background image
 
 
 
 
 
 
 
 
 
Government of the 
 Cook Islands, Federated States of Micronesia,  
Fiji, Marshall Islands, Nauru, Niue, Palau, Papua New Guinea, 
 Samoa, Solomon Islands, Tonga, Tuvalu and Vanuatu 
 
 
 
United Nations Development Programme Project Document 
Global Environment Facility 
 
 
 
Secretariat of the Pacific Regional Environment Programme 
 
 
 
PIMS 2162 
PACIFIC ADAPTATION TO CLIMATE CHANGE (PACC) 
INCEPTION PHASE REPORT 
 
 
Prepared by  
 
Taito Nakalevu 
Regional Programme Manager 
Pacific Adaptation to Climate Change Project 
 
October, 2009 
 
 
background image
TABLE OF CONTENTS 
 
 
ACRONYMS.............................................................................................................. 4 
I. Introduction .................................................................................................................... 5 
A. Purpose of Report .................................................................................................... 5 
B. PACC project design background .......................................................................... 5 
C. PACC Project Preparatory Phase .......................................................................... 6 
D. Project Milestones .................................................................................................... 6 
II. 
Inception Phase Review ......................................................................................... 7 
A. Purpose of the review............................................................................................... 7 
B. How was the review conducted ............................................................................... 7 
C. Areas that were subjected for review..................................................................... 7 
III. Review Results ............................................................................................................. 8 
A. Institutional Arrangements..................................................................................... 8 
(i) Regional Project Management Office (PMO)........................................................ 8 
(ii) PMO Personals...................................................................................................... 8 
(iii) Regional Oversight Mechanism........................................................................... 9 
(iv) National Implementation Arrangement................................................................ 9 
(v) National Climate Change Country Team and Project Management Unit ............. 9 
(vi) The National PMU ............................................................................................. 10 
B. Logical Framework ................................................................................................ 10 
C. Review of the role and responsibility of various partners.................................. 11 
(i) Local Communities .............................................................................................. 11 
(ii) Government Departments / Ministries................................................................ 11 
(iii) University of Hawaii – [Hazards and Climate Programme] .............................. 11 
(iv) International Climate Change Adaptation Initiative (AusAID) ......................... 11 
(v) International Union for Conservation of Nature (IUCN).................................... 12 
(vi) South Pacific Applied Geosciences Commission .............................................. 12 
(vii) Secretariat of the Pacific Community ............................................................... 12 
(viii) University of the South Pacific ........................................................................ 12 
(ix) United Nations Institute for Training and Research .......................................... 12 
D. Review of the project management arrangements.............................................. 13 
E. Review of the project Monitoring and Evaluation (M&E) ................................ 13 
F. Review of co-financing activities ........................................................................... 14 
G. Capacity of the National Coordinators and Country Teams............................. 15 
H. Project Operation Manual (POM) ....................................................................... 16 
I. Operational criteria for assistance including allocation of funds ....................... 16 
background image
J. An overall work plan for the first year of implementation................................. 17 
K. Disbursement of Project funds ............................................................................. 18 
L. Strategic linkages at the national and regional levels ......................................... 19 
IV. Specific Issues raised during the Inception Workshop ............................................ 19 
V. Progress and Next Steps.............................................................................................. 21 
VI. Annexes ...................................................................................................................... 29 
ANNEX I – Logical Framework [after Inception Review] ..................................... 30 
ANNEX II – Project Management Arrangement .................................................... 40 
ANNEX III - Project Monitoring and Evaluation ................................................... 41 
ANNEX IV - PACC Co-Financing Support ............................................................. 42 
ANNEX V COUNTRY PROGRESS......................................................................... 45 
 
 
 
 
 
 
 
background image
ACRONYMS 
 
CCCC - Carribean Climate Change Centre 
CROP – Council of Regional Organization in the Pacific 
EDULINK – Education Link 
GEF CEO – Global Environment Facility Chief Executive Officer 
GEF – Global Environment Facility 
GEF PAS - Global Environment Facility Pacific Alliance for Sustainability 
ICCAI – International Climate Change Adaptation Initiative 
IISD – International Institute for Sustainable Development 
IP – Inception Phase 
IPR – Inception Phase Review 
MCO – Multi-Country Office 
MIND – Munashinge Institute for Sustainable Development 
NAPA – National Adaptation Programme of Action 
NCs – National Coordinators 
NCCCTs – National Climate Change Country Teams 
NPIA – National PACC Implementing Agencies 
NUS – National University of Samoa 
PEG – Project Executive Group 
PACC – Pacific Adaptation to Climate Change 
PICCAP – Pacific Islands Climate Change Assistance Project 
PMO – Project Management Manual 
POM - Project Operation Manual 
ProDoc – Project Document 
SCCF - Special Climate Change Fund 
SEI – Stockholm Environment Institute 
SPC – Secretariat of the Pacific Community 
 
SOPAC – South Pacific Applied Geosciences Commission 
SPREP – Secretariat of the Pacific Regional Environment Programme 
UNDP – United Nations Development Programme 
UNITAR – United Nations Institute for Training and Research 
UPNG – University of Papua New Guinea 
 
 
background image
 
I. Introduction 
A. Purpose of Report 
 
1.
 
As per the PACC ProDoc, the first six (6) months of the PACC project is considered as 
the Inception Phase (IP), stretching between April to the end of September 2009. The IP provides 
an opportunity for the Project Management Office (PMO) to become acquainted with the Project 
– its agreed strategy, expected outputs and outcomes, the stakeholders, the risks etc. It is also an 
opportunity for the stakeholders and partners to provide input on the work plan and to confirm 
implementation arrangements both at the regional and national levels. It also provides an 
opportunity to finalize any outstanding implementation details and present them to UNDP and 
SPREP for clearance. The IP also brings new momentum to the project after the relatively quiet 
period during the project approval process.  In addition it includes a review of the ProDoc. Such 
review is of particular importance in this case due to the very significant time lag between initial 
project design and actual implementation, i.e. thus there is a need for adaptive management to 
reflect major changes in the present project environment.  
2.
 
The purpose then of this report is to document the review that was undertaken during the 
IP of the PACC Full Sized project. It also includes in detail the outcomes of the Inception 
Meeting that was held at SPREP on the 29
th
 of June to the 3
rd
 of July 09, and follow up actions 
resulting from it. 
B. PACC project design background 
3.
 
The PACC project is the first adaptation project to be implemented in the region that 
responds directly to the call by the Pacific leaders and people for urgent action to address the 
adverse effects of climate change they are already facing.  The project addresses these key 
concerns on three fronts: 
 
(a)
 
Improving capacity in Pacific islands' governments to mainstream climate change 
adaptation into government policies and plans; 
(b)
 
Addressing the urgent need for adaptation measures through developing systematic 
guidelines for adaptation and demonstrating their use at a pilot scale in the coastal 
management, food security and water resources sectors; and 
(c)
 
Laying the foundation for a comprehensive approach to address adaptation over the 
medium-long term at the regional level.  
4.
 
The design of the PACC project is in accordance with the guidance paper of the GEF on 
the Special Climate Change Fund (SCCF). It notes that SCCF projects should be country-driven, 
cost-effective and integrated into national sustainable development and poverty-reduction 
strategies and also take into account national communications or NAPAs and other relevant 
studies.  Therefore, the PACC project baseline and co-financing will be the national sustainable 
development and poverty reduction actions that are carried out at the national level. The PACC 
project therefore only finances the additional costs of achieving sustainable development imposed 
on the Pacific by the impacts of climate change. Critical hence in this case would be the 
alignment of PACC activities with sustainable development and poverty reduction activities at the 
national level and the synchronisation and timing of implementation of these activities. Loss of 
synchronisation means loss of co-financing support earmarked for PACC thus causing design 
demise. 
background image
C. PACC Project Preparatory Phase
 
5.
 
The PACC project started its design process in July 2006 when funds were received by 
SPREP to carry out the Inception workshop in Nadi, Fiji. This was also called the Phase I PDF-B 
exercise to design and develop and ascertain the components of the Full Sized Project in 
consultation with the participating countries.  Eleven
countries were part of the PACC 
preparatory phase then without Marshall Islands and Palau. 
6.
 
The final PACC documents were to be submitted to the GEF in July 2007 however, that 
was not to be due to a new initiative of the GEF called the GEF-PAS (Global Environment 
Facility Pacific Alliance for Sustainability). The purpose of this Facility according to the GEF 
was to give Pacific Island countries better access and an equitable share of GEF resources. This 
new framework of delivery comes with a USD 100 million package that would fund a bundle of 
activities under the various thematic areas of the GEF, which includes climate change.   
7.
 
With this delay, and the push for bilateral access to the SCCF by Marshall Islands and 
Palau became difficult, they were then included as part of the PACC regional project. Although it 
meant adjustments and further enhancement of project documents, budgets et cetera, it was an 
important development, as all sovereign nations of the Pacific region with the exception of 
Kiribati
are now participating in the PACC project.  
8.
 
There was also a request by UNDP during this stage of the project to review the project 
foci due to developments at the GEF and Implementing Agency level on the issue of comparative 
advantages.  Therefore changes were made along the following: 
 
(a)
 
Recasting the PACC Prodoc into a capacity development and institutional strengthening 
type proposal; 
(b)
 
Infrastructure should not feature prominently in the Prodoc;  
(c)
 
Demonstration projects will still be entertained but to feature more as capacity 
development activities; and  
(d)
 
National reports, log frame etc. need to be aligned to the changes made to the Prodoc. 
D. Project Milestones 
9.
 
Below are the main project milestones from preparatory phase to submission of the full 
size project to approval. 
(a)
 
Submission of the PACC Executive Summary / Pipeline Entry – 1/04/2007 
(b)
 
Submission of the PACC Project Brief – 21/12/07 
(c)
 
Approval of the PACC Project Brief by the GEF Council – 21/04/08 
(d)
 
Submission of the PACC ProDoc – 11/09/08 
(e)
 
Approval of the Project Document (ProDoc) by the GEF Chief Executive Officer – 
15/10/08 
(f)
 
Duly signed ProDoc by the GEF CEO – 23/11/09 
(g)
 
Commencement of the PACC after 3 signatures (Pacific countries) – 23/01/09 
(h)
 
Inception Phase – 23/01/09 – 30/09/09 
(i)
 
PACC Inception Workshop – 29- 03/07/09 
(j)
 
Expected commencement of implementing activities on the ground – 01/10/09 
 
                                                 
1
 
Cook Islands, Fiji FSM, Nauru, Niue, PNG, Samoa, Solomon Islands, Tonga, Tuvalu and Vanuatu
 
2
Already implementing a bilateral adaptation project funded by the GEF through World Bank 
background image
 
II.
 
Inception Phase Review  
A. Purpose of the review 
10.
 
The main purpose of this section is to outline the various areas that have been covered by 
the review process and also the project design. This is important as it provides context to any 
changes that is adopted for the new project environment. It would be important to note also at the 
outset that the review process of the PACC project is not only limited to the first six months of 
the project but have been ongoing since the project was approved in October 2008.  
B. How was the review conducted 
11.
 
The review methodology included the following: 
(a)
 
Email discussion on institutional arrangements at the national and regional level; 
(b)
 
One-to-one discussion with PACC countries on project designs, institutional and 
implementation arrangements, implementing partners etc.; 
(c)
 
Pre-Inception Meeting discussion; 
(d)
 
Inception meeting deliberation; and 
(e)
 
PEG group discussions.  
C. Areas that were subjected for review 
12.
 
The following areas were subjected for review during the Inception Phase and the results 
are presented in this report: 
 
(a)
 
The institutional arrangements; 
(b)
 
Logical Framework 
(c)
 
The role and responsibility of various participants for achieving the project outcomes; 
(d)
 
Capacity needs 
(e)
 
The project management arrangements (organizational chart); 
(f)
 
The Monitoring and Evaluation (M&E) for the implementation of the project; 
(g)
 
The co-financing activities; 
(h)
 
Capacity of the NCs and Country Teams; 
(i)
 
Project Operation Manual (POM); 
(j)
 
Operational criteria for assistance; 
(k)
 
The project risks [what are the monitoring protocols]; 
(l)
 
An overall work plan for the first year of implementation; 
(m)
 
Disbursement of Project funds; 
(n)
 
Strategic linkages at the national and regional levels; and 
(o)
 
Specific issues raised during the Inception Meeting  
 
background image
III. Review Results 
13.
 
In this section, the results of the Inception Phase review are presented. Presentation of 
results will follow areas identified in section II (c) of this report.  
A. Institutional Arrangements 
(i) Regional Project Management Office (PMO) 
14.
 
The PACC Project document states that the PMO will be established and located in 
SPREP as part of its Pacific Futures Programme and will be responsible for the overall project 
operation and financial management and reporting of PACC in accordance with the rules and 
regulations for UNDP NEX projects. As part of the review process, further discussion was carried 
out at the national and regional level on this issue. The discussions conclude that the status quo in 
terms of institutional management arrangements be maintained for the duration of the project. 
The recommendation below provides the details. 
 
Recommendation(s) 
 
The current status and purpose of the PMO is to be maintained but enhanced with further 
support from other technical agencies such as the Secretariat of the Pacific Community 
(SPC) and other Partners. SPREP has been mandated by Pacific Leaders to be responsible 
for the issue of climate change at the regional and international level and should assist 
Pacific Island countries further address the issue at the national level. All other Regional 
Organisations such as the South Pacific Applied Geosciences Commission (SOPAC) and 
the Secretariat of the Pacific Community (SPC) have a role to play to address the 
technical aspects as their mandate requires. 
 
(ii) PMO Personals 
15.
 
In accordance with the PACC Project document, two positions are earmarked for the 
Regional Project Management Office (PMO). The two officers are a Regional Project Manager 
and a Project Management officer. The full-time RPM will be appointed by SPREP, funded by 
the project and based as a contracted staff member at SPREP. The Project Officer 
(Technical/Administrative Support position) is also earmarked to be employed by the PACC 
PMO and he/she will assume direct responsibility for the financial management of the PACC 
Project, under the supervision of the Regional Project Manager whilst also working closely with 
other UNDP/GEF and SPREP staff. He/she will also be appointed by SPREP, funded by the 
project and based as a contracted staff member at SPREP. 
 
Recommendation(s)  
 
These two positions are both needed for the PACC project’s successful implementation. 
As this report is being developed, the Regional Project Manager (RPM) for PACC has 
assumed his position at SPREP and he is Mr. Taito Nakalevu a Fiji citizen. His salary is 
fully funded by the project and is already based at the Pacific Futures programme of 
SPREP as a contracted staff member;  
 
As part of the SPREP and UNDP arrangements, SPREP will provide administrative, 
logistical and technical support for the Regional Project Manager (RPM) in order to 
effectively establish a PACC PMO.  
background image
 
SPREP should be able to recover their administration costs through a cost recovery 
formula
3
 already worked out between the SPREP and UNDP. 
 
(iii) Regional Oversight Mechanism 
16.
 
There are two mechanisms in place that will provide oversight to the PACC project. 
From a management and technical aspect of PACC; a Project Executive Group or PEG is being 
established that will monitor the conduct of the project and provide strategic guidance and 
direction to the implementation of PACC at the national and regional levels. Due to the difficulty 
in transportation and communication in the Pacific region, it was discussed and agreed that the 
following PEG composition is adopted for PACC; 3 Country representatives (1 per sub region), a 
UNDP representative (Samoa MCO), SPREP and 1 representative of CROP agencies. 
17.
 
The second oversight mechanism is the Pacific Climate Change Roundtable. This is a 
forum at which all stakeholders addressing climate change meet and keep everyone abreast of 
each other’s activities in the area of climate change mainstreaming, mitigation or adaptation as 
well as on the international negotiations. SPREP coordinates the meeting and it is attended by 
Pacific Island Country representatives, donors and other interested parties, NGOs, et cetera that 
have and interest and activities on climate change. SPREP in 2008 revived the Climate Change 
Roundtable meeting for the Pacific region. The 2009 meeting was held in Majuro Marshall 
Islands on the 19
th
 to the 23
rd
 of October. 
 
