background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
1
 
 
 
 
 
 
 
 
Tsunami Recovery Priority Plan 
 
 
 
 
 
 
 
 
 
 
 
Niuatoputapu  
Kingdom of Tonga 
 
 
 
October 2009 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
2
 
Table of Contents 
 
 
 
EXECUTIVE SUMMARY  …………………………………………………….………. 3 
SECTION 0: 
ACRONYMS AND ABBREVIATIONS  ……………………………………………. 4 
SECTION 1:  
INTRODUCTION  ………………………………………………………………………… 5 
  1.1  Background  ……………………………………………………………………… 5 
  1.2  Scope and Content  ………………………………………………………….. 7 
 
1.3  Goal  …………………………………………………………………………………  8 
 
1.4   Guiding principles  …………………………………………………………….  8
 
SECTION 2:  
COORDINATION ARRANGEMENTS  …………………………………………….  9 
SECTION 3:  
DAMAGE ASSESSMENTS AND PRIORITIES FOR RECOVERY  ……….. 11 
 
3.1  Damage assessments  ………………………………………………………. 11 
 
3.2   Initial priorities  ……………………………………………………………….. 11 
 
3.3  Sectoral analysis  ……………………………………………………………..  12 
 
3.4  Logistics  ………………………………………………………………………….  16 
 
3.5  Recovery strategies and actions matrix …………………………... 18 
SECTION 4: 
FUNDING ……………………………………………………………………………..….  23 
SECTION 5: 
RISK ANALYSIS  ………………………………………………………………………… 23 
SECTION 6:    
NEXT STEPS  …………………………………………………………………………….. 23 
SECTION 7:    
CONCLUSIONS  …………………………………………………………………………  22 
 
ANNEX 1:  Immediate and long term needs ……………………………..………………………. 25 
ANNEX 2:  Summary of indicative external assistance  ……………………………………… 33 
ANNEX 3:  Table of estimated damages  ……………………………………………………………  35 
ANNEX 4:  Map of Tonga, Niuatoputapu and Tafahi  …………………………………………  37 
ANNEX 5:  Template for thematic working groups  ……………………………………………  39 
ANNEX 6:  NTT community survey  ……………………………………………………………………  40 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
3
 
 
 
Executive summary 
 
The Kingdom of Tonga consists of 169 islands, clustered into three main groups ‐‐  Tongatapu, 
Ha'apai, and Vava'u ‐‐ with a total population of 120,898 people.  The total land area is 748 
square kilometers with an EEZ of 700,000 square kilometers. Niuatoputapu is one of the two 
inhabited Islands in Tonga’s Niua group, with an estimated floating population of 850 to 1000 
people. 
 
On Wednesday, 30
th
 of September 2009, at 06:50 a.m., an earthquake of 8.3 magnitude 
centered slightly off Samoa was felt in the island of Niuatoputapu, with turbulence lasting for 20 
minutes. Five minutes after the long turbulence, three six‐meter tsunami waves struck the 
islands at three minutes intervals, travelling 600 meters inland, causing major impacts in 
Niuatoputapu and some damages on the neighboring island of Tafahi. 
 
An initial assessment report confirms nine dead, four people seriously injured, 60% of housing 
destroyed and extensive damage to buildings and other infrastructure.   While most of the boats 
on the Island of Niuatoputapu were destroyed, the tiny island of Tafahi lost all its boats, which 
were the only means of transportation to Niuatoputapu, and were also used for fishing. The 
water and sanitation systems on Niutoputapu were completely devastated by the tsunami, and 
the reef and lagoon left heavily silted.  
 
Given this sudden disaster situation, with the population displaced and having lost their houses, 
possessions and means of livelihood in many cases, diverse offers of international assistance 
were offered to the Tongan government.  Recognizing the need for donor coordination as well 
as the importance of an overall strategy for the design and implementation of the recovery 
process, the government requested UNDP’s assistance in developing this Tsunami Recovery 
Priority Plan.  This plan is fully aligned with the government of Tonga’s existing national strategic 
plans, and links with ongoing related development projects. 
 
The aim of this document is to set out a framework for action and accountability to ensure that 
a wide range of support is available to those affected. This will act as a catalyst for people taking 
action toward self‐help, to enable communities rebuilding their lives. 
 
  
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
4
 
 
Section 0.  Acronyms 
 
 
AMD ‐ Aid Management Division of the Ministry of Finance and National Planning  
DALA ‐ Damage and Loss Assessment 
DRM – Disaster risk management 
DRR – Disaster risk reduction 
ECLAC – United nations’ Economic Commission for Latin America and the Caribbean 
EEZ – Exclusive Economic Zone 
ER – Early recovery 
FAO – United Nations Food and Agriculture Organization 
HIES – Household Income and Expenditure Survey 
IOC – Inter‐governmental Oceanographic Commission 
ISDR – International Strategy for Disaster Reduction 
JICA – Japanese International Cooperation Agency 
MOH – Ministry of Health 
MOW – Ministry of Works 
MLSNRE ‐ 
Ministry of Lands, Survey, Natural Resources and Environment
 
NAP – National Action Plan 
NEMO – National Emergency Management Office 
NERC – National Emergency Recovery Committee 
NTT ‐ Niuatoputapu 
NZ – New Zealand 
SOPAC – Pacific Islands Applied Geoscience Commission 
SPC – Secretariat of the Pacific Community 
TCC – Telecommunications Company 
TDS – Tonga Defense Services 
TRPP – Tsunami Recovery Priority Plan – Niuatoputapu Tonga 
UNDP – United Nations Development Programme 
UNESCO – United Nations Education, Social and Cultural Commission 
UNFPA ‐ United Nations Fund for Population 
UNICEF ‐ United Nations Children’s Fund 
WHO – World Health Organization 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
5
 
 
 
Section 1.  Introduction 
 
The  Government  of  Tonga  has  put  together  this  Tsunami  Recovery  Priority  Plan  for 
Niuatoputapu and Tafahi after the islands were hit by the tsunami on 30 September 2009.  This 
work was led by Government with timely support from UNDP, which is fully acknowledged. 
 
The  plan  will  guide  the  recovery  phase  for  Niuatoputapu  in  order  to  restore  the  basic 
foundations that will allow people to rebuild their lives and return to normalcy
, and thereby 
paving the way for longer term development.  To achieve this, a number of key players need to 
work  together,  including  Government,  external  development  partners,  civil  society,  and  the 
people  of  the  islands  themselves.  Government  is  confident  that  through  the  spirit  of 
cooperation  and  partnership,  the  rehabilitation  phase  will  be  implemented  successfully  in 
restoring the livelihoods of the people of Niuatoputapu and Tafahi. 
 
It  should  be noted that  this  plan  is  a  work  in  progress,  and  can  be  enriched  and  expanded  as 
further assessments, in‐depth sectoral analysis and corresponding refinement of strategies are 
undertaken. 
 
