzmifhwef;ap&ef BudK;qJGí rdk;&rnf/
qufvufí ajrmif;rsm;nDnmí txdkifusap&ef csxm;&rnf/
   oGyfjym;rdk;&mwGifwpfbufxdyfwGif
cGufyHkygaomoGyf&nfokwfoHudkoHk;&rnf/ oH½dkuf&mwGif tay:buf
cHk;aeaom ae&mwGif wpfcHk;ausmf ½dkuf&rnf/ odkYrSom cdkifNrJí
av'PfaMumifh vGifhpifjcif;? rdk;a&,dkpdrfhjcif;rS   umuG,fEdkifrnf/
   ydkrdkaumif;rGefaomenf;rSm t*FvdyfpmvHk; JyHk&Sd oHrlvDrsm;udk
toHk;jyKEdkifygonf/ wefbdk;jrifhrm;ívuf0ifonf? acgiftkyf
rsm;udkajymifoGyfjym;rsm;toHk;jyKum vdktyfovdk yHkazmfNyD;
trdk;(2)bufqHk&m acgifay:wGiftkyfí oH½dkufNyD;wyfqif&rnf/wyfqif&mwGif
acgiftkwfAsufonf wpfbufvQif 12vufr&SdNyD; ab;wdkufxyf&mwGif tenf;qHk;
9 vufr &Sd&rnf/
oGyfjym;½kduf
oHrsm;
oGyfrdk;tjynfh rdk;xm;yHk
¿
J
yHk oHrlvD
r s m ; E S i f h
cGufyHk
y g a o m
oGyfrdk;
½dkufoHrsm;
¾
background image
27
A vuide for Villaeg Carpenters
(10) yef;qJG·
t d r f \ r s u f E S m p m E S i f h
aemufaz; buf
acgifrdk;tpGef;wGif&Sdaom
' d k i f ; r s m ; E S i f h
tdrf\ab;ESpfbufESpfcsuf?
j r i f h r d k & f
b u f & S d r Q m ; w e f ; r s m ;
r d k ; r p d k a p & e f E S i f h
tdrftvSqif&ef (7 vufr)
&Sdaom yef;qJGrsm;udk
'dkif;ESifhjrm;wef;xdyfwGif
o H ½ d k u f í w y f q i f & o n f /
'dkif;ydwfjrm; ydwf
[kvnf;ac:onf/
(11) a&wHavQmuf
(6vufr) tcsif;&Sdaom
y D A G D p D y d k u f r m
r
s
m
;
u
d
k
x u f 0 u f j c r f ; í a o m f v n f ;
aumif;? ajymif oHjym;udk
(6)vufr? (4)vufr t&G,f
yHkazmfíaomfvnf; aumif;?
acgifrdk;rSpD;us vmaom
r d k ; a & u d k
p k a q m i f ; c H , l N y D ;
pGefYypfEdkif&eftdrfa&SYESifh    tdrftaemufbuf wGifwyfqifxm;
&Sdonfhyef;qJGrsm;wGif
b&ufuufrsm; jzifh
csdwfqJGwyfqif xm;ygonf/
þodkY wyfqifxm;jcif;jzifh
acgifrdk;rSpD;qif;vmonfh
rdk;a&rsm; wHpuf
N r d w f r S w p f q i f h
ajray:odkYvGifhpifusjcif;
r & S d a p & e f E S i f h
acgifrdk;rS rdk;a&udktoHk;
j
y
K
&
e
f
cH,lEdkifonfhtusdK;oufa&mufrIESpfrsdK;
&&Sdygonf/
(12) Murf;cif;
Murf;cif;&ef0g;zsmjyKvkyf&efjyifqifjcif;
0g;jcrf;cif;jyKvkyf&ef
0g;cJGaeyHk ¾
?a&wHavQmufukdtokH;jyKí a&oG,fcH,laeykH 
¿
background image
A vuide for Villaeg Carpenters
28
(13) Murf;cif;jcif;
jyifqifNyD;aom0g;jym;rsm;udk wdkifae&mywfvnfwGifvSD;jzwfxkwfíwduspGm
tH0ifcGifusjzpfatmifjyKvkyfNyD; Murf;cif;\ qifhrsm;ay:wGif
oH½dkufwyfqif&onf/
(14) eH&Habmif
       a'gifvkduf? tvsm;vdkuf? tapmif;vdkuf? opfom;wef;rsm;udk wdkif?