 Recommendation(s) 
 
That the coordination of PACC at the regional level be through the PACC PEG and the 
current PEG members as presented at the conclusion of this report be confirmed; 
 
That the PACC project should use the Pacific Roundtable as an opportunity to share 
information, progress and lessons on the PACC project and build new partnerships. 
 
(iv) National Implementation Arrangement 
18.
 
Implementation at the national level will be guided by a Climate Change Country Team 
(NCCCT). The Country Team approach at the national level is based on the awareness that to 
effectively tackle cross sectors issues like climate change there is a need to bring together many 
actors from different crosscutting thematic areas. Most countries already have NCCCTs and it 
would be a yoke to an already stretched manpower and resources to establish a separate PACC 
National Coordinating mechanism.  
19.
 
Described in some detail below the administrative set-up of the PACC project at the 
national level and agreed arrangements. 
 
(v) National Climate Change Country Team and Project Management Unit 
20.
 
Implementation of project activities at the national level will be based on the “country 
team” approach, which is now a standard practice in many PICs. However, some countries are 
very progressive in that regard whilst some do lag behind and need strengthening. It was agreed 
during the Inception meeting that wherever possible, existing country teams are utilised but 
                                                 
3
 Time of SPREP professionals contributing directly to the PACC implementation will be worked out and costed as per   
salary scale.
 
background image
reviewed on their membership with the view to include appropriate stakeholders that can 
contribute effectively to the implementation or monitoring of the project.  
21.
 
On the whole, thirteen (13) multi-sectoral National Climate Change Country Teams 
(NCCCTs), will provide oversight and approve work programmes and budgets for the 
implementation of project activities at the national level in each of the 13 countries. In addition to 
the NCCCTs, a Project Management Unit (PMU) will be established within each of the National 
PACC implementing agencies (NPIA). In all cases the NPIA will be physically located in a 
government department i.e. the Ministry of Environment, Meteorology, Public Works or Utilities 
and Infrastructure. 
 
(vi) The National PMU 
22.
 
 The National PMU will comprise a Project Manager/National Project Coordinator for 
PACC (NPM/NPC) who will work full time on the project and will be fully paid by the project. 
The NPM/NPC, among others, will be responsible for the day-to-day management and 
implementation of all national project activities. The PMU will serve as a secretariat to the 
NCCCT on matters relating to PACC project implementation. An update of the PACC 
Coordinators is included as an annex to this report. 
23.
 
Most of the project activities will be conducted at the national level, implementing on-
the-ground activities, utilizing national experts and involving as much as possible the 
communities in which the project activities will be implemented. This will enable the project to 
have greater impacts and heightened visibility not only within the specific communities/villages 
but also at the national and regional levels. Additionally, use of local/national expertise and local 
communities in project implementation will ensure national ownership of the project to maintain 
the impetus for long-term sustainability. 
 
 Recommendation(s) 
 
That the current NCCCT wherever possible should also act as the PACC national steering 
committee and ensure that all relevant professionals from government, non-government, 
and civil society and community organisations who are involved in managing, 
coordinating and implementing the in-country activities carry out their role accordingly; 
 
There it is not possible to action the above recommendation, then a separate PACC 
Steering Committee is established; 
 
That a review is undertaken on the composition of the county team to ensure all 
appropriate stakeholders that can contribute effectively to the implementation or 
monitoring of the  PACC project are included as part of the NCCCT. 
B. Logical Framework 
24.
 
The PACC logical framework was discussed at length during the Inception Meeting 
(Annex I). Countries made changes or accepted current wording after reflecting on contemporary 
situation at the national level. The general agreement was that the log frame is workable and with 
a careful review of wording and indicators, it should be robust to work with. Two further 
proposals were also discussed; the first is the inclusion of a project management outcome to 
address project management outputs at the national level and the second is to also feature policy 
development/incorporation either as a separate output or incorporated into either of the two 
existing outputs under outcome one. Current wording of the two outputs under outcome one 
background image
concentrate largely on tools development. It is the opinion of many during the workshop that one 
of the major roles of PACC is to enhance the systemic and institutional frameworks at the 
national level to ensure they are able to cope with changes that will be brought about by climate 
change. The development of guidelines on climate change adaptation is an important way to 
capture good practices and lessons learnt from the demonstration projects and to inform policy 
processes for the integration of CC resilience.  
 
Recommendation(s) 
 
 
That a project management outcome as reflected in the current log frame be endorsed; 
 
That the changes made to output one (1) under outcome one (1) to reflect climate change 
policy development and/or mainstreaming be accepted. 
 
C. Review of the role and responsibility of various partners 
 for achieving the project outcomes 
25.
 
Adaptation interventions will be successful when all the necessary stakeholders at 
national and local level are engaged during project implementation. In the PACC project 
document, the following partners listed below are identified and during the Inception meeting 
they were again endorsed to be critical for the success of the project: 
 
(i) Local Communities 
26.
 
Local communities are the most important stakeholders and partners of the PACC 
project. They range from village communities in a traditional setting with institutional structures 
such as provincial and local administrations in place. It also refers to non-village settings or ad 
hoc communal set-ups outside village boundaries sometimes called settlements. Different 
countries in the region have their own unique set-ups at the national and local level that would be 
difficult to detail in this report but are important to the project. 
27.
 
They are not only recipients of interventions but active partners in the decision making 
processes that lead up to the interventions to be implemented. They own resources which include 
the land, forest and the sea that the project will work in thus their inclusion from the outset is 
critical to the success of the project.     
 
(ii) Government Departments / Ministries 
 
28.
 
At the national level, government departments are critical stakeholders in the 
implementation of the project. Environment Departments given their role as PACC Focal Points 
also play that role for the PACC project whilst implementation is carried out by line ministries.  
  
(iii) University of Hawaii – [Hazards and Climate Programme] 
 
29.
 
The hazard and climate programme work closely with communities and governments 
particularly in the northern Pacific on the issue of socioeconomics of climate change. They have 
also taken part in the Inception and Technical Meeting of the PACC project. 
 
 
(iv) International Climate Change Adaptation Initiative (AusAID)  
 
background image
The AusAID International Climate Change Adaptation Initiative (ICCAI) programme will 
provide practical assistance to Pacific Island countries to adapt to the impacts of climate change. 
Various components of ICCAI provide useful inputs to the PACC project and vice versa, 
including the Climate Change Science Support Programme aiming at enhancing  climate 
projection and modelling capacities, the Pacific Adaptation Support Programme helping 
vulnerability assessment and adaptation planning, the Australia-Pacific Climate Adaptation 
Platform supporting knowledge management activities in the region, and the Mekong Asia 
Pacific-Community Based Adaptation (MAP-CBA) programme implemented through the UNDP 
Small Grants Programmes.   
 
(v) International Union for Conservation of Nature (IUCN) 
 
30.
 
Climate change is already altering the distribution of species and the make-up of 
ecosystems. To be effective, conservation practice must plan for the growing impacts of climate 
change. IUCN mobilizes research to measure the impacts climate change is having on 
biodiversity and to identify conservation and management solutions in line with the ecosystem-
based adaptation approach. For example, connecting habitats has a key role to play in enabling 
nature to adapt to the impacts of climate change. Further, ecosystems can store carbon and 
maintain the critical ecosystem services on which livelihoods depend on. Lessons learnt from the 
work they carry out will be of importance to the PACC project.
 
 
 
(vi) South Pacific Applied Geosciences Commission 
 
31.
 
SOPAC is implementing another regional project called the Integrated Water Resources 
Management (IWRM), and linkages and complementarities have been mapped out, especially in 
the PACC project countries that address water sector to support mainstreaming and demo 
activites 
 
(vii) Secretariat of the Pacific Community 
 
32.
 
Cover most sectors, health marine, maritime, social health, land resources and PACC 
countries can work with them to screens crops for tolerance to extreme conditions (heat, drought, 
etc).  Can access and outsource materials from outside region, from international agricultural 
research centers. SPC currently has the Centre of excellence for atoll agriculture in Kiribati that 
helps to look at the effective use of atoll soil techniques for agriculture. 
 
(viii) University of the South Pacific 
 
33.
 
Deals with capacity building in the area of climate change and USP has collaborated with 
SPREP in the past on several projects such as the Pacific Islands Climate Change Assistance 
project (PICCAP), the Canadian funded Capacity Building for the Development of Adaptation 
Measures in Pacific Island countries (CBDAMPIC).  They currently implement several climate 
change projects which include the EU grant, 0.57million euros – UPNG, NUS, EDULINK 
program; AusAID community adaptation project, and are proposing a 1.68millino AUD to fund 
courses – climate leaders program, part of ICCAI. 
 
(ix) United Nations Institute for Training and Research  
 
34.
 
SPREP is participating in the C3D+ project/platform and the objective of the platform is 
to promote dialogue, increase capacity, contribute mainstream especially to other countries. 
background image
Before Africa and Asia benefited from the platform but now Pacific through SPREP and the 
Caribbean through the Caribbean Climate Change Centre (CCCC).  Partners that are now part of 
the C3D+ partnership include the following; SEI – Stockholm Environment Institute, IISD – 
International Institute for Sustainable Development, Partners – SEI Oxford and MIND Sri Lanka. 
These partners have expertise in Vulnerability & Adaptation Assessments, Sustainable 
Development mainstreaming, and climate change modeling.  Tools that C3D+ partners have 
developed that are now used widely around the globe include the Climate Change Explorer, 
WeAdapt and CRiSTAL.   
 
(x) European Commission – Global Climate Change Alliance (GCCA) 
 
Linkages can be created with GCCA through the country pilot projects (e.g. in Vanuatu), 
as well as the Capacity Building Programme being implemented through USP, aiming at 
supporting adaptation levels at the community level. 
 
(xi) Foundation of the Peoples of the South Pacific International (FSPI) 
FSPI can provide support especially for the community-level adaptation activates of 
PACC, e.g. the areas of reef restoration, ICZM, food security, sustainable tourism, 
community business management (financial accountability support programme)
 
 
Recommendation (s)  
 
That the role of each partner in the PACC project as outlined above be approved. 
 
D. Review of the project management arrangements  
(organizational chart) 
35.
 
Discussion with countries prior and during the Inception Workshop has yielded no 
change to project management arrangements as detailed in the PACC project document therefore 
current arrangements as detailed in Annex II will be the modus operandi used by PACC during 
implementation period. 
36.
 
At the operational level, the implementation of the PACC will be based on 13 individual 
PIC-specific 5 years work plan and budgets. If feasible, economical, practical, etc common 
activities among PICs will be undertaken regionally. The 13 work plans and budgets will be 
revised at least once a year (or more if a need arise). Each PIC will review its work plan and 
budget through its PACC NCCT and submit to the PEG at least a month before the annual TPR 
meetings. The PEG will then review these submissions, taking into consideration the agreed to 
operational criteria and make the appropriate recommendations to the TPR meeting. 
 
E. Review of the project Monitoring and Evaluation (M&E) 
 
37.
 
Monitoring and evaluation of the PACC project will be conducted in accordance with 
UNDP and GEF procedures. The Logical Framework Matrix in Section II provides performance 
indicators for project implementation along with their corresponding means of verification. These 
will form the basis on which the project’s Monitoring and Evaluation system will be built. 
38.
 
The PACC Project was approved with indicative activities per 13 PIC. These activities 
were reviewed and updated as part of the Inception meeting and national consultations 
undertaken during the Inception Phase. The very significant time lag between initial project 
background image
design and actual implementation was a critical basis for review. In addition the co-financing 
activities were reviewed and updated as well.  
 
Recommendation(s) 
 
That the PACC M & E Framework, as in Annex III be approved.  
F. Review of co-financing activities 
39.
 
All PACC countries except Cook Islands again confirmed their co-financing 
arrangements during the Inception Meeting. In the case of the Cooks, their baseline development 
activity (upgrade of Manihiki Airport) had to be rescinded as the latter activity had progressed 
minus the PACC project. The delay in the approval process of the project impacted negatively in 
this case on the co-financing situation thus effort to review the situation was undertaken 
immediately after the Inception Meeting by the Ministry of Infrastructure and Planning.   
40.
 
Prior to the finalisation of this report, communication was received from the Cook Islands 
that their new pilot site would be Mangaia and the PACC project would support the 
redevelopment of the Mangaia Harbour (see Plate 1&2 below).  
 
 
Plate 1      Prior to 2005                                                                                 Plate 2  March 2005 
 
 
 
41.
 
The choice for Mangaia was made after the recent decision of the government of Cook 
Islands to allocate NZ$1.8 million to the Mangaia Harbour redevelopment programme (2009-
2010). The PACC project will try and address the broader issue of coastal management that is 
plaguing the harbour. For example, after heavy seas the coral gravels used to temporary form the 
dock quay would be washed away into the lagoon leaving behind the rough coral flat as seen in 
plate 2 above. Stop-gap measures attempted in the past by the Island Administration would be to  
temporarily re-fill, repair and re- compact the quay with new gravel every time the outer island 
freighter services the island. Hopefully, the intervention by the PACC project would ensure that 
service and operations continues on the island without disruption thus providing an avenue for 
background image
people to receive required essential services to the islands or evacuate people in terms of 
disasters. Both ways, the work will significantly increase the capacity of the people of Mangaia to 
face changes in climate and extreme events. 
 
 Recommendation 
 
That the co-financing sources and partners to the PACC are noted and their support 
acknowledged (Annex IV).   
 
G. Capacity of the National Coordinators and Country Teams 
42.
 
The capacity of the national coordinators and the Country Teams to effectively 
coordinate and manage PACC were discussed and reviewed at the Inception Meeting and national 
Inception meetings. The PMO is of the view that the Country Teams are made up of highly 
qualified, experienced and committed officers but need to have their capacity built on the PACC 
project.  
43.
 
Current PACC National Coordinators are qualified in terms of university degrees but do 
lack specific climate change knowledge and experience. Most do not have project environment 
exposure and hands-on project coordination experience, thus some further operational support 
will need to be done to get them through the initial phases of the project.     
44.
 
During the Inception Meeting, a capacity needs survey was carried out for the 
participants. Several areas such as enabling environment, institutional arrangements, capacity of 
project personals, project management and logistical and technical support needs were reviewed 
using a questionnaire. 
45.
 
Results of the survey suggest that 61% have indicated that no sector policy
4
 is a critical 
issue that needs to be addressed very early in the project whilst only 15% suggested otherwise. 
Two ways of interpreting this result; either there are no water, food security and coastal 
management sector policy in place and need to be developed under the PACC or there are 
policies in place but have not incorporated climate change as part of the policy. In that regard, 
further assessment will need to be undertaken at the national to determine these different nuances. 
46.
 
In the institutional theme, processing of funds (53%) was identified as a critical area that 
needed immediate attention.  Another area that needed to be addressed very early is how to 
maintain trained personals as they are crucial to the implementation of the project. Most countries 
(69%) noted that recruiting and retaining a project coordinator was an issue that needed 
rectification very early in the project. Some countries do find it difficult to recruit the right 
personals to coordinate the project and in some cases when recruited, turn over is high as they 
proceed to so-called “greener pastures”.  
47.
 
Results for the Project management (77%) showed that many workshop participants are 
not familiar with the Log frame and that it needed to be addressed very early in the project. This 
result is not surprising to the regional PMO as those present during the Inception Meeting were 
not involved in any way in the project preparation phase. Nevertheless, the results have provided 
a good baseline understanding of situations on the ground in terms of project management, 
                                                 
4
 Sectors referred to here are water, coastal and food security. 
background image
institutional support and capacity enhancement of individual coordinators. It should be followed 
up with concrete interventions very early in the life of the project. 
 
Figure 1.0 Survey result on enabling environment (sector policy) 
 
 
 
 
 
 
 
 
 
 
                   Note: Not to be quoted              
48.
 