 
Section 1.1. Background 
 
The Kingdom of Tonga consists of 169 Islands with a total population of 120,898 people. Tonga 
stretches over a distance of about 800 kilometers (500 miles) in a north –south line. The islands 
lie south of Samoa, about one third away from New Zealand and Hawaii. The country consists of 
a series of islands, clustered into three main groups: Tongatapu, Ha'apai, and Vava'u; these were 
formerly known as the Friendly Islands. The total land area is 748 square kilometers (289 square 
miles) with an EEZ of 700,000 square kilometers. Economically, Tonga relies on heavily on 
remittances from half of the country’s population residing chiefly in Australia, New Zealand and 
United States. In rural areas, most of the people work on plantations and in subsistence 
agriculture, mainly coconuts, taro, yams, vanilla beans and bananas, which are also major cash 
crops.  Small livestock such as pigs and chickens are also raised by families. 
 
A new Household Income and Expenditure Survey (HIES) has just been conducted in Tonga, so 
the related analysis of that data should be completed shortly.  Once this is ready, that analysis 
should help to inform the recovery planning and programming.  
 
Niuatoputapu is one of the two inhabited Islands in Tonga’s Niua group, with an estimated 
floating population of approximately 850 to 1000 people or more, which fluctuates depending 
on seasonal movements relating to employment, family and church activities. The inhabitants of 
the island reside near the broad lagoon on the north side of Niuatoputapu. The island also 
serves as a main port of entry for yachts and other shipping arriving from Samoa and beyond.   
 
On Wednesday, 30
th
 of September 2009, at 6.50am an earthquake of 8.3 magnitude centered 
slightly off Samoa was felt in the island of Niuatoputapu and the turbulence last for 20 minutes. 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
6
Five minutes after the long turbulence, three giant waves struck the Islands at three‐minute 
intervals, with the third wave measuring six meters and traveling 600 meters inland, causing 
major damages in Niuatoputapu and some damage on the neighboring island of Tafahi. 
 
Report from the initial assessment conducted confirms nine dead, four people seriously injured 
and extensive damage to buildings and other infrastructure.   The island has a total of 255 
private residences, of which 79 were totally destroyed and 56 partially damaged. Most of the 
public utilities and government buildings on the island were completely destroyed. While most 
of the boats on the Island of Niuatoputapu were destroyed, the tiny island of Tafahi lost all its 
boats, which were the only means of transportation to Niuatoputapu, and were also used for 
fishing. The water and sanitation systems on Niutoputapu has been completely devastated by 
the tsunami, and the reef and lagoon have been heavily silted.  
 
During the immediate post disaster phase, emergency relief for the affected population was 
efficiently provided the Government of Tonga and its citizens, the Tongan Defense Service, the 
Churches, Red Cross, France, Australia and New Zealand.  As traditionally happens in the Pacific, 
many family‐to‐family aid packages were sent by relatives out to Nuiatoputapu, and the priority 
shipment of these packages was facilitated by NEMO and TDS.  
 
The only hospital on the island of Nuiatoputapu was destroyed by the tsunami. Only the outer 
structure of the building remains standing, but all furniture, equipment and supplies were 
ruined.  A temporary clinic has been setup to address the medical needs of the local people. A 
list of the equipment urgently required to restore the basic operations of the clinic ‐‐ such as the 
cold chain equipment, generator, water tank and autoclave – has been prepared and shared 
with donors.  Immediate health risks such as dengue, measles, diarrhea have so far not been 
observed on the island, except for destroyed and overflowing septic tanks in the area, which the 
government has been spraying to control risks.  The affected people have access to psycho‐
social support provided by the Church Minister and Red Cross staff on the Island. 
 
In the education sector, primary school buildings in the villages of Hihifo and Falehau, which  
were partially damaged by the tsunami, are being rebuilt by the TDS for temporary use. 
However, there is an imminent need for permanent reconstruction. The high school was not 
damaged, and has been used by the Government as the emergency operation centre.  
    
The main source of income on the island of Niuatoputapu and Tafahi include mat weaving, 
government employment, and remittances received from relatives residing overseas. Mat 
weaving is a practice traditionally undertaken by women’s groups, in which pandanus leaves are 
collected and soaked in sea water, dried, then weaved into final products in private houses. It 
should be noted that these fine mats have extraordinary cultural significance and value in 
Tonga, and are used for clothing on special occasions, floor covering and other daily uses. The 
mats command a high price on the national and international markets and are one of the main 
sources of cash income on NTT.  It appears from the initial assessment that six houses or sheds 
used for weaving mats have been damaged, but the weaving of mats could still continue to be a 
profitable business for women as some pandanus leaves are still intact. The economy of 
Niuatoputapu and Tafahi is mainly subsistence based, relying on fishing, agriculture and 
livestock for family consumption. While crops and livestock on mainland have not been severely 
affected, according to preliminary reports, most of the boats have been lost. Collection of 
shellfish and sea cucumbers from the reef area at low tide, which is normally done by women, is 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
7
expected to have seen major setbacks, since the coral reef has been covered with silt from the 
tsunami waves.  
 
The Government of the Kingdom of Tonga quickly organized a mission to Niuatoputapu on 
October 3 to obtain a preliminary overview of the extent and the impact of damages caused by 
the recent earthquake and tsunami, and to identify gaps in humanitarian assistance that could 
be met through donor contribution.  
 
As per the initial overview and the series of briefing sessions held at the Tonga Defense Service, 
it has been reported that widespread damage has occurred to medical facilities, infrastructure 
and residential areas in low lying coastal villages of NTT, and to a lesser extent Ha’apai.  
 
International (humanitarian) partners such as Australia and New Zealand, together with local 
NGOs, have significantly contributed towards addressing some of the immediate needs of the 
affected population.  See Annex 2 for a summary of the external assistance provided to Tonga 
by development partners after the tsunami. 
 
On October 16, the Chief Secretary and Secretary to the Cabinet and the Commander of Tonga 
Defense Services officially announced the closing of the tsunami emergency phase, and moving 
into the early recovery phase.   However, as to be expected, while the recovery process is being 
launched, there are still several humanitarian and relief activities yet to be fully completed.  
  
It should be noted that the tsunami affecting Tonga struck the country only two months after 
the tragic sinking of the Princess Ashika inter‐island ferry, which claimed 87 lives and led to a 
formal inquiry into the causes and impacts of that disaster.  The combination of these two 
disasters so close together compromised the nation’s resilience, hampering the capacity of the 
government and population for recovery. 
 