wdkifxdef;wef;? qifhrsm;wGif wyfqifum eH&Hwyfqif&efabmif&vmygonf/
eH&Hum&ef&mwGif taxmuftuljyKonfhtjyif taqmuftOD\tcsKyftjzpfvnf;
aqmif&Gufygonf/ tvsm;vdkufwef;rsm;udk MuGufavQmuf[kac: NyD;
a'gifvdkufwef;rsm;udk usHwdkif^uRJeH[kac:onf/
“gwfyHk (45)eH&Hwyfqif&ef
eH&Habmifrsm; wyfqifxm;yHk
cJGíayguf
xm;aom
0g;jym;rsm;ukd
csnfaESmifaeykH
eH&Hwyfqif&ef eH&Habmifrsm;
wyfqifxm;yHk
¿
½
background image
29
A vuide for Villaeg Carpenters
(15) wHcg;? jywif;abmif
                  aetdrfwpftdrfwGif t0iftxGufjyKvkyf&efESifhav0ifavxGufEdkif&ef
tdrfa&SU ESifhtdrfaemufab;wGifwHcg; (1)aygufpDESifh
av0ifavxGufaumif;ap&ef tenf;qHk;jywif;ayguf (2) ayguf&Sd&rnf/
wHcg;ESifhjywif;abmifrsm;udk cGJom; 3vufr? 2vufr  (odkYr[kwf 4vufr? 1vufr)
jzifhjyKvkyf&rnf/ abmifudkqif&mwGif uefYvefYjzwfwpf0ufzHk; (Cross half lap)
ESifhtvsm;vdkufwpf0ufxyftxufoHk;&rnf/ abmif&Sdtquf rsm;udkoH½dkuf&rnf/
þenf;udkvufckyfvuf0g;qufenf; [kvnf;ac:NyD;aus;vufa'oESifhoifhawmfonf/
abmifrsm; jyKvkyfNyD;aomtcgeH&HwGif
wyfqifxm;aomusnf;abmifwGifywåmESifh0uftlrsm;oHk;íwyfqif&rnf/ wHcg;jywif;
tumrsm;udkeH&HumNyD;rSwyfqif&rnf/  wHcg;jywif;tumrsm;onf
trsm;tm;jzifheH&Hum&Honfh ypönf;trsdK;tpm;jzpfonf/ rSwfcsuf/  /
ywåmudkabmif\tay:bufwGif wyfqifxm;onfh a'gifvdkufzGifhaom
wHcg;jywif;rsm;onfav\ wdkufcwfrIudkydkrdkcHEdkif&nf&Sdonf/
wHcg;usnf;abmifwyfqifxm;yHk
¿
a'gifvdkufzGifh wJvm;jywif;\ wHcg;&Guf(ydkrdkí
av'PfcHEdkifonf)
¿
wHcg; wyfqifNyD;yHk (ydkrdkí
av'PfcHEdkifonf)
¿
background image
A vuide for Villaeg Carpenters
30
(16) tdrfwGif;odkY 0ifxGufjcif;
           wdkifjzifhjr§ifhwifumaqmufvkyfxm;aom
aetdrfrsm;odkYwufa&mufEdkif&efavSum;odkYr[kwf
qifajcavsmtwuftqif;cHkwyfqifxm;&efvdktyfonf/
t0iftxGufjyKvkyfEdkif&eftdrfa&SUESifhtdrftaemufbuf
(2) bufpvHk;wGifwyfqifxm;&rnf?
taqmuftOD
u
d
k
,
f
x
n
f
w
G
i
f
o H k ; a o m y p ö n f ; r s m ; u d k y i f
oHk;Edkifonf/
r o e f r p G r f ; o l r s m ; ?
v G e f p G m t o u f B u D ; o l r s m ; ?
v
G
e
f
p
G
m
t
o
u
f
i,faomuav;rsm;rdom;pkxJwGif&Sdvsif
q
i
f
a
j
c
a
v
s
m
twuftqif;cHkrSmydkrdkoifhawmfonf/
tu,fí qifajcavsmtwuftqif;cHkwyfqifygu
qifajcavsm onf  tvsm; (4) aywGif tjrifh
(1) ayEIef;xufrydk&/
avSum;xpfrsm;wGifuyfvsuf&SdaomavSum;xpf(2)
xpf\ tjrihfudk ajcausmf[kac:NyD;
ajceif;jym;\ Asufudk ajceif; [kac:onf/
avSum;xpfa&G;cs,f wGufcsuf
o w f r S w f & m w G i f
atmufygyHkaoenf;udkoHk;onf/
g
w
f
y
H
k
(50)qifajcavsmtwuftqif;cHk
ajceif;
(2 _ajceif;) +(ajcausmf) =23 vufr
avSum;xpfrsm;wyfqifyHk
avSum;\ ajcausmfajceif;
tcsdK;jyyHk À
qifajcavsm twuftqif;cHk
¿
background image
31
A vuide for Villaeg Carpenters
ed*Hk;
þvrf;nTefonf rdrdwdkY\todOmPfESifhpGrf;&nfudkjrSifhwifum
cdkvHSk&maetdrfwnfaqmuf&mwGif jrpf0uRef;ay:a'o½dS vuform;rsm;twGuf
vufpGJpmtkyftjzpf toHk;csEkdifrnf[k,HkMunfygonf/ þvrf;nTefonfvuform;
wpfOD;aqmif&Guf&rnfhu@? aetdrfaqmufvkyf&mwGif
ab;tEå&m,fusa&mufEdkifrI avQmhcs&efvdkufem&rnfhtcsuf tvuf?
jrpf0uRef;ay:a'owGiftoHk;rsm;aomaqmufvkyfa&;ypönf;rsm;? opfom;?