The Inception Workshop was also a first opportunity to start addressing the baseline 
situations mentioned above. The Coordinators were introduced to the project cycle management; 
a typical GEF/UNDP project implementation cycle that included reporting and project 
management requirements (budgetary planning and budget reviews). Participants also spent a half 
day reviewing their log frame after introductory presentations by UNDP advisers. 
 
Recommendation(s)  
 
That the capacity of the national coordinators and country teams and their capacity 
building needs be noted and acted upon. 
H. Project Operation Manual (POM) 
49.
 
A PACC National Execution Modality (PACC NEX) was developed during this quarter, 
which mirrored very closely the UNDP NEX. After inputs and comments to the document were 
made by UNDP, the PACC NEX was shared with the PACC countries prior and during the 
Inception Meeting for their comments. At present, this document is the first source of information 
at the national level for the PACC Focal Points, Implementing Agencies and incoming National 
Coordinators. 
 
I. Operational criteria for assistance including allocation of funds  
to individual countries as part of the project 
50.
 
The PACC project by design (paragraph 3) is closely linked to national level sustainable 
development and poverty reduction strategies. It provides additional resources for national 
governments to address climate change issues in the design of their development programmes to 
background image
ensure resilience to current and future changes in climate. Therefore, co
-
financing activities from 
governments or overseas development assistance provide the baseline programme targeted 
towards the achievement of sustainable development whilst PACC activities provide the 
additionality provisions to address climate change adaptation. By default, the GEF guidance 
nullifies the notion that all countries should have equal sharing of the GEF resources.  
51.
 
During the preparatory phase of the project, funding allocation for each country presented 
by the PACC preparatory team
5
 during national consultation workshops were strictly based on the 
following criterias; a) most vulnerable sector; b) prior assessment already undertaken on the most 
vulnerable sector; c) baseline development activity; d) co-financing opportunity/ability. After 
national consultation and progress of project design, it was realised that the smaller countries that 
were very vulnerable to climate change impacts had very little co-financing available to them. It 
was the geographically bigger PICs that had co-financing potential.  
52.
 
SPREP was notified by UNDP that it needs to solicit more co-financing as some of the 
smaller PICs were not able to raise enough co-financing. Such a regional scenario required a 
regional solution. Measures that the project management team consciously made included 
requesting two countries; Fiji and FSM to assist with co-financing shortfall for the overall project. 
Fiji in turn provided USD8 million and FSM USD 6 million. These were development activities 
that were linked to the PACC project in these two countries. With this support, they were 
allocated USD 1 million each from the PACC budget. Four countries were given USD800,000 
(Cook Islands, Marshall Islands, Palau and PNG) and seven countries were allocated 750,000 
each (Nauru, Niue, Samoa, Solomon Islands, Tonga, Tuvalu and Vanuatu). The seven countries 
that were given USD75,000 had difficulties raising their co-financing thus as the project 
progresses, there is a need to continue to better define the co-financing support from these 
countries vis-à-vis other GEF supported projects. 
53.
 
The allocations indicated above are indicative and it was made known to country 
representatives that were present during the Inception Meeting. These measures are undertaken to 
ensure that funds are not withheld unnecessarily by countries that for some reason are not able to 
spend their allocation accordingly. It is to be noted that this amount may change based on 
delivery of resources and results as per the approved annual work plans.     
 
 Recommendation(s)  
 
That the PACC NEX be used as the guiding document for national project 
implementation at the national level.   
 
J. An overall work plan for the first year of implementation 
54.
 
A work plan for the 2009 calendar year was developed and submitted to UNDP on the 
last week of third week of August (third quarter). It was subsequently discussed by the PACC 
PEG members at the 17
th
 of August for the purpose of approving the work programme.  
55.
 
A review of the 3
rd
 quarter funding distribution suggests that most activity in the third 
quarter will largely focus on project management. This includes office set-up, recruitment of 
coordinator, communication strategy development et cetera. Nauru, Tonga and Tuvalu have 
budgeted for Component One. FSM and Fiji are planning to carry out some Component Two 
activities during this quarter. Table 1.0 below provides a breakdown of funding per component 
for the 3rd quarter. 
                                                 
5
 Taito Nakalevu (SPREP), Ms Misa Andriamihaja (UNDP) and Dr. Graham Sem (Consultant) 
background image
Table 1.0 Total Projected 3
rd
 Quarter Funding 
FUNDING IN COMPONENTS 
TOTAL 
Component 1: Mainstreaming 
50,000 
Component 2: Guideline and Demonstration 
36,600 
Component 3: Technical Support and Lessons 
Learnt 
1,000 
Project Management 
251,928 
Total 
339,528 
 
56.
 
Bulk of the 4th quarter activity and funding requested are on component One and Two. 
This reflects progress at the national level from setting up to addressing the more technical issues 
of Mainstreaming and Vulnerability and Adaptation Assessment. Several countries are now 
working on reviewing/analysing their sector specific policy. In the case of Solomon Islands and 
Niue, they will be developing a climate change policy using PACC resources. Solomon Islands 
has also able to secure additional resources from the Euroupean Union to assist in the climate 
change policy development work. The table 2.0 below provides the total projected 4th Quarter 
funding per component. 
 
Table 2.0 Total Projected 4th Quarter Funding 
Funding in components 
Total 
Component 1: Mainstreaming 
181,000 
Component 2: Guideline and Demonstration 
276,300 
Component 3: Technical Support and Lessons 
Learnt 
3,000 
Project Management 
94,172 
Total 
554,472 
 
Recommendation(s)  
 
That the status of the individual PIC work plan and budget as well as the overall work 
plan and budget for the first year of on-the-ground implementation be noted.  
 
K. Disbursement of Project funds 
57.
 
UNDP will transfer funds to SPREP on a quarterly basis and in accordance to approved 
work plan. SPREP will then advance part of the funds to the PICs for the execution of national 
activities. At the end of the quarter, PICs report to SPREP who then reports to UNDP with a 
request for further transfer for the next quarter. Hopefully this will process will proceed smoothly 
as past projects have had mixed experiences on this. For many reasons, reports may not be 
prepared on time or incomplete, expenses are not accounted for and some funds get trapped in the 
local bureaucracies. This has then led to delays in the flow of project funds and project activities 
are held up.  
 
  
Recommendation(s)  
 
That the PACC advance project funds to countries and when requested direct payments 
be carried out, and  
 
That the effectiveness of the arrangement in the above recommendation be reassessed at 
the first TPR meeting in April 2010.     
background image
 
L. Strategic linkages at the national and regional levels 
58.
 
It is very crucial that the sustainability of the PACC be strengthened through strategic 
linkages at the national and regional levels. At the national level, PACC activities should be 
linked to adopted national policies, action plans and strategies, and ongoing national adaptation 
projects, such as the NAPA LDC Fund projects. For instance, Samoa’s NAPA is its national 
adaptation strategy in which the PACC is implementing its coastal ecosystem priority.  The 
development of the Climate Early Warning System (CLEWS) in its other NAPA LDC Fund 
Project
6
 links directly with the PACC.   PICs are currently preparing their Second National 
Communications under the United Nations Framework Convention on Climate Change where 
PACC activities are designed with the view to link these to the Vulnerability and Adaptation 
Assessment (V&A) part of SNCs.  Samoa for example has completed its SNC and is looking at 
building on the V&A studies from this enabling activity to further its activities under PACC.      
59.
 
At the regional level, it is important to report the PACC as a key intervention in the 
Pacific Plan’s initiative relating to the Pacific Islands Framework Action on Climate Change and 
the Pacific Islands Action Plan for the PIFACC.    
60.
 
At both levels, there is a need to ensure adaptation interventions developed in PACC is 
mainstreamed into the planning and budgetary processes.   
 
 Recommendation(s)  
 
 
That the need for establishing strategic linkages for PACC at both the national and 
regional levels as well as the need for mainstreaming be noted as a priority activity in 
PACC.  
 
PACC coordinators to be part of the SNC V&A Thematic Groups in order to ensure 
linkages and synergies with the SNC projects 
  
IV. Specific Issues raised during the Inception Workshop  
61.
 
The discussions focused principally on PACC issues, but most of them were much 
broader on the UNDP-country project and programming interface. References were made to 
administrative issues in other GEF processes (e.g. recruitment, salaries, advances and financial 
administration, etc.). It has been reiterated in various occasions that operational and financial 
issues are two-way processes between GEF-UNDP-Executing agency (SPREP)-countries, with 
the need for the countries to sort out their internal coordination and communication between the 
project line ministries and the finance departments, treasuries, cabinet and other financial 
management procedures. UNDP reiterated its adherence to the Paris Principles on Aid 
Effectiveness, therefore the alignment of its financial management with national procedures (the 
need for national project counterparts to follow routes and procedures established by 
corresponding financial departments). UNDP will make available funds for countries through 
SPREP as soon as possible, but national implementing agencies have to sort out national 
arrangements and coordinate duly with their Finance Departments to actually get hold of funds, 
ensuring bottlenecks are not occurring at the national level.  
                                                 
6
 Samoa’s NAPA LDC Fund project is the 2009-2014 ICCRAHSS project – Integrating Climate Change 
Risks in Adaptation and Health Sector Samoa.  
background image
62.
 
Receiving and administering financial advances: various countries raised issues with the 
quarterly advance practice for project staff salaries and other purposes. For instance, Federated 
States of Micronesia needs a full year’s salary to be downloaded at once due to procedural issues 
between national and state governments. Addressing questions on slippages and roll over of 
quarterly advances; it was clarified that unspent funds can be rolled over to next quarter but 
disbursement will only be made when the 80% expenditure is proved. UNDP will also be closely 
involved in monitoring and assisting countries in the preparation of their quarterly and annual 
reports. National coordinators play a very critical role at the national level as responsibilities for 
supervising consultants, approve payments, provide information through quarterly narrative and 
financial reports will ensure that constant communication with the regional project office is 
maintained. 
63.
 
Options to fasten disbursement of funds: Several options were discussed and one that 
was taken up was for SPREP to make available to countries “Start-Up”fund of USD10,000 to 
quickly facilitate the establishment of a project management unit at the national level. Also, to 
avoid loss and confusion of exchange rates to be used, SPREP will be downloading funds to 
PACC countries in US dollars. Exchange to national currency will be made at the national level 
thus one rate will be used by countries and SPREP. It was also agreed that if so decided by 
countries; SPREP can make direct payments to consultants on their behalf.   
64.
 
Use of the new FACE form: it was introduced to harmonize the financial payment and 
reporting procedures (aligned to Paris Declaration). UNDP gave a short briefing on the Face form 
and provided an information package on its use with examples. It was also agreed that national 
UN Country Development Managers would be able to assist countries with the Face forms if 
requested. UNDP is also keen to take up further training of the financial reporting during joint 
country missions. 
65.
 
Vehicle purchase: it has been clarified that GEF project budget can be used to facilitate 
transport for project operations (e.g. vehicle, boat rental), but cannot be used to purchase vehicle. 
This can be sourced from co-financing.  
66.
 
Sourcing, contracting and retention of country project staff: countries raised the issue 
of lack of qualified persons for project management, leaving often limited options to draw in new 
staff and need to use already existing government staff. The post-project retention of project staff 
is also an issue. Recommendation was made to second qualified government staff to the project, 
retaining his/her post throughout the project, allowing re-insertion after the project. It was 
underlined by UNDP that project funds cannot be used to subsidize regular government salaries, 
however, different countries face different situations and such a situation need to be examined on 
its own merit. It was agreed that a no size-fit-all solution can address the unique situations each 
country faces.  
67.
 
Communication: with GEF and UNFCCC Focal Points, UN Ambassadors, other national 
and regional stakeholders: the need for the national coordinators to regularly inform these 
national constituencies on PACC progress was reiterated on various occasions. The PACC 
Snapshots (regular updates prepared by SPREP in collaboration with UNDP) will be sent to these 
persons. It was advised to set up an email communication group by the countries for this purpose. 
SPREP will assist countries through the inception phase to draw up national communication 
strategies addressing these issues. 
 
background image
V. Progress and Next Steps 
 
68.
 
The PACC Inception Phase is now completed and there are already some tangible 
progress made at the national and regional level. Below in summary form are some of the 
achievements to date.
 
 
Memorandum of Understanding 
69.
 
All the PACC countries have signed their MoU with SPREP. This MoU together with the 
PACC project document embodies the entire agreement between the countries and SPREP 
regarding the implementation of the programme at the national level.  The MoU declares the 
intention and commitment of the Government of the Federated States of Micronesia and SPREP 
to work together in pursuit of the common and expected goal, outcomes and outputs of the 
project. 
                                               Table 3.0 MoU Signatures                 
COUNTRY NAME 
SIGNED ( ) 
1. Cook Islands 
 
2. Fiji 
 
3. Federated States of Micronesia 
 
4. Marshall Islands 
 
5. Nauru 
 
6. Niue 
 
7. Palau 
 
8. Papua New Guinea 
 
9. Samoa 
 
10. Solomon Islands 
 
11. Tonga  
 
12. Tuvalu 
 
13. Vanuatu 
 
 
Institutional Arrangement at the National Level 
70.
 
The implementation of the PACC pilot project vary among participating countries but 
essentially divided into five broad areas.  
 
Table 4.0 Institutional Arrangement 
SPREP Focal Point 
Foreign Affairs or Government Environment 
Agency 
SPREP Operational Focal Point 
Technical contact for all SPREP activities 
PACC Focal Point 
Technical contact for PACC 
Lead Agency 
Sub-contracted Government agency responsible
for pilot project implementation as described in 
a Letter of Agreement exchanged with the 
PACC Focal Point 
Executing Agency 
NGO or community group responsible for pilot 
project execution as described in a Letter of 
Agreement exchanged with the Lead Agency 
and the PACC Focal Point. 
background image
71.
 
The primary point of contact for the PACC in each participating country is the designated 
SPREP Focal Point.  The SPREP Focal Point is usually the Government ministry responsible for 
foreign affairs or the Government environment agency.  It takes responsibility for policy issues 
associated with SPREP’s activities in the region and nationally.   
72.
 
SPREP-supported activities in each of its member countries may be promoted through an 
Operational Focal Point, a Government Agency designated to be responsible for technical issues 
associated with SPREP’s work programme.   
73.
 
Some participating countries may elect to designate the Operational Focal Point as the 
PACC Focal Point (PACCFP).  In such cases, the PACCFP may assume responsibility for all 
administrative and logistical issues associated with pilot project implementation and actually 
execute the pilot project.  In such situations, the PACCFP, the Lead Agency and the Executing 
Agency would be the same agency. 
74.
 
However, there are other cases where the local implementing agency may not be the 
PACCFP.  For example, the PACCFP may choose to delegate responsibility for pilot project 
implementation to another government agency (for example the Department of Public Works in 
respect of a road relocation pilot project).  In cases where this is instituted the implementing 
agency, the Department of Public Works, would be referred to as the Lead Agency.  The 
relationship between the PACCFP and the Lead Agency in respect to the pilot project would be 
stipulated in a Letter of Agreement signed by the head of the respective agencies. 
75.
 
The Lead Agency, whether that be the PACCFP or an alternative government agency, 
may actually execute the pilot project, in which case it would also be the Executing Agency.  
However, it may also elect to delegate responsibility for execution of the pilot projects to another 
organisation, for example a non-government organisation or a community group.  In such 
instances, the organisation or group responsible for execution would be known as the Executing 
Agency.  The relationship between the Lead Agency and the Executing Agency in respect to the 
pilot project would be stipulated in a Letter of Agreement signed by the head of the Lead Agency, 
the head of the Executing Agency and the head of the PACCFP. 
 