 
 
1.2  Scope and content 
 
This  document  sets  out  a  multi‐sector  integrated  framework  for  prioritizing  and  designing 
activities  in  a  centralized  fashion,  and  across  line  Ministries,  for  the  substantial  task  of  early 
recovery  from  the  effects  of  the  disaster.  It  identifies  overall  guiding  principles  as  well  as 
national priority  areas  and  issues,  sector  by  sector,  arising  from  the  information  available  and 
the assessments to date. It presents a recovery action matrix with measures and actions to be 
carried out by line ministries and other stakeholders over the course of the recovery period. The 
recovery action matrix will be used to focus resources and to monitor progress.  
 
It  must  be  noted  that  this  Tsunami  Recovery  Priority  Plan  (TRPP)  should  be  adjusted  and 
updated as further assessments are completed and made available, to reflect and capitalize on 
those valuable inputs. 
 
The  ongoing  recovery  phase  is  expected  to  last  approximately  24  months:    October  2009  – 
September  2011.    The  first  six  months  of  this  period  can  be  considered  “early  recovery.”  The 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
8
National  Emergency  Recovery  Committee  (NERC)  will  monitor  the  progress  of  the  recovery 
phase and ultimately determine when this phase is officially concluded. 
 
This  TRPP  is  fully  aligned  with  and  contributes  to  implementation  the  Kingdom  of  Tonga’s 
Strategic Development Plan 8, in particular its goal 7: “ensure environmental sustainability and 
disaster risk reduction.”  Under this goal, the TRPP can make a vital contribution to strategy 5: 
“improve the capability of communities to be more resilient to disasters.”  
 
In addition to the Strategic Development Plan 8, Tonga has also prepared a National Strategic 
Planning Framework as of February 2009, with the purpose of guiding planning over a longer 
term of 5‐10 years.  This plan focuses on a limited number of uniquely national or whole of 
government priorities, with a vision for the future based on creating a Tonga “where 
opportunity exists for all.”  This Tsunami Recovery Priority Plan aligns with the priorities stated 
in the National Strategic Planning Framework, specifically contributing to two of its primary 
outcome objectives:  “facilitate community development by involving district/village 
communities in meeting their service needs,” and “integrate environmental sustainability and 
climate change into all planning and executing of programs.”  The TRPP makes a substantial 
contribution to one of four enabling themes set out under the National Strategic Planning 
Framework, namely:  “ensure a more coordinated whole of government approach to donor 
funding.”  
  
This TRPP is also in line with the National Emergency Management Act, as detailed in section 2. 
 
The recovery plan will also link to and leverage existing related projects, such as the  National 
Action Plan process initiated this year by NEMO with support from SOPAC.  
 
 
1.2. Goal  
 
The overarching goal for the recovery phase is to restore the basic foundations that will allow 
people  to  rebuild  their  lives  and  return  to  normalcy
,  thereby  paving  the  way  for  longer‐tern 
development.  The aim of this document is to develop a framework for action and accountability 
to ensure that a wide range of support is available to those affected. This will act as a catalyst 
for people taking action toward self‐help, to enable communities rebuilding their lives. 
  
Considering the remote and inaccessible location of the islands affected, a major effort will be 
required  to  inform  and  engage  affected  communities  with  respect  to  issues  and  decisions 
concerning the fundamental rehabilitation of their lives, livelihoods and community facilities. 
 
 
 
1.3. Guiding principles 
 
Experience shows that there are several overall principles which are fundamental for guiding 
effective and sustainable early recovery. These principles will be observed both in the more 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
9
immediate actions, and in the medium term actions envisioned under this strategy. These 
include: 
 
maximize  synergies  among  different  actors  through  efficient  coordination  of 
stakeholders in the early recovery process 
 
guarantee national ownership by the fullest possible engagement of national and local 
authorities in the planning , execution and monitoring of recovery actions 
 
“build back better” to ensure that shelter, infrastructure and systems are more resilient 
to better protect people and communities, and so as not to rebuild the risk  
 
promote  local  and  national  capacities  by  ensuring  that  external  technical  assistance 
complements rather than replaces existing capacities, and is seen by national actors as 
supportive rather than directive  
 
promote  gender  equality  by  assessing  particular  needs  and  vulnerabilities,  and  by 
acknowledging and using women’s varied capacities and skills 
 
use  and  promote  participatory  practices  to  identify  needs,  build  capacities  for 
empowering  communities  and  create  the  foundations  of  sustained,  free,  active  and 
meaningful participation through out all phases of the early recovery process 
 
monitor,  evaluate  and  learn  through  appropriate  participatory  techniques  and 
mechanisms  that  allow  timely  identification  of  corrective  measures,    and  capture  the 
experiences and voices of the target population 
 
In  addition,  in  the  case  of  tsunami  recovery  for  Niuatoputapu,  three  context‐specific  criteria 
were identified to guide the early recovery strategy: 
 
 
Facilitate recovery in such a way that the outer island of Niuatoputapu does not become 
dependent  on  external  aid,  and  therefore  can  conserve  its  traditional  and  necessary 
self‐reliance.  
 
Rebuild  and  re‐equip  the  community’s  basic  infrastructure  and  assets  with  similar 
traditional  styles  and  quality,  avoiding  distortions  of  the  local  culture  or  an  artificial 
increase in the standard of living as compared to the pre‐disaster situation. 
 
Encourage initiatives which engage the affected population in clean‐up, reconstruction 
or  disaster  reduction  activities,  for  their  empowerment  as  agents  in  the  recovery 
process  and  to  help  overcome  any  lingering  psycho‐social  trauma  through  positive 
actions. 
 
 
Section 2.   Coordination arrangements  
 
In  2007,  the  Kingdom  of  Tonga  approved  its  first  ever  Emergency  Management  Act.  This  Act 
establishes that in the event of a significant  disaster affecting Tonga.  The  National Emergency 
Operations Committee takes charge of the response and emergency relief efforts, and when the 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
10
emergency  phase  is  concluded  and  the  recovery  phase  initiated,  the  National  Emergency 
Recovery Committee (NERC) leads the recovery strategy and implementation. The Act indicates 
that the NERC has the following functions: 
a)
 
 coordinate the recovery phase following any event; 
b)
 
 carry out detailed assessments in partnership with the relevant committee; 
c)
 
 coordinate the provision of emergency relief; and 
d)
 
 coordinate all recovery and rehabilitation works. 
The National Emergency Recovery Committee consists of the following members:  the Minister 
of  Works  as  Chair,  Chief  Secretary  and  Secretary  to  Cabinet,  Secretary  for  Finance,  Director, 
Secretary  for  Foreign  Affairs,  Commander  of  Tonga  Defense  Services;  representatives  of  non‐
governmental organizations who may be co‐opted as required; and the Manager who shall be 
Secretary. 
 