0 g ; w d k Y N z i f h a q m u f v k y f a o m
pHerlemcdkvIH&maetdrfrsm;wnfaqmuf&mwGif ppfaq;&eftcsufrsm;?
tqifhqifhaqmif&Guf&rnfh udpö&yfrsm;udk ½Sif;vif;az:jyxm;ygonf/
pmzwfol\tm½HkpdkufrIudk pdwfcs&aomcdkvIH&maetdrfwnfaqmufa&;\ ta&;
ygyHkay:wGif oufa&mufapaomfvnf; þvrf;nTefonf a'owGif;
usa&mufavh½dSonfh rdk;onf;xefpGm&GmoGef;jcif;? a&vQHjcif;?
rkefwdkif;usa&mufjcif; ponfhab;tEå&m,frsm;cHEdkifap&ef
wnfaqmufa&;enf;vrf;rsm;udkvnf; xnfhoGif; az:jyxm;ygonf/
þenf;vrf;rsm;onfyifvQif ajrivsifvIyfjcif;'PfudkcHEdIifNyD; cdkvHI&maetdrf\
wnfNidrf cdkifchHrIudk wdk;wuf&½dSEdkifygonf/ rD;ab;umuG,fa&;udk
þvrf;nTefwGifraz:jyxm;yg/ tb,faBumihfqdkaomf tdrfaxmifpk
0ifrdom;pkrsm;ESifhjynfolvlxktrsm;pkrSmrD;ab;tEå&m,fumuG,fa&;udkaocsmpGmBuKdwifjyifqifxm;NyD;aMumihfhyif/
þvrf;nTefESifhvufpGJpmtkyfygtwdkif; aetdrfrsm;tm;jyKjyifjcif;?
wnfaqmufjcif;jyKvkyfrnfqdkygu az:jyyg tEå&m,frsm;udk
ydkrdkcHEkdif&nf½dSum toufaygif;rsm;pGmaoaMuysufpD;jcif;?
pnf;pdrfOpömqHk;½SHK;jcif;rSavsmhyg; apEdIifrnfjzpfygonf/
oYdkjzpf&mjynfolwdkY\toufarG;0rf;aMumif;rSmvnf; xdcdkufrIenf;yg;rnfhtjyif
pD;yGm;a&;ESifh  vlrIa&;wdk;wufrIudk t[efYtwm;jzpfaprnfh
ab;tEå&m,fjzpfrItvm;tvmudkvnf; avsmhcsEdkifrnfjzpfonf/
þtcsufonfyifvQifab;tEå&m,fusa&mufEdIifrI avsmhcsa&;yifjzpfonf/
ydkrdkvHkjcHKpdwfcs&aom aetdrfjyefvnfwnfaqmufa&;onf
ta&;tBuD;qHk;aom&nf&G,fcsufjzpfojzifh rdom;pk wdkif;\ta&;jzpfonf/
rdom;pkwdkif;onf rdrdwdkY\aetdrfrsm;udkjyifqifxdef;odrf;jcif;?
wdk;wufatmifjyKjyifjcif;? rBumrDa&muf&Sdvmawmhrnfhrdk;&moDudk
xnfhoGif;pOf;pm;um rdrdwdkY\wnfjidrfrIESifh ckdifcHhrItm;enf;aom
aetdrfrsm; tm;tqiffhjrSifhwifjcif;? jyefvnfjyKjyifwnfaqmufjcif;rsm;udk
aqmif&GufBu&ayrnf/ þudpöudk tdrfaxmifpk vrf;nTefwGifaz:jyxm;ygonf/
jyifqifxdef;odrf;jcif;ESifh tqifhjrSifhwifa&;onf rdom;pkwdkif;ESifhoufqdkifojzifh
wpfOD;aumif;wpfa,mufaumif; aqmif&Gufír&yg/ &GmvHk;uGswf
nDnmpGmpkaygif;aqmif&Guf&rnfh vkyfief;jzpfonf/ jynfolvlxktm;vHk;
tm&kHpdkuf pdwf0ifpm;vma&; vkyfief;tqifhqifh
aqmif&Guf&efpnf;&kH;vIHYaqmfa&;? rdrdwdkY\&Sd&if;aiGtiftm;? vltiftm;
ponfht&if;tjrpfrsm;? xyfrH&&Sdvmrnfh&HyHkaiGESifh
background image
Points to observe
Build on higher/safer ground
Short face of the house to wind-
ward direction
Roof pitch – minimum 30 degree
Roof projection – not more than
18" from all sides
Roof cover firmly fixed to rafter,
and purlin
Rafters, purlins, tie beams and
post plates have to be securely
fixed to posts
Provide bracings.
Posts firmly anchored to ground
Maintain/repair regularly
Repair/upgrade before monsoon
Disaster Risk Reduction
More safety from floods
More stability against winds.
Proper roof drainage.
Prevents roof blowing away
Prevents roof blowing away
Keeps roof cover intact against wind
forces
Prevents structural failure
Makes structure wind resistant
Prevents the posts (and even the
entire shelter) to tilt, sway or be
blown away
Extends the durability of shelter
Ensures that shelter remains resis-
tant and safe.
Disaster Risk Reduction (DRR) Compliance