 
 
 
background image
Table 5.0 Institutional Arrangement at the National Level 
 
COUNTRIES 
SPREP OPERATIONAL 
 FOCAL POINT
7
 
PACC FOCAL  
POINT
8
 
LEAD AGENCY
9
 
EXECUTING 
AGENCY
10
 
Cook Islands 
Director 
National Environment Service 
PO Box 371 
RAROTONGA Cook Islands 
Ministry of Infrastructure and 
Planning and Outer Island 
Affairs 
MOIP 
MOIP 
Federated States 
of Micronesia 
Office of Environment and 
Emergency Management 
Palikir 
Pohnpei 
FSM 96941 
Office of Environment and 
Emergency Management 
Palikir 
Pohnpei 
FSM 96941 
Kosrae Island 
Resource 
Management 
Authority 
Public Works 
Fiji 
Director of Environment 
Department of Environment 
PO Box 2109 
Government Buildings 
SUVA, Fiji 
Director 
Land and Water Resources 
Division, Ministry of 
Agriculture 
Land and Water 
Resources 
Division, Ministry 
of Agriculture 
Land and Water 
Resources 
Division, Ministry of 
Agriculture 
Republic of the 
Marshall Islands 
Director 
Office of Environmental Planning 
and Policy Coordination (OEPPC) 
PO Box 975 
MAJURO 96960 
Director 
Office of Environmental 
Planning and Policy 
Coordination (OEPPC) 
PO Box 975 
Office of 
Environmental 
Planning and 
Policy 
Coordination 
R and D 
EPA 
MWSC 
EPPSO 
 
                                                 
7
 Technical contact for all SPREP activities 
8
 Technical contact for PACC 
9
 Sub-contracted Government agency responsible for pilot project implementation as described in a Letter of Agreement exchanged with the 
PACC Focal Point 
10
 NGO or community group responsible for pilot project execution as described in a Letter of Agreement exchanged with the Lead Agency and the 
PACC Focal Point.
 
background image
Republic of the Marshall Islands 
96960 
MAJURO 96960 
Republic of the Marshall 
Islands 96960 
(OEPPC) 
 
 
Niue 
Director for Environment 
Department of Environment 
PO Box 80, ALOFI, Niue 
Director for Environment 
Department of Environment 
PO Box 80, ALOFI, Niue 
Public Works 
Department 
(Waters Division) 
Public Works 
Department (Water 
Division) 
Nauru 
Secretary for Foreign Affairs 
Department of Foreign Affairs 
Republic of Nauru 
Central Pacific 
Department of Commerce, 
Industry & Environment 
 
 
 
Nauru 
Rehabilitation 
Corporation 
Nauru 
Rehabilitation 
Corporation 
 
Palau 
Office of Environmental Response 
& Coordination 
Office of Environmental 
Response & Coordination 
Office of 
Environmental 
Response & 
Coordination 
Ngatpang Maritime 
Authority 
Papua New 
Guinea 
Department of Environment & 
Conservation 
Department of Climate 
Change and Mitigation 
Land Use 
Division, Ministry 
of Agriculture 
Land Use Division, 
Ministry of 
Agriculture 
Samoa 
Chief Executive Officer 
Ministry of Natural Resources and 
Environment 
Private Mail Bag, APIA, Samoa 
Climate Change Section 
Meteorology Department 
Apia, Samoa 
 
 
 
Climate Change 
Section 
Meteorology 
Department 
Apia, Samoa 
Ministry of Natural 
Resources and 
Environment 
 
Solomon Islands 
Permanent Secretary 
Ministry of Environment, 
Conservation and Meteorology 
HONIARA, Solomon Islands 
Permanent Secretary 
Ministry of Environment, 
Conservation and 
Meteorology 
HONIARA, Solomon Islands 
Ministry of 
Agriculture and 
Livestock  
Ministry of 
Agriculture and 
Livestock  
Tonga 
Secretary for Lands, Survey, 
Natural, Resources & 
Environment 
Ministry of Lands, Survey & 
Department of Environment, 
Ministry of Lands, Survey & 
Natural Resources 
PO Box 5 
Department of 
Environment and 
Natural 
Resources 
Department of 
Environment and 
Natural Resources 
background image
Natural Resources 
PO Box 5, Nuku’alofa, Tonga 
Nuku’alofa, Tonga 
Tuvalu 
Director  
Department of Environment 
Private Mail Bag 
Vaiaku, Funafuti, Tuvalu 
Director  
Department of Environment 
Private Mail Bag 
Vaiaku, Funafuti, Tuvalu 
Public Works 
Vaiaku 
Funafuti 
Tuvalu 
Public Works 
Vaiaku 
Funafuti 
Tuvalu 
Vanuatu 
Head Environment Unit 
Private Mail Bag 9063 
PORT VILA  
Vanuatu 
Vanuatu Meteorological 
Services, Ministry of 
Infrastructure and Public 
Utilities, PMB 9052, Port 
Vila, Vanuatu 
 
Department of 
Public Works and 
Infrastructure 
Department of 
Public Works and 
Infrastructure 
 
 
background image
Coordinators 
76.
 
Currently, six PACC Coordinators have been recruited/appointed whist seven other 
countries have their processes in motion. Every effort is being made at the regional level to see 
how best the countries can be assisted to find a good Coordinator which has been difficult for 
some. 
 
Table 6.0 PACC NATIONAL COORDINATORS 
Country 
Name 
Telephone 
Email 
Cooks 
*Mr. Otheniel 
Tangianau 
+682-20034 
otheniel@moip.gov.ck 
 
Fiji 
*Mr. Kyaw Win 
+675- 
kwin@govnet.gov.fj 
kyawwin1@gmail.com 
FSM 
*Mr. Simpson 
Abraham 
+691-320-
8815/8814 
sdplanner@mail.fm 
Marshalls 
*Mr. Warwick Harris 
+692-625-7944 / 
7945 
warwick47@gmail.com 
Nauru 
Ms. Mavis Depaune 
+674-444 3133 
monmave@gmail.com 
naoerowoman@yahoo.com 
Niue 
Mr. Haden Talagi 
+683-4021 / 4011
h_talagi@mail.nu / 
environment.ca@mail.gov.nu 
Palau 
Mr. Rhinehart Silas 
+680-67 1269 
rsilas@palaugov.net 
PNG 
Mr. Andrew Mika 
+675-3402175 
 
Samoa 
Ms Moira Faletutulu 
+685-23800 ext 
19 
moira.faletutulu@mnre.gov.
ws 
Solomons 
Ms Jean Galo 
+677-24074 
dzinnieb@yahoo.com.au 
Tonga 
*Mr.Lisiate Bloomfield   
 
Tuvalu 
Ms Tausi Loia 
+688 20826 
lmolipi@gov.tv 
puavasa@gmail.com 
Vanuatu 
Mr. Denis Alvos 
+678-
22555/22888 / 
7757243 
dalvos@vanuatu.gov.vu 
            * Acting Coordinators [for now] until PACC Coordinator positions are finalized in their respective countries. 
 
Project Executive Group Members 
 
77.
 
A meeting of the PEG was undertaken and UNDP Apia multi-country office was 
reaffirmed to be the chairperson of the PEG to ensure consistency in meeting proceedings.  
78.
 
Mr. Taito Nakalevu the PACC Regional Project Manager was confirmed as the 
secretariat. The two positions would remain for the duration of the project until or unless 
circumstances warrant a change. 
 
Membership 
79.
 
The meeting affirmed the following as the incumbent members of the PACC PEG. They 
will be representing their sub-groupings for a period of one year after which new representation 
will be reviewed. 
 
[i] Melanesia: Mr. Jope Davetanivalu; 
background image
 
[ii] Micronesia: Mr. Abraham Simpson 
 
[iii] Polynesia: Ms. Anne Rasmussen  
 
[iv] CROP Representative – Mr. Marc Wison (IWRM Project Manager) 
 
[v] SPREP - Mr. Espen Ronneberg 
 
PACC Communication 
 
80.
 
A medium of communication called the PACC Snapshot was developed for the PACC. 
The purpose is to bridge the divide between the regional PMU based at SPREP and national 
PACC Coordinators. This communication is. Four Snapshots went into circulation this quarter 
detailing issues ranging from; i) reporting requirements, ii) Annual Work Plans; iii) Start-Up 
Funding; iv) Memorandum of Understanding and Project Executive Group. 
81.
 
A PACC website has also been developed and will continue to be upgraded to assist in 
communicating PACC regionally and beyond. The PACC official website address is: 
http://www.sprep.org/climate_change/paccc
 
 
 
Next Steps 
82.
 
The milestones below were developed collaboratively during the Inception Meeting with 
all PACC countries taking into consideration the three main outcomes of the project as stipulated 
in the Project Document. 
                                                        
Table 7.0 Milestones for 2009
 
MILESTONES FOR 2009 
I. 
Signing of the Memorandum of 
Understanding between SPREP and 
Countries; 
II. 
Start-up funding made available to 
countries; 
III. 
Set-up of Project Management Units; 
IV.  Recruitment of the National PACC 
Coordinator carried out; 
V. 
Set-up of National Steering Committee 
VI. 
PACC Technical Meeting 
83.
 
Based on current progress, most of the milestones are on target to be achieved. However, 
challenges may be faced by countries in the recruitment of National PACC Coordinators due to 
the limited availability of qualified people at the national level.  
84.
 
The table below outlines some tangible steps being undertaken by the regional PMU 
based at SPREP to address some of the specific issues raised in the Inception Meeting and 
highlighted in Section IV of this report.  
85.
 
More detailed information on progress that has been made at the national level is 
included as Annex V of this report. 
background image
Table 8.0 Issues raised in the Inception Meeting and action taken 
Issue 
What has been done 
Further Action 
Receiving and administering 
financial advances: Federated 
States of Micronesia needs a 
full year’s salary to be 
downloaded at once due to 
procedural issues between 
national and state 
governments. 
UNDP and SPREP in their 
discussion have agreed that FSM 
could be assisted in their request. 
SPREP will transfer funds to 
country level in USD rather then 
local currency to ease reporting 
particularly exchange rates to be 
used. 
Monitor and action any 
request particularly the need 
for Appropriation - a 
requirement in FSM 
financial systems. 
Options to fasten disbursement 
of funds 
“Start-Up”fund of USD10,000 to 
quickly facilitate the 
establishment of a project 
management unit at the national 
level. 
 
Use of the new FACE form 
Continuous training is being 
carried out and recently in the 
PACC technical Meeting. 
UNDP will continue to 
assist in this training in 
regional settings or national 
level. 
Vehicle purchase 
It has been clarified that GEF 
project budget can be used to 
facilitate transport for project 
operations (e.g. vehicle, boat 
rental), but cannot be used to 
purchase vehicle. 
Discussions to be 
undertaken bilaterally if 
issue is persistently raised. 
Sourcing, contracting and 
retention of country project 
staff 
Recommendation was made to 
second qualified government 
staff to the project, retaining 
his/her post throughout the 
project, allowing re-insertion 
after the project. It was 
underlined by UNDP that project 
funds cannot be used to 
subsidize regular government 
salaries, however, different 
countries face different 
situations and such a situation 
need to be examined on its own 
merit. It was agreed that a no 
size-fit-all solution can address 
the unique situations each 
country faces.  
 
Communication: 
The PACC Snapshot and website 
already in place. 
Professional 
communication support to 
be sourced at strategic 
points of the project. 
 
 
 
background image
VI. Annexes 
 
ANNEX I – Logical Framework  
 
ANNEX II – Project Management Arrangement 
 
ANNEX III – Project Monitoring and Evaluation 
 
ANNEX IV – PACC Co-financing Support 
 
ANNEX V - Country Progress 
 
ANNEX VI – Partners and their Activities 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
background image
 
 
 
ANNEX I – Logical Framework [after Inception Review] 
 
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Goal: To reduce vulnerability and to increase adaptive capacity to the adverse effects of climate change in key Development Sectors identified 
by 13 participating countries in the Pacific. 
Objective:   To enhance 
the capacity of the 
participating countries 
to adapt to climate 
change, including 
variability, in selected 
key development 
sectors.
 
Number of references to 
vulnerability of the coastal, 
crop production and water 
sector to climate risks in 
policies, plans and projects. 
 
Climate change risks 
in the coastal, crop 
production and water 
sector are not 
acknowledged in 
relevant policies, 
plans and projects 
both at the national 
and local level. 
By the end of the project, 100% 
of national and regional relevant 
plans in all participating countries 
include climate change risk 
considerations for the coastal, 
crop production and water sector. 
Surveys/interviews /plans 
 
 
There is political willingness 
to integrate climate change 
related risks into coastal, 
crop production and water 
sector management plans, 
policies and strategies 
Outcome 1: Policy 
changes to deliver 
immediate 
vulnerability- reduction 
benefits in context of 
emerging climate risks 
defined in all 13 PACC 
countries. 
Number of references to 
coastal, crop production and 
water sector climate change 
risks in relevant plans and 
programmes. 
Relevant 
development and risk 
management plans do 
not include climate 
change risks on the 
coastal, crop 
production and water 
sector. 
By the end of the project, climate 
change risks in the coastal, crop 
production and water sector are 
addressed in three (3) national 
plans and at least two (2) 
provincial development plans. 
Survey and review of 
national and provincial 
coastal, crop production and 
water sector management 
plans. 
Political will to review the 
plans is ensured and 
maintained throughout the 
life of the project. 
 
Output 1.1:  Develop 
policies, methodologies, 
and tools to enhance 
Pacific Island countries 
efforts to mainstream 
climate change into their 
current national 
development plans and 
1.1.1 Number of instances 
where the Guidelines on 
climate change risk 
management have been 
applied in national and sub-
national coastal, crop 
production and water sector 
related plans and 
Relevant 
development and risk 
management plans, 
both at the national 
and the local level, do 
not address climate 
change risk in the 
coastal, crop 
By the end of the project, all 13 
project countries integrate climate 
change risk resilience in the 
corresponding national and sub-
national policies or plans of their 
target sector (coastal, crop 
production or water sector) 
Survey and review of revised 
relevant national policies and 
plans. 
Political will to review and 
revise the plans is ensured 
and maintained throughout 
the life of the project. 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
priorities. 
programmes. 
1.1.2 At least three climate 
change policies developed in 
three PACC countries. 
1.1.3 Number of plans that 
integrate climate change risk 
issues related to coastal, crop 
production and water sector 
management. 
production and water 
sector. 
 
 
 
 
Output 1.2 Climate 
change economic tools 
for evaluation of 
adaptation options 
developed and utilized. 
 
1.2.1 Availability of an 
economic tool to cost 
different climate change 
adaptation options 
1.2.2 The number of 
countries that apply 
economic costing of 
adaptation options in their 
project activities 
Currently, no such 
models exist.  
By the end of the project, at least 
5 countries have used the model 
in their pilot sites. 
Evaluation reports 
Relevant experts are 
available.  
Outcome 2: 
Demonstration 
measures to reduce 
vulnerability in coastal 
areas and crop 
production (in Fiji, 
Papua New Guinea and 
Solomon Islands) and in 
water management (in 
Nauru, Niue, Tonga and 
Tuvalu) implemented. 
Number of adaptation 
measures implemented at the 
national level 
Number of adaptation 
measures implemented at the 
sub-national level 
Number of adaptation 
measures implemented at the 
local (community) level. 
No long-term climate 
change adaptation 
measures 
implemented. 
By the end of the project, 
adaptation measures to address 
climate change risks are adopted 
in the corresponding target sectors 
(coastal, crop production or water 
sector) by: 
 
All countries (100%) at 
the national level. 
 
50% of countries at the 
sub-national level. 
 
At least one (1) 
community in each country. 
Evaluation reports 
Field Surveys 
Local stakeholders support 
the adoption of adaptation 
measures. 
 
Output 2.1.1a:  
Guidelines to integrate 
2.1.1a At the end of year 
two, community 
Currently, no coastal 
developments have 
By the end of the project, the 
Climate Change adaptations & 
Field assessment, feasibility 
The willingness of key 
stakeholders to work 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Coastal Climate Risks 
into the design of one of 
the following harbours. 
Manihiki (Tukao or 
Tauhunu), Penrhyn and 
Nassau. 
consultations and project 
design guidelines are 
completed and applied to the 
chosen harbour design. 
taken future changes 
in climate into 
consideration. 
design guidelines are in place and 
incorporated in the design of the 
demonstration project. 
and design reports.  
 
Stakeholder consultations 
record. 
together to complete the 
project. 
 