Following the tsunami, the NERC was activated.  Declaration of a District State of Emergency for 
Niuatoputapu  was  issued  the  same  day  that  the  tsunami  struck.    Subsequently  the  NERC 
established a sub‐committee – comprised of Aid Management Division (Ministry of Finance and 
National  Planning),  NEMO,  Secretary  to  Foreign  Affairs  as  Chair,  and  other  agencies  to  be  co‐
opted  as  needed  ‐‐  to  synthesize  the  discussion  on  early  recovery  strategies  and  entry  points 
and on that basis to propose the national priorities. These are presented in section 3.2. 
 
While  the  NERC  plays  the executive  role  for  the early  recovery  phase,  providing  direction  and 
making  decisions  on  policy  options,  the  operationalization  of  the  early  recovery  programming 
will be coordinated jointly by the National Emergency Management Office (NEMO) and the Aid 
Management  Division  from  the  Ministry  of  Finance  and  National  Planning.    The  Director  of 
NEMO will serve as secretariat for gathering information related to assessments and needs, as 
well  as  the delivery of aid  items  and actions.  Aid Management Division  (AMD)  will liaise  with 
donors  and  maintain  updated  detailed  tables  of  status  on  the  aid  requested  and  received.  
Regular monitoring of the recovery initiatives will also be conducted by AMD. UNDP will provide 
some support to these AMD functions through an additional short‐term staff person. 
 
To  facilitate  the  recovery  strategizing  and  detailed  planning,  thematic  working  groups  have 
been  established  for  the  key  sectors  affected  which  require  further  analysis  and  careful 
assessment of policy options, due to their complexity.  The general structure for these working 
groups  requires  that  they  are  led  by  the  respective  line  ministry  from  that  sector,  with 
membership  comprised  of  civil  society  organizations,  national  and  international  NGOs,  United 
Nations agencies, and other organizations with expertise in that sector.   A representative of Aid 
Management  Division  will  sit  on  each  thematic  working  group,  so  as  to  facilitate  systematic 
linkages into the centralized recovery program. 
 
The mandate of these thematic working groups will be to provide an assessment of impacts in 
the  sector,  elaborate  a  range  of  policy  options  for  recovery  in  that  sector,  advise  on  possible 
technical  solutions,  and  develop  project  proposals  to  secure  donor  funding  for  the  chosen 
solutions and activities.  The thematic working groups will report to the NERC.  Project proposals 
to be developed by these working groups should provide costing, indicating the costs of items to 
be replaced in order to return to the pre‐tsunamis standard of living, and as a separate item, the 
incremental expenditure required for improvement or increased resilience. 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
11
 
To address the recent tsunami impacts, thematic working groups have been set up to cover the 
following key and complex sectors:  resettlement/relocation, health, water and sanitation, and 
early warning systems.  
 
Some other key sectors – such as infrastructure and education – were also significantly impacted 
by the disaster.  However, the needs for reconstruction and recovery assistance to these sectors 
seems more clear cut, and the related programming on course, so accordingly thematic working 
groups have not been set up at this time to address these sectors. 
 
 
 
 
Section 3.  Damage assessments and priorities for recovery 
 
3.1.
 
Damage assessments 
 
A  government  assessment  team  led  by  Lord  Ma’afu  as  national  Controller,  and  including  the 
Princess  Regent  and  the  Acting  Prime  Minister,  conducted  a  field  visit  to  Niuatoputapu  on  3 
October,  to  obtain  an  overview  of  the  extent  of  damages  and  losses,  and  the  situation  of  the 
affected population.  Lord Ma’afu stayed on in NTT to take charge of the ground operation. 
 
A government technical assessment team was dispatched to NTT on October 20‐22 to accelerate 
the  assessment  and  planning  for  potential  resettlement  of  the  population  in  a  safer  location. 
This team  was comprised  of engineer, surveyor, architect and GIS  expert form the  Ministry of 
Lands,  Survey,  Natural  Resources  and  Environment,  as  well  as  the  Habitat  for  Humanity 
representative. While there, the team also facilitated a rapid community consultation conducted 
by  local  government  officials,  to  get  a  general  sense  of  the  community’s  concerns  and 
preferences  in  regard  to  complex  issues,  such  as  sanitation  arrangements  and 
housing/relocation scenarios. 
 
More  detailed  and  specialized  damaged  and  loss  assessments  by  sector  will  be  organized  and 
conducted by the thematic working groups, as needed.  The NERC will determine whether any 
further  overall  assessments  are  required,  such  as  socio‐economic  impact  assessments,  macro‐
economic  assessments,  assessments  by  tsunami  scientists,  the  ECLAC  Damage  and  Loss 
Assessment (DALA), or others.   
 
 
 
 
3.2 Initial priorities 
 
Consensus  among  all  stakeholders  identifies  the  following  priority  sectors  for  recovery 
programming.  These  sectors  and  the  relevant  prioritized  solutions  are  listed  in  order  of 
importance: 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
12
Ranking 
Sector 
Phased actions in sequence 
Resettlement/relocation 
 
-
 
Rapid community consultation 
-
 
Temporary housing 
-
 
Safe community shelters 
-
 
Relocation of hospital 
-
 
Permanent disaster resilient private housing  
 
Sanitation 
 
-
 
Rapid community consultation 
-
 
Temporary sanitation facilities 
-
 
Permanent  sanitation  systems  linked  to 
resettlement design 
 
Livelihoods re‐activation 
 
-
 
Rebuilding of sheds for mat weaving 
-
 
Purchase of fishing boats and equipment 
-
 
Replanting of pandanus plants along coast 
 
Early warning systems 
 
-
 
Adjustments  to  improve  effectiveness  of 
current early warning system 
-
 
End‐to‐end review of EWS to  develop optimal 
system 
 
Government buildings 
 
-
 
Reconstruction  of  offices  using  prefabricated 
structure 
-
 
Construction of multi‐use storage warehouse 
 
 
 
 
3.3. Sectoral analysis 
 
Resettlement/relocation 
Composition  of  thematic  working  group:    led  by  Ministry  of  Lands,  Survey,  Natural  Resources 
and  Environment.    Members  include  Ministry  of  Works,  Tonga  Red  Cross,  Tonga  National 
Women  and  Children’s  Centre,  Ma’a  Fafine,  Habitat  for  Humanity,  UN‐Habitat,  Rooftops,  Aid 
Management Division and others as required.  
 
Situation: 
It is estimated that more than 60% of the Niuatoputapu population have become homeless as a 
result  of  the  tsunami.  Many  affected  families  are  relying  on  relatives  for  shelter,  while  others 
are living in temporary shelter, which is provided in the form of tents. It is also reported that a 
portion of the affected population have resorted to shelter at higher grounds on the mountains 
and are reluctant to move back to their original homes. There is an immediate need for better 
temporary  shelters  to  be  provided  for  the  affected  population  whilst  options  for  permanent 
shelters are being considered as part of the medium to long term recovery.     
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
13
Overall strategy for this sector: 
Adopt  a  phased  approach  to  the  housing  and  resettlement,  with  the  first  phase  focusing  on 
guaranteeing secure and dignified basic living conditions for the NTT population in view of the 
coming cyclone season.  The second phase will examine various options for permanent housing 
which  is  culturally  suitable  but  more  resistant  to  the  recurrent  disasters  which  threaten  NTT, 
and determine which option to proceed to implement.   
 