Funding being available on 
time. 
2.1.2b At the end of the year 
one a climate change 
resilient design is completed, 
peer reviewed and approved 
for the harbour chosen. 
Currently, no coastal 
developments have 
taken future changes 
in climate into 
consideration. 
By the end of the project, one 
harbour (demonstration) that 
incorporates climate change 
adaptation risks in its structural 
design is completed and 
operational. 
 
Field assessment, feasibility 
and design reports.  
Stakeholder consultation. 
The willingness of key 
stakeholders to work 
together to complete the 
project. 
 
Funding being available on 
time. 
 
2.1.1.b Demonstrate the 
integration of coastal 
climate risks into the 
Harbour designs of  one 
of the following 
harbours; Manihiki 
(Tukao or Tauhunu), 
Penrhyn and Nassau. 
 
Output 2.1.1a:  
Guidelines to integrate 
Coastal Climate Risks 
into the design of one of 
the following harbours. 
Manihiki (Tukao or 
Tauhunu), Penrhyn and 
Nassau. 
2.1.1a At the end of year 
two, community 
consultations and project 
design guidelines are 
completed and applied to the 
chosen harbour design. 
Currently, no coastal 
developments have 
taken future changes 
in climate into 
consideration. 
By the end of the project, the 
Climate Change adaptations & 
design guidelines are in place and 
incorporated in the design of the 
demonstration project. 
Field assessment, feasibility 
and design reports.  
 
Stakeholder consultations 
record. 
The willingness of key 
stakeholders to work 
together to complete the 
project. 
 
Funding being available on 
time. 
Output 2.2.1a: 
Guidelines to integrate 
climate risks (e.g. intense 
rainfall and storm surges) 
into coastal road designs. 
 
2.2.1a  Number of guidelines 
revised and applied 
Guidelines for road 
design exist, but they 
are not climate-proof 
At the end of year two, a 
Guideline is developed and 
integrated into one (1) national 
and one (1) State road 
management plan 
Field Surveys 
 
Guidelines document 
All key stakeholders listed in 
the project document (both at 
State and national level) 
support the work to be 
carried out. 
Output 2.2.1b: Measures 
identified in the 
Guidelines (2.2.1a) 
demonstrated in Walung 
community, Kosrae (with 
2.2.1b. Number of existing 
road projects where the 
guidelines (developed under 
One existing road 
project, which is not 
climate-proofed 
By the end of the project, at least 
one (1) climate resilient road 
design is demonstrated.  
Field Surveys 
All key stakeholders listed in 
the project document (both at 
State and national level) 
support the work to be 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
co-financing support). 
 
2.2.1.a.) are applied 
carried out. 
Output 2.3.1a:  
Existing coastal and river 
protection guidelines and 
flood modeling within 
the CIMP revised and 
updated.  
 
2.3.1aAt least 4 district 
CIMP revised and updated  
CIMP, Saoluafata sea 
wall assessment 
report. PUMA 
Development consent 
guidelines  Flood 
model program  
By the end of the PACC project, 
the updated guidelines integrated 
into national coastal and river 
protection programs.  
 
Field Surveys 
Model documentation 
Guidelines and documents, 
Field assessment reports. 
Discussion notes  
CLEWS report  
Relevant expertise is 
available to assist with the 
guidelines locally  
Accurate flood model  
Accurate coastal geographic 
information available  
Accurate CLEWS report to 
coastal and river sub sectors. 
Output 2.3.1b: Climate 
Proof Measures identified 
in the Guidelines (2.3.1a) 
demonstrated in  
coastal and river 
communities 
Gataivai, Salelavalu 
(Savaii) Lotofaga, 
Tafitoala(Upolu) 
Vaisigano river ( Apia) 
Fuluasou river (Vailoa 
Faleata ) 
 (With government – and 
community co-financing 
support). 
2.3.1b At the end of year 2, 
coastal and river protection 
defense system in place in 
the 6 villages. 
 CIMP, Saoluafata 
sea wall assessment 
report.  
PUMA Development 
consent guidelines  
Flood model program 
By the end of the PACC project, 
community coastal and river 
protection defense is 
demonstrated.  
Field Surveys 
Actual pilot Guidelines and 
documents, Field assessment 
reports. Discussion notes  
CLEWS report 
 
Relevant expertise is 
available.  
Accurate flood model  
Accurate coastal geographic 
information available  
Accurate CLEWS report to 
coastal and river sub sectors. 
 
 
Output 2.4:1a 
Guidelines that 
incorporate 
multistakeholder 
decision-making in the 
redesign and relocation 
of coastal roading 
infrastructures due to the 
impacts of climate 
2.4.1a Number of guidelines 
developed incorporating a 
multi-stakeholder decision-
making system in the 
redesign and relocation of 
coastal roading 
infrastructures. 
No guidelines in 
place for coastal 
roading infrastructure 
redesign and 
relocation. 
By the end of the project, at least 
one (1) guideline for redesigning 
and relocation of coastal roading 
infrastructures in isolated coastal 
communities is used. 
Field Surveys 
1 guideline for redesigning 
and relocation of coastal 
roading infrastructures 
Stakeholder (NACCC, Shefa 
Provincial Gov, & Epi 
communities) 
All stakeholders (NACCC, 
Shefa Provincial Gov, & Epi 
communities)  have the same 
understanding and support. 
Accuracy of climate change 
model to be used in the 
formulation of the guideline  
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
change. 
interviews/consultations 
Output 2.4:1b Climate 
Proofing Measures 
identified through use of 
the Guidelines (2.4.1a) 
demonstrated in Epi 
communities, Shefa 
Province (with co-
financing support). 
2.4.1b Number of 
demonstration sites 
implemented using guideline 
for redesigning and 
relocation of coastal roading 
infrastructure 
No such guidance is 
available at the time 
of project signing. 
By the end of the project, at least 
one (1) Demonstration project 
implemented using guideline for 
redesigning and relocation of 
coastal roading infrastructures. 
Field Surveys 
Demonstration project 
reports 
 
 
Public Works Department 
have the necessary 
background technical 
information. 
Output 2.51a: Drainage 
design criteria for the 
drainage network and all 
associate drainage 
infrastructures are revised 
to adapt to future rainfall 
regime and sea level rise 
due to the Climate 
Change 
2.5.1a Number of guidelines 
with revised design criteria 
on rainfall, runoff, 
discharging capacity for the 
drainage network, outfall 
structure and seawall & other 
associate drainage 
infrastructures. 
Drainage guideline 
exist; but not 
adequate to address 
current and future 
rainfall trend, and sea 
level rise due to 
Climate Change.  
By the end of the project, at least 
4 new guidelines (design criteria) 
are developed and applied in the 
demonstration areas. This will be 
the basis for future drainage 
design and construction works in 
Fiji. 
Field Surveys 
Government report 
Revised guideline. 
PMU evaluation reports on 
projects.  
Project steering Committee.  
All relevant base data are 
easily accessible. 
Output 2.5.1b: The 
revised guidelines (2.1) 
are demonstrated in 
drainage network and on 
associate infrastructures 
in the Tailevu/Rewa and 
Serua Namosi Province 
(with co-financing 
support). 
2.5.1b Number of drainage 
schemes (including drains, 
outlet waterways, outfall 
structures, seawalls, culverts) 
renovated/ enhanced as per 
new guide line in the 
demonstrating schemes  
The present drainage 
infrastructures are not 
adequate to cope with 
the future rainfall 
regime & sea level 
rise due to Climate 
Change effects.  
By the end of the project drainage 
schemes are renovated to meet the 
new design criteria and 
requirements, at least at the 
Tailevu/Rewa and Navua 
(Serua/Namosi) areas. 
Field Surveys 
Government report 
Work evaluation report. 
Project Steering committee.  
 
Farmers; villagers; 
collaborate in the 
demonstration process and 
capturing of lessons. 
Technical staff trained on the 
revised guidelines is retained 
Output 2.6.1a 
Guidelines to improve 
resilience of coastal food 
production systems to the 
impacts of climate 
change. 
2.6.1a Number of Guidelines 
developed. 
No such Guidelines 
exists.  
By the end of the project, at least 
one (1) Guideline is developed for 
Ngatpang State in Palau. 
Ngatpang State report 
Field Manual 
Field Survey 
All necessary background 
information is available. 
All implementing  partners 
are involved for the entirety 
of the project 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Output 2.6.1b Measures 
identified in the 
Guidelines (2.6.1a) 
demonstrated in 
Ngatpang 
State/Communities  
2.6.2b Number of coastal 
food production systems 
projects where the guidelines 
(developed under 2.6.1.a.) 
are applied 
No measures in place 
that have taken 
climate change into 
consideration at 
implementation of 
project 
By the end of the project, at least 
one (1) community in Ngatpang 
State has demonstrated and 
accepted a measure developed 
and applied through the project. 
Ngatpang State report 
Field Survey 
State Government 
contributes to the PACC 
initiative. 
Farmers collaborate in the 
demonstration process. 
Output 2.7.1a: 
Guidelines for design of 
underground irrigation 
networks to adapt to 
future rainfall regimes. 
2.7.1a One guideline for the 
design of irrigation systems 
using underground water 
developed 
No guidelines in 
place for the use of 
underground water 
for irrigation 
No design that takes 
into consideration of 
long-term change in 
precipitation levels 
By the end of the project, 
guideline for irrigation using 
underground water approved by 
government  
National Project inception 
report 
Field feasibility study report 
Quarterly monitoring reports 
Annual Implementation 
Report 
Inadequate political will  
Insufficient co-funding 
Limited capacity 
  
Output 2.7.1b: Measures 
identified in the 
Guidelines (2.7.1a) 
demonstrated in Kivori 
Poe, Kairuku district, 
Central Province (with 
co-financing support). 
2.7.1b Number of measures 
demonstrated 
 
By the end of the project, at least 
one village in the Kivori Poe 
Ward applies the guidelines in 
their demonstration project. 
 
Community differences 
influence participation for 
collective action 
Land ownership 
High community expectation 
Output 2.8.1a: 
Guidelines for reducing 
vulnerability of small 
isolated island 
communities’ to the 
effects of climate change 
in the food production 
and food security sector. 
2.8.1a Number of Guidelines 
developed and applied. 
No such guidance is 
available at present. 
By the end of the project, at least 
1 Guidelines is developed and 
applied. 
Department of Agriculture 
report. 
Field Survey 
Transportation is not 
disrupted by bad weather. 
Output 2.8.1b: Measures 
identified in the 
Guidelines (2.8.1a) 
demonstrated in Ontong 
Java Island (with co-
financing support). 
2.8.1b Number of measures 
demonstrated in small island 
communities. 
No new measures in 
place that have taken 
climate change into 
consideration 
By the end of the project, at least 
one (1) small island community in 
the Solomon Islands has 
demonstrated and accepted a 
project intervention. 
Department of Agriculture 
report. 
Field Survey 
Transportation is not 
disrupted by bad weather 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Output 2.9.1a 
Water policy and 
guidelines developed to 
support water 
conservation and 
minimize reliance on 
central reservoir  
Number of policy and 
guidelines developed 
Draft Water policy 
developed, but not 
climate proofed 
 
No guidelines 
established to support 
water conservation 
By the end of project at least three 
(3) guidelines developed for: 
a) Conservation of water in the 
Reservoir  
b) Water storage for agriculture 
activities 
 
Government reports 
 
Water Policy document 
 
Field survey reports 
Political will at the national 
level is maintained 
 
Officers have adequate time 
to commit to project 
 
Effective collaboration 
between national agencies 
Output 2.9.1b 
Measures identified in 
the guidelines 
demonstrated in Majuro 
atoll 
Number of measures 
demonstrated in Majuro atoll 
No conservation 
measures for central 
reservoir in place and  
inadequate measures 
in place to reduce 
reliance on reservoir 
By the end of project, at least one 
(1) intervention to: minimize 
evaporation in the current water 
reservoir; increase water storage 
for farming activities. 
PACC project reports 
 
Government reports 
Political will at the national 
level is maintained 
 
Funding remains adequate 
 
Effective collaboration 
between national agencies 
Output 2.10.1.a: 
Guidelines for design of 
conjunctive supply 
systems to enhance 
resilience to drought 
events 
2.10.1a Number of 
conjunctive designs 
combining current 
freshwater and groundwater 
supply and storage 
Existing guideline 
needing 
strengthening 
By the end of the project, at least 
2 guidelines are developed: 
1)
 
Revamp Storage and 
Catchment 
2)
 
Improved community 
access to current system 
3)
 
Establish Water Unit 
(merging IWRM and 
PACC) 
Government Report 
 
Field Survey 
All stakeholders provide 
necessary support 
 
Communities concerned to 
support project interventions 
 
Political Will 
Output 2.10.1.b: 
Measures identified in 
the guidelines (2.10.1.a) 
demonstrated in 3 
districts Denig, Aiwo and 
Buada District (with co-
financing support) 
2.10.1b Number of 
conjunctive designs 
combining current  
freshwater and groundwater 
supply and storage 
demonstrated 
Existing guideline 
needing 
strengthening 
By the end of the project, at least 
2 guidelines are developed and 
demonstrated in a pilot situation 
in Nauru 
Government Report 
 
Field Survey 
All stakeholders provide 
necessary support 
 
Communities concerned to 
support project interventions 
Output 2.11.1a: 
Guidelines for design of 
water storage systems on 
a raised atoll island to 
enhance resilience to 
drought events. 
2.11.1a Number of instances 
of practical guidance being 
used. 
No previous 
experience in such 
design. 
By the end of the project, at least 
one (1) practical guidance is in 
place and five (5) officers trained 
on the use of the guide. 
Guide document 
Training report 
All stakeholders provide 
necessary support. 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Output 2.11.1b: 
Measures identified and 
approved in the 
Guidelines (2.11.a) 
demonstrated in at least 3 
villages (approx. 100H) 
 
 
2.11.1b Number of improved 
and approved water storage 
system on the raised atoll 
island to enhance resilience 
to prolonged drought 
situations in place 
Limited experience in 
place. 
 
By the end of the project at least 1 
guideline to improve water 
storage systems is demonstrated 
in a pilot situation in Niue  
 
At least 100 water storage system 
installed, adopted and in use 
Government Report 
Field Survey 
All relevant stakeholders and 
household provide necessary 
support. 
Output 2.12.1a: National 
Guideline developed to 
drought proof Tongan 
Communities 
2.12.1.a No of national 
drought proofing guideline. 
No previous experience in 
climate-proofing water 
supply design 
No national drought 
proofing guideline. 
No previous 
experience in 
climate-proofing 
water water supply 
design 
By the end of the project, drought 
proofing guidelines for assessing 
and addressing water resource use 
and management developed  
Government Report – 
National Draught Proofing 
Guideline 
Assessments 
 
National and Provincial 
Agencies support the project 
intervention 
  
Output 2.12.1b: 
Measures identified in 
the Guidelines (2.12.1a) 
demonstrated in Hihifo 
district (with co-
financing support). 
 
2.12. Number of drought 
proofed measures in the 
guideline demonstrated  
 
Existing non resilient 
water supply system 
in Hihifo. 
 
 
By the end of the project, the six 
villages of Hihifo draught proofed 
to National Standards. 
 
Reports from Hihifo Water 
Committee 
Government Report 
Assessments 
 
National and Provincial 
Agencies support the project 
intervention 
All communities concerned 
support the project 
interventions 
Associated stakeholders 
supports project 
implementation 
Output 2.13.1a: 
Guidelines for climate 
proofing integrated water 
management plans. 
 
2.13.1a Number of instances 
of guidance. 
This activity has 
never been carried 
out. 
By the end of the project, a guide 
on how to climate proof water 
management plans in place.   
Government Report 
Field Survey 
All stakeholders support the 
process. 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
Output 2.13.1b: 
Measures identified in 
the Guidelines (2.13.1a) 
demonstrated in Fogafale 
village (with co-financing 
support). 
 
2.13.1b Number of 
interventions to climate 
proof current integrated 
water management plan 
demonstrated. 
No previous in 
carrying out this 
work.  
By the end of the project, 
Tuvalu’s current integrated water 
management plan is climate 
proofed. 
Climate proofed water 
management document 
developed and disseminated. 
All stakeholders support the 
process. 
Outcome 3: Capacity to 
plan for and respond to 
changes in climate 
related risks improved. 
Technical capacity at the 
national level to support the 
work in 13 PICs enhanced.  
Carried out in ad hoc 
arrangements. 
By the end of the project, the 13 
PICs rate that the quality of 
support received as a 1 (out of 4, 
with 1 being excellent and 4 being 
poor). 
Country reports 
PACC Annual Reports 
Workshop Reports 
Stakeholder surveys. 
Countries clearly formulate 
and communicate their 
capacity needs throughout 
the project. 
Output 3.1.1: Technical 
advice for implementation 
of national adaptation 
 
3.1.1 Number of instances of 
technical guidance provided 
and accepted. 
Regional support 
mechanisms ad hoc 
in nature. 
By the end of year 2, the Support 
Mechanism for the Project is in 
place and provides relevant 
technical guidance to all PICs on 
a regular basis, 
Country comments in 
quarterly reports 
Stakeholder surveys 
Countries clearly formulate 
and communicate their 
capacity needs throughout 
the project 
Trained and qualified project 
staff is retained throughout 
the project 
Output 
3.1.2: Best 
practices and lessons 
exchanged among 
countries through SPREP. 
 
3.1.2 Number of lessons 
exchanged. 
No climate change 
adaptation lessons 
have been shared 
around the region in a 
systematic fashion. 
By the end of year 4, at least 26 
lessons are documented and 
exchanged (two lessons for each 
of the 13 PICs) between the 
countries. 
 
Country reports 
PACC Annual Reports 
Workshop Reports 
Stakeholder surveys 
Publications 
All stakeholders at the 
national and regional level 
play their part in capturing, 
documenting and sharing 
lessons. 
Output 3.1.3: Project 
website established at 
SPREP. 
3.1.3 Project website 
functioning 
No specific website 
targeted at climate 
change adaptation. 
By the end of the 2
nd
 year of the 
project, the PACC project website 
is established at SPREP and 
regularly updated with lessons 
learnt from all participating 
Website address and site. 
All stakeholders provide 
regular and timely 
information for the 
development and 
background image
Project Strategy 
Indicator* 
Baseline value 
Target and benchmarks 
Sources of verification 
Risks and Assumptions 
countries. 
maintenance of the site. 
Outcome 4 
Project Management 
Implemented. 
Number of PMUs operating 
successfully at the national 
level. 
None existing at 
present. 
By the end of year one, 13 PACC 
national PMUs are operating and 
reporting regularly to the PACC 
PMO based at SPREP. 
Quarterly reports 
Publications 
Pilot site progress reports 
High turn over of staff is not 
addressed. 
Output 4.1 
Project Management 
Implemented. 
4.1.1 At least one officer 
manning the national PMU 
 
No dedicated officer 
exists at present. 
By the end of year one, at least 13 
PACC Coordinators are manning 
the 13 national PMUs and 
reporting regularly to the PACC 
PMO based at SPREP. 
Quarterly reports 
Immediate supervisors report 
Coordinators are adequately 
trained to carry out their 
work effectively. 
background image
ANNEX II – Project Management Arrangement 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
UNDP 
Implementing Agency 
 (UNDP-Samoa) 
COUNTRY X 
 
National Lead 
Agency 
(NEX) 
 
 
 
National 
Coordinator 
 
 
 
National 
Consultative 
Committee 
Project Executive Group 
(IA, ExAs, Countries, Obs.) 
 
 
SPREP 
Regional Technical Agency  
(Project Management Office) 
 
 
 
COUNTRY Y 
 
National Lead 
Agency 
(NEX) 
 
 
 
National 
Coordinator 
 
 
 
National 
Consultative 
Committee 
background image
ANNEX III - 
Project Monitoring and Evaluation
 
 
Type of M&E Activity 
Responsible Parties 
Budget US$ 
Excluding Project 
Staff time 
Time frame 
Inception Workshop (IW) 
 
Project team 
 
UNDP Samoa MCO 
 
UNDP-GEF 
100,000 
Within first 4 months of project start up 
Inception Report 
 
Project team 
 
UNDP Samoa MCO 
 
UNDP-GEF 
None 
Draft IR available before IW 
Final IR available immediately following 
IW 
Measurement of means of 
verification for project 
purpose 
Indicators 
 
Regional Project Manager 
will oversee hiring of 
specific studies and 
institutions, and delegate 
responsibilities  
To be finalized in 
Inception Phase and 
IW.  
100,000 (indicative 
cost) 
Start, mid, and end of project 
APR and PIR 
 
Project team 
 
UNDP Samoa MCO 
 
UNDP-GEF 
None 
Annually 
TPR and TPR report 
 
Government Counterparts 
 
UNDP Samoa 
 
Project team 
 
UNDP-GEF RCU 
None 
Annually, upon receipt of APR 
Periodic status reports 
 
Project team 
None 
To be determined by Project team and 
UNDP 
Technical Reports 
 
Project team 
 
Consultants as needed 
20,000 
To be determined by Project team and 
UNDP Samoa 
Mid-term External 
Evaluation 
 
UNDP Samoa 
 
UNDP-RCU 
 
External consultants (i.e. 
evaluation team 
20,000 
At mid-point of project implementation 
Final External 
Evaluation 
 
UNDP Samoa 
 
UNDP-RCU 
 
External consultants (i.e. 
evaluation team 
20,000 
At end of project implementation 
Terminal Report 
 
Project team 
 
UNDP Samoa 
 
External Consultant 
None 
At least one month before the end of 
project 
Lessons learned 
 
Project team 
 
UNDP Samoa 
 
UNDP-GEF RCU 
(suggested formats for using 
best practices, etc) 
25,000 
(i.e. 5,000 per year) 
Annually  
Audit 
 
UNDP Samoa 
 
Project team 
25,000 
(i.e. 5,000 per year) 
Annually 
Visits to field sites 
(UNDP staff travel costs to 
be charged to IA fees) 
 
Project team 
 
UNDP Samoa 
 
UND-GEF RCU (as 
appropriate) 
 
Government/PEG 
representatives 
100,000 
(i.e. 20,000 per year)  
Annually 
TOTAL INDICATIVE COST 
Excluding project team staff time and UNDP staff and travel 
expenses and misc. expenses 
 
US$410,000 
 
background image
  
 
42
ANNEX IV - PACC Co-Financing Support 
 
Countries 
Co-financing programmes and projects descriptions 
Amount 
Amount USD
Nauru 
Planned annual government expenditures as per 2006 budget 
218,000 AUD 
168,000
JICA funded water tanks for communities project 
100,000 AUD 
77,000
  
MOU with Australia on water catchment & storage and repairs 
1,500,000 AUD 
1,150,000
  
Australia COMPACT for groundwater prospection and monitoring 
400,000 AUD 
307,000
  
FAO regional food security programme with a package on water storage 
136,000 USD 
136,000
  
office space (in-kind) 
50,000 USD 
50,000
Subtotal
 
 
$1,888,000.00
Niue 
Construction of water reservoir under Cyclone Recovery Project 
67,036 NZD 
46,000
office space (in-kind) 
50,000 USD 
50,000
  
DSAP Project / EU funded  
 
Subtotal
 
 
$96,000.00
Solomons 
Ministry of Agriculture and Livestock / Rice Development project / Taiwan funding 
  
  
FAO Technical Cooperation Project 
  
  
  
FAO regional food security 
  
  
  
Ministry of Agriculture budget estimate based on 2006 figures 
  
  
  
office space (in-kind) 
  
4,800,000
Subtotal
 
 
$4,800,000.00
Cook Islands 
ADB Cyclone Emergency Loan Project 
  
2,650,000
Office space (in-kind) 
  
50,000
Subtotal
 
 
$2,700,000.00
Tonga 
AUD funding for adaptation for Tonga TBC 
2,000,000 AUD 
1,538,000
Groundwater monitoring / Geology Department operational budget 
  
  
  
Canada and Japan funded water tanks for community 
  
  
  
Rainwater harvesting / Tonga Trust Operational Budget 
  
  
  
Office space (in-kind) 
50,000 USD 
50,000
Subtotal
 
 
$1,588,000.00
FSM 
Compact Funds (on-going exp) 
1,270,480 USD 
1,270,480
Compact Funds (planned exp) 
1,535,000 USD 
1,535,000
  
Japanese Grant for Road construction Tafunsak-Walung 
4,000,000 USD 
4,000,000
background image
  
 
43
  
office space (in-kind) 
50,000 USD 
50,000
Subtotal
 
 
$6,855,480.00
Samoa 
AusAID Adaptation Support 
100,000 AUD 
77,000
World bank IAM I and II 
1700000 USD 
1,700,000
  
CERP / Coastal resilience recovery 
500,000 USD 
500,000
  
office space (in-kind) 
50,000 USD 
50,000
Subtotal
 
 
$2,250,000.00
Vanuatu 
US Millennium Challenge Account / transport infrastructure project in Epi (roading) 
2,900,000
2,900,000
office space (in-kind) 
  
  
Subtotal
 
 
$2,900,000.00
Fiji 
Government of Fiji Expenditures based on 2007 estimates Drainage and Irrigation 
4800000 FJD 
2,860,000
Government of Fiji Expenditures based on 2008 estimates land Drainage and Flood protection 
4800000 FJD 
2,860,000
  
Government of Fiji Expenditures based on 2009 estimates Drainage and Irrigation 
4800000 FJD 
2,860,000
Subtotal
 
 
$8,600,000.00
Tuvalu 
AUSAID Adaptation to Climate Change project 
1,200,000 AUD 
923,076
Government of Tuvalu / Water Tank 
600,000 AUD 
461,538
  
Office space (in-kind) 
50,000 USD 
50,000
Subtotal
 
 
$1,500,000.00
PNG 
National Department of Agriculture and Livestock 
  
1,000,000
Donor funded (FAO & EU) 
  
1,000,000
  
Central Provisional Administration 
  
500,000
  
DEC Water Resources Division 
  
500,000
Subtotal
 
 
$3,000,000.00
Palau 
Salaries of Technical Experts from organisations that would support PACC implementation 
  
1,010,000
Costs of base data and technical inputs to be provided to PACC 
  
592,000
Subtotal
 
 
$1,602,000.00
Marshall Islands 
Airport Runway works 
  
4,000,000
  
Salaries of Technical Experts from organisations that would support PACC implementation 
  
1,975,000
Subtotal
 
 
5,975,000
UNDP 
time of finance staff and management (in-kind) 
50,000 USD 
50,000
office space (in-kind) 
50,000 USD 
50,000
 Subtotal
 
 
$100,000.00
background image
  
 
44
SPREP 
time of finance staff and management (in-kind) 
50,000 USD 
50,000
office space (in-kind) 
50,000 USD 
50,000
 Subtotal
 
 
$100,000.00
UNITAR 
Capacity Building Programme contributing to Outcome 1 and 2 
210,000 Euro 
330,000
Subtotal
$330,000.00
Total Co-financing
 
  $44,284,480
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
45
  
ANNEX V COUNTRY PROGRESS 
 
This section of the report documents the progress made for each PACC participating 
country against the milestones set for 2009. This status report for each country is 
collated from the third quarter reports provided to SPREP and visit reports by the PACC 
RPM. 
 
I. COOK ISLANDS 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU had been signed by the Ministry of Infrastructure and Planning and SPREP. 
 
II] Start up funding  
 
Funds were not available to Cook Islands when the quarter ended. 
 
III] Project Management Units 
 
 
PMU has been established at the Ministry of Infrastructure 
 
IV] PACC Coordinator 
 
 
Mr. Vaipo Mataora has been confirmed as PACC Coordinator 
 
V] National Steering Committee 
 
Steering Committee to be used as a policy oversight for PACC is yet to be 
confirmed. 
General Progress 
During this quarter, Cook Islands confirmed that their new pilot site as Mangaia. It is 
related to a harbour development that will be undertaken by government in the 2010 and 
2011 financial year. Their first pilot (upgrade of Manihiki Airport) had to be withdrawn due 
to the late approval of PACC causing a slippage in timing. In line with government 
development, the PACC project would support the broader coastal management issues 
related to the redevelopment of the Mangaia Harbour (see Plate 1&2 below). Hopefully, 
the intervention by the PACC project would ensure that service and operations continues 
on the island without disruption thus providing an avenue for people to receive required 
essential services to the islands or evacuate people in terms of disasters. Both ways, the 
work will significantly increase the capacity of the people of Mangaia to face changes in 
climate and extreme events. 
 
     Plate 1      Prior to 2005          
 
 
Plate 2  March 2005 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
46
  
 
 
The choice for Mangaia was made after the recent decision of the government of Cook 
Islands to allocate NZ$1.8 million to the Mangaia Harbour redevelopment programme. 
The PACC project will try and address the broader issue of coastal management that is 
plaguing the harbour. For example, after heavy seas the coral gravels used to temporary 
form the dock quay would be washed away into the lagoon leaving behind the rough 
coral flat as seen in plate 2 above. Stop-gap measures attempted in the past by the 
Island Administration would be to temporarily re-fill, repair and re- compact the quay with 
new gravel every time the outer island freighter services the island.  
 
Fourth Quarter Projection 
 
-  
 
II. FEDERATED STATES OF MICRONESIA 
 
Summary 
 
I] Memorandum of Understanding 
MoU had been signed by the 
Kosrae Island Resource Management Authority 
(KIRMA)
 and SPREP 
 
II] Start up funding  
 
Funds were not available to Kosrae when the quarter ended. 
 
III] Project Management Units 
 
 
PMU has been established at KIRMA. 
 
IV] PACC Coordinator 
 
 
No Coordinator has been recruited during this quarter 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
47
  
V] National Steering Committee 
 
Steering Committee to be used as a policy oversight for PACC is yet to be 
confirmed. 
 
General Progress 
 
During the last PACC Inception Workshop in Apia, some progress has been 
made as follows. 
  Hiring of the PACC Coordinator is in process 
  The PACC bank account has already been established 
  PMU for the PACC is again confirmed to be KIRMA 
  The MOU has already been signed 
  There was a consultation meeting with the Governor and the Cabinet 
members 
  Director of the implementing Agency attended the 2
nd
 PACC Inception 
Workshop 
 
At the State level, it is again confirmed that Office of Kosrae Island Resource 
Management Authority (KIRMA) will remain the lead agency for PACC and the 
Department of Transportation and Infrastructure (DT&I) is the implementing 
agency.  The Office of Environment and Emergency Management at the FSM 
national government will remain as the National Focal point. The PACC PMU it 
was decided at State level to be hosted by KIRMA thus they had signed the MoU 
with SPREP. 
 
Fourth Quarter Projection 
 
III. FIJI 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU had been signed by the Environment Department, Ministry of Primary 
Industries 
 and 
SPREP. 
 
II] Start up funding  
 
Funds were not available to Fiji when the quarter ended. 
 
III] Project Management Units 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
48
  
PMU has been established at the Land and Water Resources Division, Ministry 
of Primary Industries. 
 
IV] PACC Coordinator 
 
 
No Coordinator has been recruited during this quarter 
 
V] National Steering Committee 
 
 
Not clear at present which Steering Committee would be used 
 
General Progress 
 
As a follow up action, the Department of Environment (National focal point) and the Land 
& Water Resource Management Division (LWRM) (Implementing Agency) met and set 
the initial action plan and time line for the formulation of Project Management Unit and 
necessary meetings. The Draft MOU was reviewed and vetted by the Solicitor General 
office of Fiji. After final vetting it was signed by the Permanent Secretary for Agriculture 
(MPI) and the Director Environment on behalf of the Fiji Government. Payment 
agreement form was also signed and sent to the SPREP in August. Both MOU and 
agreement of payment document were sent to the SPREP for their signature and 
formalization. 
 