Key policy considerations: 
 
The community must be consulted on where the new houses should be located, as well  
essential  characteristics  of  the  house,  so  that  this  can  be  done  successfully  and  to 
ensure  their  satisfaction  as  “clients.”    Both  men  and  women  must  be  properly  and 
separately  consulted,  and  their  concerns  addressed,  in  particular  in  relation  to  safety, 
security and livelihoods insofar as these pertain to settlements. 
 
The availability of land, and the land tenure and lease arrangements must be explored 
and resolved prior to finalizing the settlement design. 
 
Strongly recommended to seize this opportunity to “build back better,” by building both 
shelters and private homes which are disaster resistant for earthquakes, tsunamis and 
cyclones.  Minimally the buildings should be able to withstand a category 4 cyclone, and 
national  and  international  expertise  should  be  fully  exploited  to  obtain  the  optimal 
design solutions.   
 
The  design  should  be  compliant  with  the  existing  building  codes  in  Tonga,  and  it  may 
also be advisable to review the current codes to verify whether they effectively ensure 
multi‐hazard disaster resilience.  
 
Estimated total cost:  USD $3 million. 
 
Health 
Composition of thematic working group:  led by Ministry of Health.  Members include Tonga Red 
Cross,  Tonga  National  Women  and Children’s Centre, Ma’a  Fafine, World Health Organization, 
UNICEF, UNFPA, Aid Management Division and others as required.  
  
Situation: 
The four critically injured people were evacuated to Tongatapu for medical attention and their 
medical needs have been adequately addressed. A temporary clinic has been setup to address 
the  medical  needs  of  the  people  of  the  island.  Most  of  the  hospital  equipment  was  lost  and 
requests have been made to the government to replace the clinic’s essential equipment, such as 
the  cold  chain  equipment,  generator,  water  tank  and  autoclave.  There  is  a  need  for  the 
damaged  hospital  to  be  relocated  and  reconstructed  and  the  much  needed  equipment  to  be 
supplied  for  the  smooth  operation  of  the  hospital  to  look  into  the  medical  needs  of  the 
population. 
 
Overall strategy for this sector: 
First phase, maintain the health of the displaced population, and prevent epidemics and disease 
outbreaks, by operating a temporary health clinic.  Second phase, build and equip new hospital 
in  safe  location  away  from  the  coast,  with  a  structure  resistant  to  cyclones,  so  that  health 
services are not interrupted by future disasters.  
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
14
Key policy considerations: 
 
While  temporary  arrangements  are  made  for  interim  health  care  provision,  discussion 
and analysis should be immediately initiated on what would be required for establishing 
full hospital conditions which in the future will not be interrupted by disasters. 
 
Estimated total cost:  USD $900,000. 
 
 
Water and sanitation 
Composition of thematic working group:  led by Ministry of Health.  Members include Tonga Red 
Cross,  Tonga  National  Women  and Children’s Centre, Ma’a  Fafine,  World  Health Organization, 
UNICEF, Aid Management Division and others as required.  
 
Situation: 
As per the latest updates on the NTT situation, the water systems in all the three villages have 
been restored. However, it is recommended that the water systems on the island be replaced. 
There  is  also  a  prominent  need  for  proper  sanitation  facilities  to  be  provided  for  the  affected 
population living in temporary shelter. Ensuring access to clean water and proper sanitation is 
an ongoing concern for the Ministry of Health.  
 
Overall strategy for this sector: 
In  the  short  term,  maintain  hygiene,  health  and  safety  of  the  affected  population  through  
adequate temporary facilities. In the medium term, build a new reticulated water system as a 
necessary component of the resettlement design.  
 
Key policy considerations: 
 
As the population is living in quite precarious conditions since the disaster, in tents, it is 
essential  to  have  a  mechanism  for  frequent  monitoring  of  the  sanitation  and  health 
situation,  which  can  deteriorate  rapidly.  This  will  enable  early  action  if  any  disease 
outbreaks occur. 
 
Special  attention  should  be  paid  to  verifying  the  specific  water‐related  and  sanitary 
needs of girls and women, based on a separate consultation with these groups to help 
detect  any  issues  and  provide  prompt  solutions.    Women  and  girls  should  be 
comfortable  in  carrying  out  their  daily  activities,  with  adequate  privacy,  safety  and 
keeping their dignity intact. 
 
Estimated total cost:  not yet finalized. 
 
 
Early warning systems 
Composition  of  thematic  working  group:    led  by  National  Emergency  Management  Office.  
Members  include  Tonga  Meteorological  Services,  Tonga  Defense  Services,  Tonga  Police  Force, 
Tonga  Red  Cross,  SOPAC,  Secretariat  of  the  Pacific  Community,  UNESCO,  UNDP,  Inter‐
governmental Oceanographic Commission, Aid Management Division and others as required.  
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
15
Situation: 
The earthquake occurred at 06:48 hours, the warning issued out of Hawai’i at 07:04, and the 
tsunami wave hit Niuatoputapu (NTT) at 07:15 hours. Though the Tsunami warning was 
broadcasted on radio, lamentably the people of Niuatoputapu did not receive the warning in 
time. There is accordingly an urgent need to undertake a review of the existing early warning 
system for tsunamis and other hazards in Tonga, particularly with an emphasis on how 
effectively these systems are working in the outer islands and for the most vulnerable groups. 
The organizational and planning dimensions of EWS should also be assessed, taking into account 
the chain of communications, roles of community members and the different vulnerabilities and 
capacities of men and women. 
 
It has been identified that there is an urgent need for disaster risks awareness programmes to 
be conducted for stakeholders both at national and community level. During the tsunami, it was 
noted that while most of the foreigners ran towards higher ground to avoid the waters, the local 
people actually ran toward coastal areas. This serves to show an insufficient awareness on some 
of the fundamentals issues pertaining to disaster such as tsunamis. 
 
Overall strategy for this sector: 
Use the lessons learned from this disaster experience, and the post‐disaster interest in improved 
DRM,  to  conduct  an  end‐to‐end  review  of  the  current  EWS,  identify  critical  shortcomings  and 
obtain  resources  to  significantly  improve  the  system.    This  should  be  complemented  by  an  
emphasis on awareness‐raising among the public on all hazards, along with practice drills.  
 
Key policy considerations: 
 
The  post  disaster  moment  provides  a  window  of  opportunity  to  leverage  public  and 
government  concern  to  significantly  enhance  the  country’s  overall  disaster  risk 
management,  including  early  warning  systems.    This  window  will  likely  close  again 
within a few months.  
 
Particular  emphasis  should  be  placed  on  identifying  and  addressing  the  gaps  or 
“weakest  links”  in  the  EWS  and  overall  disaster  risk  management  systems,  entailing 
outreach  to  and  full  participation  of  the  most  vulnerable,  which  in  the  case  of  Tonga 
points to the outer islands. 
 
Substantial improvements in the effectiveness of the overall system can be attained by 
ensuring  gender  sensitivity  at  all  levels,  so  that  women’s  talents  and  capacities  are 
mobilized  to  strengthen  the  system,  in  addition  to  taking  into  account  their 
vulnerabilities.   
 
Estimated total cost:  USD $200,000. 
 
 
Livelihoods 
Composition  of  thematic  working  group:    led  by  local  NTT  government  representative.    
Members include Ministry of Agriculture, Food, Fisheries and Forestry, Tonga Red Cross, Langa 
fonua’a  fafine  Tonga,  Secretariat  of  the  Pacific  Community,  UNDP,  FAO,  Aid  Management 
Division and others as required.  
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
16
Situation: 
Most of the boats on the Island of Niuatoputapu and Tafahi were destroyed or lost during the 
tsunami. These boats were used as a medium for transportation and also a source of fishing to 
cater for their livelihoods. The need has been identified to provide the affected population with 
some boats in order to enable them to resume with their normal fishing and also have access 
transportation  from  Tafahi  to  NTT.  The  other  source  of  livelihood  identified  is  mat  weaving 
which is done by women groups in private houses. These private houses or community houses 
have been reported to be damaged after the Tsunami. 
 
Overall strategy for this sector: 
Reactivate  traditional  livelihoods  on  the  islands  as  soon  as  feasible,  prioritizing  the  livelihoods 
practiced by women, due to their greater vulnerability. 
 
Key policy considerations: 
 
Livelihoods  tend  to  be  quite  differentiated  by  gender,  therefore  this  must  be  well 
understood in the specific local context, so that any investments in and support to the 
re‐activation of livelihoods will benefit both men and women. 
 
Consideration should be given to any viable alternative or non‐traditional livelihoods, as 
these may help diversify the local economy, expand people’s options, and thereby build 
greater resilience in the community. 
 
Synergies  should  be  sought  in  terms  of  possible  livelihoods  related  activities  which 
simultaneously  reduce  disaster  risk  and  enhance  environmental  protection,  such  as 
reforestation programs.  
 
Estimated total cost:  USD $250,000. 
 
 
 
3.4 Logistics 
 
The remote Niuas group of islands is difficult to access under normal circumstances, and suffers 
from shortages in regular transport and supplies.  This situation was aggravated by the tsunami 
impact,  as  it  damaged  the  airstrip,  wharf  and  virtually  destroyed  telecommunications.    This 
critical  infrastructure  is  in  the  process  of  being  restored  as  a  priority  under  the  relief  phase, 
however,  this  is  not  yet  fully  completed.    Therefore  it  is  important  to  take  into  account  and 
anticipate the logistics challenges implied for the recovery process. 
 
The standard options available for transporting passengers and cargo out to Niuatoputapu and 
back include: 
 
 
type of craft 
origin/source 
capacity 
travel time to NTT 
availability 
Island 
hopper 
plane 
 
Nuku’alofa 
6 pp 
1.5 hours 
Charter 
C130 
plane 
(Hercules) 
Australia or NZ 
60 pp 
3 tons cargo 
4 hours 
Special request 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
17
 
Tongan 
Navy 
patrol boats 
 
Nuku’alofa 
10 tons 
18 hours 
On request 
LCH barge 
 
Australia or NZ 
90 tons 
Travel in pairs 
12 days 
On request 
Navy frigate 
(RANS 
Tobruk, 
HMNZ 
Canterbury) 
 
Australia or NZ 
1300 tons 
6 days 
On request 
 
 
The strategy for managing the logistics entailed in the recovery mission is to develop a logistics 
plan  for  the  duration  of  the  recovery  phase,  to  match  as  closely  as  possible  the  transport 
opportunities  with  the  materials  and  items  to  be  transported,  as  well  as  travel  of  persons  for 
technical  assistance,  assessments  or  monitoring.    Given  that  new  developments  and 
opportunities  arise,  and  priorities  may  shift  somewhat,  this  logistics  plan  should  be  reviewed 
and updated monthly. 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
18
 
3.5   Recovery strategies and actions matrix 
 
SECTOR 
 
IMPACTS AND 
VULNERABILITIES 
 
Summary of key 
impacts and 
vulnerabilities 
NEEDS 
 
Overview of key early 
recovery needs 
CAPACITIES 
 
Summary of 
available capacities 
in affected areas 
SOLUTIONS AND 
STRATEGIES 
 
Proposed solutions/ 
strategies for early 
recovery programs 
DEVELOPMENT 
PARTNERS 
 
Interested in 
supporting early 
recovery efforts 
of government 
 
Resettlement/ 
relocation 
 
 
 
 
 
79 houses completely 
destroyed 
 
56 houses partially 
damaged 
 
Displaced population 
living tents mainly in 
tents 
 
Cyclone season starts in 
November 
 
Adequate temporary 
shelter which is cyclone 
resistant 
 
Assessment of relocation 
options  
 
New houses which are 
disaster resistant 
 
Community could be 
mobilized for building 
and construction 
 
Some construction 
materials may be 
salvaged from debris 
 
 
 
Short term 
Build collective shelter to 
withstand category 4 
cyclones 
 
Technical assessments and 
options required 
 
Build Tongan style houses 
as temporary shelter for 
family units 
 
Medium term 
Relocate residential area to 
higher ground, if validated 
by community consultation 
 
Design and build houses 
which are more disaster 
resistant 
 
 
 
Habitat 
 
World Bank 
 
ADB 
 
Mormon Church 
 
NZAid 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
19
 
Water and 
sanitation 
 
 
 
Water reticulation system 
lines damaged in all three 
villages 
 
High density of rubbish 
left by tsunami 
 
Normal sanitation system 
interrupted 
 
Septic tanks overflowing 
 
 
Continued and monitored 
supply of fresh water to 
displaced population 
 
Review of temporary 
sanitation arrangements 
from health and safety 
perspectives 
 
Consultation with  
community about 
adequacy of temporary 
and preferences for 
permanent new 
sanitation systems, 
especially seeking input 
from women and girls 
 
 
 
Community could be 
mobilized for digging 
latrine pits 
 
Communal solidarity 
tends to share scarce 
resources such as water 
equitably 
 
 
Short term 
Gender‐sensitive 
community consultation to 
detect water and sanitation 
issues 
 
Adjustment of temporary 
water and sanitation 
system as needed 
 
Technical assessments and 
options required 
 
 
Medium term 
Build culturally suitable 
new sanitation and water 
reticulation systems as part 
of resettlement plan 
 