The Department Environment is preparing one Cabinet information paper regarding the 
PACC project for submission to the Fiji Government. It will be finalized in the first week 
of October. However, the Fiji Prime Minister had highlighted in his speech in the UN the 
vulnerability that Fiji is facing that are related to the changes in climate. 
 
For the purpose of dissemination and participating of relevant stake holders, the LWRM 
Division had organized two inter Department meetings within the Ministry. The Director 
of Crop Extension, Director of Crop Research, Director of Animal Health & Production 
were invited and explained about the context of the PACC project and requested to 
participate and contribute in their role at the demonstration stage of the pilot areas. The 
second meeting was held upon the request of the Research Division to convey further 
information of the PACC project to the research officers of the Division. Through those 
meetings, their proposals in related with the PACC project demonstration activities were 
requested. The Research Division has already submitted its proposals, including 
program activities, cost and time line. These requirements will be included in the AWP 
for Fiji. 
 
For the advertising of the PACC NPC, the job sizing and necessary document had been 
prepared and submitted to the Public Service Commission (PSC) through the Ministry. It 
is now at the PSC and waiting for the final approval for the advertisement.  
 
Due to lack of start up fund, the national inception workshop and the wider stake holder 
meeting could not be started yet. 
 
Fourth Quarter Projection 
 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
49
  
 
 
IV. MARSHAL ISLANDS 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU had been signed by the 
Office of Environment Policy and Coordination 
 
II] Start up funding  
 
Funds were not available to Marshall Islands when the quarter ended. 
 
III] Project Management Units 
 
 
PMU has been established at the Office of Environment Policy and Coordination 
 
IV] PACC Coordinator 
 
 
No Coordinator has been recruited during this quarter 
 
V] National Steering Committee 
 
Steering Committee to be used as a policy oversight for PACC is yet to be 
confirmed. 
 
General Progress 
 
 
 
 
V. NAURU 
 
Summary 
 
I] Memorandum of Understanding 
Mou had been signed by the Ministry of Commerce, Industry and 
Environment and 
SPREP 
 
II] Start up funding  
 
Start-up funding was already available during this quarter 
 
III] Project Management Units 
 
The PACC PMU in Nauru is established within the Commerce, Industry and 
Environment (CIE) government department.  
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
50
  
IV] PACC Coordinator 
 
The PACC project coordinator is Ms. Mavis Depaune.  
 
V] National Steering Committee 
 
PACC/ IWRM with other projects will be part of a broader Projects Steering 
Committee to be tasked with endorsing project activities, budgets etc. The term 
of reference for this steering committee is currently being finalised. 
 
General Progress 
 
The PACC Inception Workshop was carried out during this quarter and it was well 
attended and stakeholder feedback was very positive. There were a lot of concerns 
raised that involved both potable and non potable water. Shared knowledge and 
information provided a better understanding of the areas that urgently needs to be 
addressed for effective management of water as a resource. Main issues that were 
raised and provoked discussion were: 
  The cost estimates of water production of desalination plants and Reverse 
Osmosis units 
  Different districts raising different water issues, e.g. Aiwo district has oil seepage 
in their groundwater. Location district have a high population which is equivalent 
to two other districts put together which requires a higher demand for water.  
  The Priorities that were identified by stakeholders were 
i.  Tanks and Guttering at community level 
ii.  Storage Tanks at a National level (involving the Utilities storage units) 
iii.  Water Management and Awareness programs 
iv.  Well Installations in communities 
v.  Water Catchments at national level 
vi.  Addressing the underground water contamination 
vii.  Delivery trucks used for potable water distribution 
  
Further consultations were carried out at government and community level with Utilities 
Department. It was identified during the Inception workshop that policies for the better 
management of water and its use need to be developed. This includes obtaining the 
data for the amount of water that is used by the general public. In discussion with 
Utilities, It was agreed that they will work closely with PACC so that all PACC activities 
can be mainstreamed into their work programme when PACC funds utilized. 
 
Plans are also in place for the Statistics Department to assisting PACC analyze survey 
data from the surveys and questionnaire that is to be collected for the water use of the 
location community. This will give a measurement of water use in the community that 
would be a basis that can be used for other districts. 
 
Current Status 
 
  Desalination plant is out of operation. Main potable water for the island from 
rainwater harvesting and three Reverse Osmosis units which are only operated 
during work hours. Reason is the storage capacity. It was noted with Tony 
Falkland that that there are open valves from the water pipes transporting water 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
51
  
to the temporary storage facilities, these valves are not monitored as locals are 
able to obtain water without restrictions. 
  Assessment of potable water use is still underway, working closely with Utilities 
and ED9 project to find the current estimate of water use using existing data for 
future predictions (adding in the cost implications for the real value of water for 
the Nauruan population). This can give an estimate for future water use with 
growing population.  
  Co – financing with ED9 water project for development of water guidelines. 
  Researching tank types and variations, water pipes and guttering systems, this 
includes the prices for units as well as shipping costs. Labour costs with Eigigu 
holdings have yet to be finalized.   
 
 
Policy Development  
 
  There are no current baseline policies on climate change for Nauru, but this is 
being addressed in the long term goal on the Nauru National Sustainable 
Development Plan through the climate change unit housed under the CIE 
government department.  
  The NSDS is currently in the process of evaluation by government and external 
technical support. (Draft NSDS attached).  
  Water policies can be and will have a starting point through the development of 
the water use guidelines by the PACC project and can be mainstreamed as a 
climate change component during the implementing process of climate change 
policies.  
  The draft Nauru Water Plan by Ian. Wallis (Nauru Health Department private 
consultant) is still to be endorsed. Other visiting consultants for the health 
department are also using the Nauru water plan as a baseline for other water – 
health related issues.        
 
 
Pilot Development  
 
Guideline development 
  
  Water use monitoring and management is an issue that will be addressed. Work 
that has been done so far is the collection of previous data and reports that has 
been done by different government departments, in particular Utilities and Health 
departments.  
  Survey and Questionnaires for the identified area where the PACC project will 
take place are currently in the process. This work will be in collaboration with 
local consultants for statistical analysis of water use at household level. This will 
help in identifying the amount of water use at a household level within the 
community.   
 
Demonstration guide 
 
  The PACC project is concentrating on water harvesting for communities, in 
particular in the location in Denig district. This area has been chosen due to the 
number of people living in the area.  
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
52
  
  Water harvesting units (e.g. tanks, pipelines, guttering parts) are being 
researched taking into account Nauru’s environment such as the humidity and 
salinity of the air.   
 
Fourth Quarter Projection 
 
 
VI. NIUE 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU already signed by the Department of Environment and SPREP 
 
II] Start up funding  
 
Funding was received by the Bank on the 18
th
 August 2009 before being 
transferred to the Niue Governments Treasury Department. Funds were not 
available until the 20
th
 August 2009 as Treasury went through its processes of 
allocating relevant Account codes. 
 
III] Project Management Units 
 
 
PMU has been established at the Department of Environment 
 
IV] PACC Coordinator 
 
 
The PACC Coordinator is Mr. Haden Talagi. 
 
 
 
V] National Steering Committee 
 
The Niue Water Steering Committee (NWSC) will run both projects parallel 
(PACC Project and IWRM Project) to avoid duplication and repetition of activities. 
 
General Progress 
 
An Inception meeting/workshop was conducted on the 19
th
 August 2009 with the below 
mentioned participants as well as advisers and other relevant stakeholders in the private 
sector. This workshop had positive feedback however participants felt overwhelmed with 
certain technical, operational and requirement aspects of the workshop but were 
satisfied with the basic foundations of the PACC Project and the scope involved. 
 
Niue has developed a Draft Climate Change Policy as the Government has recognised 
the need for a coordinated approach to addressing Climate Change Issues. With the 
assistance of SPREP/SOPAC and with national stakeholders, this approach would 
demonstrate an effective and efficient use of limited resources to ensure resilience to 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
53
  
such changes, minimising adverse effects to resource management, food security and 
livelihoods on Niue.  
 
The draft policy has been developed through one-on-one consultations with relevant 
stakeholders and a multi-sectoral workshop that examined institutional and coordination 
arrangements that would help strengthen Climate Change activities on the island. This 
policy deals with mitigation and adaptation but has potential for more overarching 
initiatives. 
 
The PACC project and IWRM project will be managed by one Steering Committee with 
the PACC project implemented by Department of Environment and the IWRM project 
implemented by Public Works Department (Water Division). The EU-funded Water 
Support Officer would provide linkages between both projects. 
 
The Coordinator for the PACC Project was also able to attend the SGP/MAP/CBA 
Workshop held in Apia, Samoa from the 26
th
 August-02
nd
 September 2009. Participation 
to this meeting was funded by UNDP as one of the villages (Tuapa) has requested to be 
part of the water-tanks/rainwater-harvesting initiative funded under the SGP/CBA 
(Australian Initiative on Adaptation). The PACC Project has been asked to also assist 
with this program as part of community development, sharing information and efficient 
use of resources. More scoping is needed. 
 
Tools Development 
 
Development of the tools for the PACC Project has been limited to stakeholder 
consultations and Steering Committee Inception Workshop. The PACC Project and the 
IWRM (Integrated Water Resource Management) Project would be streamlined for more 
effective outcomes from consultations and the identification of relevant tools from these 
engagements.  
 
Guide Development 
 
Currently consulting with the IWRM project but this has been limited as the parallel 
projects go through Inception phases. A better understanding is needed on the scope of 
the guidelines and its development to capture the different stages of the PACC project 
for lessons learnt and gap analysis. 
 
Demonstration of Guide 
 
To date, information has been limited due to capacity constraints through the inception 
phase of the PACC project. A better understanding is needed on the scope of the 
guidelines. 
 
Technical Support  
 
In terms of mainstreaming, technical expertise were sourced from SOPAC and SPREP 
to conduct stakeholder consultations and draft Niue’s Climate Change Policy. The status 
of these officers highlighted the importance of a more coordinated approach to 
addressing the adverse effects of Climate Change for all stakeholders. 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
54
  
For the Pilot Demonstration, technical support and advice will be provided by the Water 
Division’s (PWD). The Manager for this division is also on the Niue Water Steering 
Committee as well as the Water Operations Advisor. Both are Niueans, trained overseas 
and are capable of implementing this important initiative.  
 
Steering Committee  
 
Niue Water Steering Committee (NWSC) to coordinate PACC and IWRM Project) 
activities and it was endorsed by Cabinet in June 2009. 
 
Name Designation 
Role 
Deve Talagi 
Director of Public Works Department 
Chairperson 
Sauni Tongatule 
Director of Environment Department 
Deputy 
Chairperson 
Sione Hetutu 
Water Quality officer 
Member 
Sionetasi 
Pulehetoa 
Director of MET Services 
Member 
Fa’apoi Akesi 
Director of Community Affairs (Women, Youth, 
Old Folks, NGOs) 
Member 
Brandon Pasisi 
Director Dept. Agriculture, Forestry & Fisheries 
Member 
Andre Siohane 
Manager Water Supply  
Member 
Clinton 
Chapman 
Water Operations Technical Adviser 
Member 
Sonya Talagi 
President Niue Chamber of Commerce 
Member 
Doreen Siataga 
Treasury Donor Projects Officer 
Member 
 
The Project Managers for both Projects will brief the relevant Ministers on a quarterly 
basis. Noted by Cabinet was the large size of the Committee Membership as previous 
experience from other projects has recognized smaller committees as being effective. 
However early steps by this new committee will be closely monitored for effective and 
efficient decision-making processes. 
 
Stakeholder Engagement: 
 
A Steering Committee Inception meeting/workshop was conducted on the 19
th
 August 
2009 and the Niue Golf and Sports Club. Invited to this meeting/workshop were all 
steering committee members and also technical officers from all relevant agencies. 
Invitations were also extended to the private sector through the Niue Island United 
Alliance of Non-Governmental Organisations (NUANGO) and the Niue Chamber of 
Commerce (NCOC). This stakeholder engagement was to provide historical background 
to Climate Change, timeline of activities and current status on Niue Island and the 
context of the PACC Project including objectives, strategies and activities of the Project. 
This meeting/workshop also provided details on issues for the NWSC to consider 
regarding the PACC Project and for technical advice from local expertise on issues. This 
was a great opportunity to put faces to names and the roles they will be playing in the 
important project. The Climate Change Policy consultations also took place in 
September 2009. 
 
 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
55
  
Decision Making Processes [Institutional and Pilot site and community level] 
 
The NWSC will meet following the Technical Meeting (Oct 2009) to establish and 
formalize decision-making processes that is outside of the Project Management Unit. 
The PMU will consult and finalize activities after the NWSC has held a meeting at the 
end of October. 
 
Fourth Quarter Projection 
 
 
VII. PALAU 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU has already been signed by the Office of Environment and Response 
Coordination and SPREP. 
 
II] Start up funding  
 
Funds for the initial phase have been received without any difficulties. These 
funds are currently in an account in the national treasury and have not been 
used.  Developing the face form has been difficult as we have not had the 
inception workshop. Currently we have been talking with the implementing 
partners and we are trying to develop an official work plan and log frame which 
then can be used to develop the face form. 
 
III] Project Management Units 
 
This project will be based out of the Ministry of Natural Resources, Environment 
and Tourism.  The PACC coordinator, with guidance from the steering 
committee, will be responsible for the organization and execution of the overall 
project. Implementing partners would be responsible for the execution of their 
individual projects within the overall project. 
 
IV] PACC Coordinator 
 
 
No Coordinator has been recruited during this quarter. 
 
V] National Steering Committee 
 
 
Not clear at present which Steering Committee would be used 
 
General Progress 
 
The officer designated to be the PACC Coordinator has taken up a post with the ADB 
and will be based in Manila. He was only in office for three months. Effort is now 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
56
  
underway to recruit another PACC coordinator. However, finding someone qualified is 
fairly difficult and will probably take time to do so.  
 
PACC is being implemented by the Office of Environmental Response and Coordination 
(OERC) and there is an overarching committee called the Climate Change Steering 
Committee. 
 
Due to administrative changes within the national government as well as the approach of 
the  end of the fiscal year, the implementation of the PACC project has not progressed at 
the desired pace.  A national inception workshop with all implementing partners has not 
taken place but informal talks with members have.  These informal talks are fairly 
important as they provide an opportunity to reengage and remind the implementing 
partners of their roles within the PACC project. This is important as it has been over a 
year since the development of the PACC proposal.  Some partners have started 
developing their own log frames, which will be incorporated into the national log frame. 
 
Within the month of October, an informal workshop is planned with all implementing 
partners.  Topics of discussion would include updates on the project and the execution 
of the implementation workshop.  Upon completion of the implementation workshop, 
which is also planned for October, we expect the completion of our national log frame 
and the immediate implementation of the project. 
 
Steering Committee  
   Ngedikes Olai Polloi 
Office of Environmental Response and Coordination (OERC) 
PO Box 100 
Koror, Palau 96940 
Phone: 
Email: 
 
Fred Sengebau 
Director, Bureau of Agriculture 
PO Box 100 
Koror, Palau 96940 
Phone 
Email: 
 
David Idip Jr. 
Program Manager, Palau Automated Land And Resource Information System 
(PALARIS) 
PO Box 100 
Koror, Palau 96940 
Phone: (680)488-6654 
Email: 
idipd@palaugis.org
 
 
Ngiratmetuchl Reagan Belechl 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
57
  
Chief Financial Officer, Office of Environmental Response and Coordination 
(OERC) 
PO Box 100 
Koror, Palau 96940 
Phone: 
Email: 
belechl@palaunet.com
 or 
nrbelechl@gmail.com
 
 
 
 
VIII. PAPUA NEW GUINEA 
 
Summary 
 
I] Memorandum of Understanding 
 
The MoU between PNG and SPREP is yet to be signed. 
 
II] Start up funding  
 
Not available as MoU is yet to be signed. 
 
III] Project Management Units 
 
 
Once MoU is signed then PMU establishment should follow. 
 
IV] PACC Coordinator 
 
Mr. Mika from Land Use has been identified as Coordinator for the PACC project. 
 