 
 
WHO  
 
UNICEF 
 
JICA 
 
 
Livelihoods 
 
 
 
Extensive damage to 
pandanus plants 
 
Minor damage to 
breadfruit trees 
 
8 fishing boats destroyed 
 
6 sheds for women’s mat 
weaving destroyed 
 
Fisheries office and ice‐
 
Fishing boats (8) 
 
Net and other equipt for 
fishing 
 
Ice‐making plant rebuilt 
 
Sheds for mat weaving (6) 
 
Fisheries office rebuilt 
 
Root crops not affected 
as they are inland 
 
Community has strong 
farming skills 
 
Men have extensive 
fishing skills and 
experience 
 
Women are highly 
skilled at weaving fine 
 
Short term 
Mobilize community to 
replant pandanus plants 
along coast, also for DRM 
 
Purchase of fishing boats 
for communities 
 
Replacement of lost fishing 
equipment 
 
Possible cash‐for‐work 
 
UNDP  
 
AusAid 
 
FAO 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
20
making plant destroyed 
 
mats 
 
2 replacement fishing 
boats already sent to 
NTT 
 
programs for debris 
clearance or pandanus 
planting 
 
 
 
Early warning 
systems 
 
 
 
Current national EWS not 
always effective 
 
NTT did not receive the 
warning this time 
 
Both hardware and soft 
aspects need 
improvement 
 
Cyclone season starts in 
November 
 
Continued period of 
seismic activity from 
Tonga trench 
 
 
Equipt to ensure full 
reliability and 
functionality of EWS 
(electrical generator, 
microwave link, wind and 
pressure instruments) 
 
Linkages to regional and 
international expertise on 
state‐of‐the art EWS 
 
Tonga Met Service 
already has a proposal 
for improvement of 
Met Service component 
of EWS 
 
NAP project with SOPAC 
could be adjusted to 
prioritize review of EWS 
 
 
Short term 
Invest in equipt to ensure 
better functionality of 
current EWS system 
 
Review of whether system 
is effectively reaching the 
most vulnerable groups  
 
Medium term 
Review of EWS to identify 
critical gaps and actions so 
as to perfect system 
 
Training and certification 
for climate observers in 
outer islands 
 
 
UNDP  
 
JICA 
 
UNESCO  
 
ISDR 
 
SOPAC 
 
SPC 
 
 
Government 
buildings 
 
 
 
Gov’t buildings destroyed 
– courthouse, police 
station and others 
 
Staff quarters destroyed 
 
Given the post‐crisis 
situation and displaced 
population, high need for 
 
Rapid replacement of 
gov’t offices  
 
Gov’t workers on island 
and keen to return to 
full capacity  
 
National gov’t raising 
with donors the need to 
fund these buildings 
 
Short term 
Prefabricated buildings for 
transitional provision of 
govt services 
 
Consideration of design 
options for permanent 
office buildings 
 
 
NZAid 
 
World Bank 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
21
gov’t services 
 
Medium term 
Build culturally suitable and 
disaster resilient gov’t 
offices in safe location 
 
 
Infrastructure 
 
 
 
Wharf damaged 
 
Airstrip covered in debris, 
security fence destroyed 
 
Damage to air terminal 
and staff quarters 
 
Telecommunications 
equipt and buildings 
damaged 
 
Roads damaged  
 
5 vehicles destroyed 
 
 
 
 
Repair of wharf 
 
Airstrip and facilities 
cleared of debris and 
functioning 
 
Restoration of 
telecommunications 
equipt and buildings 
 
Repair of roads, in 
relation to resettlement 
design 
 
Initial repairs already 
conducted have made 
the wharf and airstrip 
serviceable 
 
Negotiate with appropriate 
donors for funding to 
reconstruct transportation 
infrastructure on a “build 
back better” principle 
 
 
 
World Bank 
 
ADB 
 
Health 
 
 
 
Hospital ruined, all 
equipment lost 
 
Staff quarters quite 
damaged 
 
 
Rebuilding of hospital 
based on disaster‐
resistant design 
 
Temporary health clinic 
running out of the 
Mormon Chapel 
 
Seize opportunity to 
relocate hospital in location 
further from the coast  
 
Investigate “safe hospital” 
program led by WHO and 
ISDR for application in NTT 
 
 
Govt of France  
 
UNICEF  
 
UNFPA  
 
WHO 
 
ISDR 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
22
 
Education 
 
 
 
Primary school damaged 
 
Schools used as shelters 
in post‐disaster period, 
which compromises the 
children’s education and 
delays their return to 
normalcy  
 
 
Rebuilding of primary 
school 
 
High school not 
damaged 
 
Lost school supplies 
already replaced with 
donor assistance 
 
 
Consider retrofitting of 
school buildings for 
disaster resistance 
 
Engage children as agents 
in promoting disaster 
awareness through the 
school curriculum 
 
UNICEF 
 
NZAid 
 
 
Disaster risk 
management 
 
 
 
No evacuation plan 
 
Insufficient community 
preparedness activities 
 
Cyclone season starts in 
November 
 
Continued period of 
seismic activity from 
Tonga trench 
 
Limited resources 
 
 
Gender‐sensitive drills for 
tsunamis and cyclones 
 
Increased community 
level preparedness 
activities 
 
Local evacuation plans 
 
Vulnerability mapping on 
outer islands 
 
 
 
 
 
Heightened awareness 
of disasters among 
community 
 
Govt support through 
NEMO 
 
A tsunami response 
plan for Tongatapu has 
been drafted 
 
Existing ATWS tsunami 
capacity assessment 
report for Tonga 
 
 
Capitalize on heightened 
awareness and fear of 
disaster by launching a 
public awareness campaign 
 
Promote gender‐sensitive 
disaster risk management 
based on understanding 
the social dimensions of 
both vulnerabilities and 
capacities 
 
Prioritize local 
preparedness and disaster 
planning for outer islands, 
given their high 
vulnerability 
 
Secure additional resources 
so as to significantly 
expand community 
preparedness and 
awareness activities 
 
 
UNDP  
 
SOPAC 
 
SPC 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
23
Section 4.  Funding 
 
The priorities outlined in this plan will be used as a basis for negotiating offers of funding and 
assistance  from  various  donors,  to  avoid  duplication  and  to  ensure  the  maximum 
complementarity among donors.  
 