V] National Steering Committee 
 
Steering Committee that would be used as a policy oversight body for PACC is 
yet to be decided. 
 
General Progress 
 
SPREP is working with the Department of Climate Change and Land Use to get the MoU 
signed. 
 
Fourth Quarter Projection 
-
 
An informal workshop is planned with all implementing partners around October.  
Topics of discussion would include updates on the project and the execution of 
the implementation workshop.   
-
 
Upon completion of the implementation workshop, which is also planned for 
October, we expect the completion of our national log frame and the immediate 
implementation of the project. 
 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
58
  
IX. SAMOA 
 
Summary 
 
I] Memorandum of Understanding 
 
The MoU has been signed by the Ministry of Natural Resources and Environment 
(MNRE) and SPREP. 
 
II] Start up funding  
 
Funding was already available to Samoa during this quarter. There were no 
problems encountered during the transfer of funds from SPREP to the bank 
account with the Ministry of Finance.  
 
III] Project Management Units 
 
 
PMU has been established at MNRE, Land Management Division 
 
IV] PACC Coordinator 
 
Ms Moira Faletutulu was officially recruited as the National Coordinator for the 
PACC Samoa on August 26, 2009, and is based within the Land Management 
Division and will be working very closely with the Climate Change Division and 
PUMA Division of the Ministry of Natural Resources and Environment as well as 
the Ministry of Works, Transport and Infrastructure. 
 
V] National Steering Committee 
 
There is a PACC National Steering Committee already established and had their 
first meeting on the 24
th
 of July 09. 
 
 
Samoa PACC National Steering Committee 
Names Designation 
Organisation 
Contact 
details 
Taulealeausumai L Malua 
(Chairman) 
CEO – MNRE 
23800 ext 11 
Patea Loli M Setefano 
ACEO – Land 
Management Division 
23800 
Tagaloa Jude Kolhase 
ACEO – PUMA  
23800 
Vaaelua Nofo Vaaelua 
CEO – MWTI 
 
Noumea Simi 
ACEO – Aid Division, MoF
 
Rep from NGO’s 
SUNGO 
 
Easter Galuvao 
UNDP rep 
 
Sala Josephine Stowers 
ACEO – Legal Division, 
MNRE 
23800 
Rep from MWCSD 
Internal affairs division 
 
Anne Rasmussen 
PACC PEG rep 
20855 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
59
  
General Progress 
 
The main activities that have been undertaken over the reported quarter include the 
official signing of the Memorandum of Understanding between the Government of 
Samoa as represented by the Ministry of Natural Resources and Environment and 
SPREP; the recruitment of the National Project Coordinator, the endorsement of the 
Annual Work Plan for the remaining of 2009 by the National Steering Committee, as well 
as the commencement of the collation and desk review of the available baseline 
information. 
 
The receipt of the start-up funding of USD10,000 (equivalent of ST$25,601.74) was 
acknowledged by the Ministry of Finance on September, and has been utilized in the 
procurement of furniture and equipments for the setting up of the Project management 
unit. 
 
As per the approved AWP for 2009, the main activities that are currently underway as a 
rough start to developing the implementation guide include; (i) Review of the relevant 
CIMPs by the PMU and a report on the identified gaps will be prepared as the planned 
outcome of this activity.  (ii)Desk review of all relevant and available baseline information 
and (iii) Technical Specifications currently reviewed under the SIAM II Project funded by 
World Bank. 
 
A preliminary list of pilot demonstration sites have already been compiled, and will be 
shared with all relevant stakeholders during the Inception meeting planned for October 
19, 2009 for screening and final selection.  **Post tsunami tragedy – there MAY BE a 
change in the list.  The preliminary list already indicated includes the communities of 
Lalomalava, Gataivai, Tafitoala, Lotofaga, Fuluasou Stream and Vaisigano Riverside. 
 
 
Fourth Quarter Projection 
 
The planned activities in the pipeline include the Inception meeting and the National 
Steering Committee meeting commencing mid October towards the end of the month. 
 
 
X. SOLOMON ISLANDS 
 
Summary 
 
I] Memorandum of Understanding 
 
The MOU has been signed by the Permanent Secretary for the Ministry of 
Environment, Conservation and Meteorology and the Acting Director of SPREP. 
 
II] Start up funding  
 
Yet to be made available to Solomon Islands during this quarter 
 
III] Project Management Units 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
60
  
The PMU has been established at the Ministry of Agriculture and Livestock 
Division (MALD).  
 
IV] PACC Coordinator 
 
 
No Coordinator has been recruited during this quarter 
 
V] National Steering Committee 
 
During a briefing meeting with the Permanent Secretary of the Ministry of 
Environment, Conservation and Meteorology, it was agreed that a NCCCT that 
will consist of main line ministries and NGOs (including church and women 
groups) will be established. 
 
General Progress 
 
A project account was established with a commercial bank (Bank South Pacific). This 
account will hold all PACC funds transferred from SPREP, Apia through the Central 
Bank of Solomon Islands (CBSI). Signatories to this account are from MALD, MECM and 
Ministry of Treasury and Finance.  
 
Ms Jean Galo had been coordinating PACC Project work to date. Secondment of Jean 
to the  project for the coordinators post is not forthcoming from MALD, therefore the post 
will be advertised along with the project assistants post.  
 
Inception Workshop Preparation  
 
A national inception was proposed for early September but did not eventuate due to 
delay in transfer of funds. Hopefully it will be realized as soon as funds are accessed. 
The inception workshop will involve participants from all stakeholders of climate change 
including main line ministries, NGOs as well as church organizations.  
 
Liaison with Church of Melanesia on climate change issues in Ontong Java 
 
The Project had been liaising very closely with the Church of Melanesia for the issues in 
Ontong Java. Two church members also visited Ontong Java and had submitted a report 
about the impacts of climate change on the island which is very much similar to reports 
done by NMDO which is the basis of the PACC project and pilot site selection. Church of 
Melanesia is the only denomination on that island and had been a strong influence in the 
community. Thus, linking with COM in PACC implementation is an advantage for the 
project as COM already has its network and a shipping service that links Ontong Java to 
the capital.   
 
Critical Issues 
 
Securing the Project Coordinator 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
61
  
Conditions of employment for project coordinators must include housing to attract even 
government technical officers. There should also be room for Govt responsibilities to be 
built in to the TOR of Project Managers or Coordinators where technical knowledge is a 
major requirement for a project manager or coordinator. In this way, even where there is 
staff shortage with government ministries, secondment is facilitated. 
 
Involvement of UNDP Honiara Sub office 
Solomon Islands Government would like the involvement of UNDP Honiara Sub Office in 
the PACC project if this arrangement will assist in facilitating smooth transfer of funds. 
 
 
Fourth Quarter Projection 
 
Policy Development:  The PACC Project will co-finance the development of a climate 
change policy with EU. PACC will also provide some financial assistance towards 
mainstreaming climate change into Agriculture policy.  
 
 
 
XI. TONGA 
 
Summary 
 
I] Memorandum of Understanding 
 
The MoU has been signed by the Director Ministry of Environment and Climate 
change and SPREP. 
 
II] Start up funding  
 
Start-up funding of US$10,000 has just been deposited to a general account for 
GEF funded project in Tonga and they are now in the process of isolating the 
fund to a separate vote. 
 
III] Project Management Units 
 
The PACC PMU has been established in the Ministry of Environment and 
Climate change. 
 
IV] PACC Coordinator 
 
The recruitment process of the Project Coordinator is underway and 
hopefully he/she should be on board by December and that the actual 
implementation of the project is rescheduled to January next year. The 
2009 AWP has now been reviewed so that it takes on some of the 
activities planned for this year.  
V] National Steering Committee 
 
 
Not clear at present which Steering Committee would be used 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
62
  
 
General Progress 
 
During this quarter, the Department of Environment (Focal Point and Implementing 
Agency for PACC) has been upgraded to a Ministry of Environment and Climate Change 
(MECC). The MECC is now in the process of getting laws and legislation passed and 
return for implementation and enforcement. This is an opportunity for the PACC project 
to also contribute to the mainstreaming of climate change into some of these legislations.  
 
A paper was presented to the Tongan Cabinet for Ministers information and 
approval. The project was approved the Cabinet in mid-September 
 
Fourth Quarter Projection 
 
 
 
XII. TUVALU 
 
Summary 
 
I] Memorandum of Understanding 
 
The MoU is already signed by the Director of Environment and SPREP 
 
II] Start up funding  
 
Start-up funds yet to be received when quarter ended. 
 
III] Project Management Units 
 
 
The Public Works Department in close collaboration with the Ministry of 
Natural Resources and Environment decided to locate the project under 
the Ministry of Water, Works and Energy since PACC focuses on water as 
its main thematic area. This is to make it easier for the coordination and 
implementation of all water related activities.
 
 
IV] PACC Coordinator 
 
 
Ms Loia Tausi has been recruited as the PACC Coordinator. 
 
V] National Steering Committee 
 
There is an existing National Water and Sanitation Committee (NWSC) 
which the IWRM and the PACC will re-engage them as their Steering 
Committee to oversee both the projects to avoid duplication and repetition 
of activities. This committee consist of main line ministries and NGOs 
including some key community members.
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
63
  
General Progress 
 
Soon after the Inception workshop, the existing National Water and Sanitation 
Committee were presented with an update of the inception workshop and this was where 
different governmental decision makers and NGO’s re-designed the project requirement 
which is agreed upon in the signed Memorandum of Understanding 
 
Recruitment process for the PACC Coordinator took quite sometime but it is now filled 
even though no contract has been signed. Ms Loia has been verbally informed of her 
recruitment but have yet to sign any contract.  
 
Setting up of the Project Management office should happen upon the return of the PACC 
Coordinator from the Technical Meeting held in Suva. Equipment have not been 
procured due to slow progress in fund transfer SPREP.  
 
Fourth Quarter Projection
  
1.
  Set up Project Management Unit
  
2.
  Re-engagement of the existing National Water and Sanitation Steering 
Committee
  
3.
  Collect baseline information in preparation for the inception workshop 
 
4.
  In country inception workshop
  
5.
 Community 
consultation
  
6.
  Develop communication strategy
  
7.
  Review existing legislation and policy framework
  
 
XIII. VANUATU 
 
Summary 
 
I] Memorandum of Understanding 
 
MoU has been signed by the Director Vanuatu Meteorology Department and the 
Acting Director, SPREP 
 
II] Start up funding  
 
Confirmed that PACC Start up funds is now with Reserve Bank of Vanuatu 
[RBV] 
 
III] Project Management Units 
 
 
PMU has been established within the Meteorology Department 
 
IV] PACC Coordinator 
 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
64
  
A Coordinator and his assistant have been recruited during this quarter 
 
V] National Steering Committee 
 
 
National Advisory Council on Climate Change (NACCC) 
General Progress 
 
  Amendment and finalization of MoU and Payment Process 
  Signing of MoU and Payment Process and submission to SPREP 
  Receipt of advice of transfer of funds from SPREP 
  Confirmation of receipt of Funds from RBV 
  Incorporate two [ PACC Coordinator & Assistant Coordinator] new position to 
Climate Change Office 
  Amendment of PACC National Coordinator and Assistant Coordinator 
Contract and submission for comments 
  Development of PACC Project Profile for Prime Minister’s Office clearance. 
 
Fourth Quarter Projection 
 
  Project Management Unit office set up 
  Contract 2 project staff  
  National Inception Workshop 
  Pilot Community Consultation 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
65
  
Partners SOPAC/IW
RM 
SPC SPREP 
Partnerships 
AusAid-ICCAI EC-GCCA USP 
FSPI 
NOAA 
IUCN 
Contacts (to complete) 
  
  
  
  
  
  
  
  
  
Support areas: 
  
  
  
  
  
  
  
  
  
Demo implementation 
support in thematic 
areas 
(technical support, 
training, equipments, 
etc.) 
  
  
  
Complement 
activities in the 
PACC 
demonstration 
sectors, 
locations, or help 
replicating in 
other locations 
GCCA - 
USP 
Proposal: 
targeted 
training, 
community 
engagemen
  
  
  
  
SPC-GTZ 
Partnership: 
Vanuatu-, 
landuse 
planning, 
AusAid project 
(ending this 
year) – use 
best practices, 
Disaster 
preparedne
ss 
Coastal management 
(Cook Islands, FSM, 
Samoa, Vanuatu) 
  
SPC Marine 
Division –
AusAid project 
  
  
Vanuatu - 
GCCA Pilot 
Experience 
from 
CDAMPIC 
Reef 
restoration, 
ICZM, 
community 
work, 
sustainable 
tourism 
(Oceania 
Ssustainabl
e Tourism 
Alliance), 
AusAid – 
CC Science 
Programme
- Tourism 
Adaptation 
research 
  
Ecosystem-
based 
adaptation 
(mangroves, 
corals), coastal 
community 
based 
management 
(experiences 
from Indian 
Ocean), DRM 
Food production/security 
(Fiji, Palau, PNG, 
Solomon Islands) 
  
Center for 
Pacific Crops 
and Trees, 
Center of 
Excellence for 
Atoll 
Agriculture 
  
  
  
  
Pan-Pacific 
Food 
Programme 
  
Fiji just became 
an IUCN 
member 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
66
  
(Kiribati) 
SPC-GTZ-
Partnership: 
Fiji - agro 
forestry 
project 
  
Water resources (Nauru, 
Niue, Tonga, Tuvalu, 
Marshall Islands) 
Linkages 
between 
IWRM and  
PACC in  
participating 
countries. 
AusAid project 
(ending this 
year) – use 
best practices, 
UNDP funded 
M&E part 
  
Complemen
t water 
sector 
sustainabilit
y activities 
in demo 
areas and 
topics 
SPC-GTZ 
partnership:  
Tonga- land 
use planning 
  
  
EU - Water 
Sector 
Support 
Projects 
CDAMPIC - 
lessons learnt 
Health 
issues 
  
Water-shed 
management 
(ecosystem-
based) 
CC mainstreaming 
(policy work) 
Link with 
Water 
sector 
strategies 
  
  
Assist to 
incorporate 
PACC outcomes 
to national 
strategies 
Vanuatu - 
GCCA pilot, 
USP 
Proposal 
  
 
PaCIS 
  
Institutional 
strengthening and 
capacity building 
Link with 
national 
water 
boards, 
technical 
committees, 
  
  
AusAid-Future 
Climate Leaders 
Programme – 
scholarships, 
links with SGP-
CBA, 
GCCA - 
USP 
Proposal: 
targeted 
training and 
courses 
GCCA - USP 
proposal 
Center for 
financial 
accountabili
ty (NGOS 
and small 
businesses) 
Supporting 
Met stations ( 
rain gauges, 
measurement)
, Tools for 
sector-specific 
Application of 
CRISTAL tool 
background image
 
GEF/UNDP/SPREP PACIFIC ADAPTATION TO CLIMATE CHANGE PROJECT 
67
  
  
USP-SPREP 
– training: 
community 
development 
(Vanuatu) 
Vanuatu 
Pilot (NAPA 
Follow up) 
  
GCCA – 
community 
engagemen
  
IWRM 
PMUs 
Strengthening 
Pacific 
Meteorological 
Services 
 
  
Community 
developme
nt 
climate 
information 
Pacific CC 
Science and 
Research 
Programme 
(Inauguration 
Workshop in 
October 2009), 
Info 
exchange, 
National 
Climate 
Services, 
Pacific 
Climate 
Information 
System – 
PaSYS. 
Australia-Pacific 
Climate 
Adaptation 
Platform 
Pacific RISA – 
Pacific Islands 
Regional 
Integrated 
Science and 
Assessment 
Programme, 
  
 
 
 
Knowledge sharing, 
awareness, research 
Link with 
IWRM good 
practice 
and 
knowledge 
sharing 
activities 
  
UNITAR C3D+, CC 
explorer 
 
GCCA - 
USP 
Proposal: 
applied 
research 
  
Google 
Ocean 
 
Google Earth - 
Ocean 
Others