 
 
Section 5.  Risk analysis 
 
Rating of probability: 1 = very low, 2 = low, 3 = moderate, 4 = high, 5 = very high 
 
 
Project Title:   Tsunami Recovery Priority Plan – NTT Tonga 
Date: October 2009 
 
#  Description 
Date 
Identified 
Type 
Impact & 
Probability 
Countermeasures / 
Mgmt response 
Owner 
Recurrence of 
natural disasters in 
the upcoming 
months 
October 2009
 
Act of God 
P = 5 
I = may impact work plan 
priorities or volume of 
work 
Agree on strategies 
with development 
partners for such 
events 
Aid Mgmt 
Division 
 
NEMO
 
 
Limited funding 
due to increased 
scope of recovery 
work 
 
October 2009 
Organizational 
P= 2 
I = funding constraints  
Seek other funding to 
supplement the 
activities 
Aid Mgmt 
Division 
 
Delay in internal 
processes and 
decision‐making to 
design buildings 
and purchase 
equipment 
 
 
October 2009 
Organizational 
P =1 
I = delay in 
implementation 
Prioritize technical 
assessments and design 
activities 
 
Obtain quotations in 
advance from local 
suppliers for planned 
equipment 
Aid Mgmt 
Division 
 
NEMO 
 
 
 
 
Section 6.  Next steps 
 
1. Activate thematic working groups. 
2. Determine which further assessments are needed. 
3. Commence purchasing process for the prioritized short term activities.  
4. Initiate detailed work planning for key programming activities. 
5. Secure extra staff assistance for Aid Management Unit. 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
24
 
Section 7. Conclusions  
 
At times nature and Acts of God deliver us blows from which we cannot easily recover.  In the 
face  of  these  trials,  the  way  forward  will  depend  primarily  on  the  resilience,  strength  and 
ingenuity  of  the  Tongan  people  and  the  wisdom  of  their  leaders  and  rulers.  International 
agencies, NGOs  and  governments  can  prove to be valuable  friends  and allies in such  times,  in 
their roles of supporting the Tongan government and population.   
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
25
ANNEX 1: 
Immediate and long term needs 
 
As assessed by AMD at 20 October 2009: 
 
Immediate needs: 
 
 
 
 
 
 
 
 
 
 
Sector/ Organisation 
Needs 
Status 
 Estimated 
Cost 
 Coordinator 
from 
GoT/Tonga  
Donor 
 Required actions  
Resettlement/Relocation 
Plan 
GIS boundary survey, 
community consultation, 
recommendations to committee 
on alternatives for relocation 
L&S team to NTT to 
complete relocation 
assessment 20‐27 Oct 
 
 Lands & Survey  
Waiting on assessment & 
recommendations from 
resettlement thematic 
group 
 
 
Confirm if temporary housing is 
sufficient 
 
 
 
Habitat for 
Humanity 
 
 
 
Repair works on existing housing   
 
 
 
 
 
 
 
 
 
 
 
 
Sanitation 
Ventilation improved pit latrines 
until people resettled, Sanitation 
engineer to recommend long 
term solution 
 
 
 MoH  
 
 
 
 
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
26
Livelihoods reactivation 
Fisheries ‐ Supply fishing boats & 
equipment 
One boat sent by UNDP, 
one TDS. 6 additional 
boats lost/destroyed 
       120,000  
 MAFFF  
UNDP/FAO 
MAFFF to prepare detailed 
report on number and type 
of boats and equipment 
lost, owner, and quotes for 
replacement 
 
 
Rebuilding of sheds for mat 
weaving 
 
 
 MAFFF  
UNDP 
MAFFF to prepare options 
for design of sheds and cost 
estimates to rebuild 
 
 
Planting of pandanus along coast   
 
 MAFFF  
FAO 
MAFFF to prepare detailed 
assessment of damage/loss 
of pandanus, and proposal 
for replanting 
 
 
Replanting crops 
Initial reports that no 
damage sustained to 
crops or livestock 
 
 MAFFF  
 
MAFFF to confirm 
damage/loss of crops, and 
proposal for replanting if 
required 
 
 
 
 
 
 
 
 
Early warning systems 
Immediate review of current 
early warning system, design 
improvements to increase 
effectiveness 
 
 
 NEMO/MET services  
 
 
 
 
 
 
 
 
 
Government Centre 
Storage shed 
Requested 16 Oct from 
Aus 
 
 
 
Waiting on response from 
Aus to confirm if this can be 
received on HMAS Tubrok 
 
 
8 standard pre‐fab houses for 
Govt office & accommodation 
Requested 16 Oct from 
Aus 
       240,000  
 
Australia 
 
 
Two light trucks for distribution 
of supplies 
Requested 16 Oct from 
Aus 
         50,000  
 
Australia 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
27
 
 
 
 
 
 
 
 
Transport 
Barge for transportation of 
heavy equipment 
Requested 16 Oct from 
Aus 
       500,000  
 TDS  
Australia 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Health 
 
 
 
 
 
 
 
 
Provide field hospital & 
equipment including an 
autoclave, Oroscope, otoscope, 
ophthalmoscope, 
thermometers, 
sphygmomanometer, 
stethoscope, examination table, 
delivery table, drugs cabinet, 
beds for patients, trolley for 
patients, bed sheets, etc etc. 
Field hospital currently 
located in LDS church hall. 
MoH to confirm how long 
this can remain. MoH to 
confirm what supplies are 
still required. 
       250,000  
 MoH  
WHO, 
UNICEF, 
UNFPA 
MoH to update this list to 
confirm if need still exists, 
relevant donors to be 
contacted ASAP to fulfil 
remaining needs 
 
 
Electric generator and fuel, 
refrigerator 
 
 
 MoH  
 
 
 
 
Washing machine 
 
 
 MoH  
 
 
 
 
Personal dignity packs 
 
 
 MoH  
 
 
 
 
IEC material  
 
 
 MoH  
 
 
 
 
Detergents, soap, toothpaste 
and brushes, toilet paper 
 
 
 MoH  
 
 
 
 
Vaccine supply 
 
 
 MoH  
 
 
 
 
Small incinerator 
 
 
 MoH  
 
 
 
 
Supply of ORS  
 
 
 MoH  
 
 
 
 
Mental Health support 
 
 
 MoH  
 
 
 
 
Food and water for hospital staff 
 
 
 MoH  
 
 
 
 
Health spray ‐ Insecticide & 
Disinfectants 
 
         30,000  
 MoH  
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
28
 
 
Cooking stove, gas, chairs, bed, 
table, drawer for the staff, 
kitchen ware such as plates, 
forks, spoons, cooking pots, 
knives, can opener, cups etc. 
 
 
 MoH  
 
 
 
 
Admin supplies ‐ A4 papers, one 
type writer and ink, pens, 
folders for patient files and 
records, relevant medical forms, 
filing cabinets, bookshelves , 
table and chairs etc. 
 
 
 MoH  
 
 
 
 
Vehicle to replace MoH WHO 
vehicle from Tongatapu 
Vehicle sent to NTT 13 Oct 
‐ vehicle required to 
replace this in due course 
         50,000  
 MoH  
 
 
Water Supply 
 
 
 
 
 
 
 
 
Repair pumps 
Completed ‐ pumps 
operating in 3 villages 
         20,000  
 MoH  
 
 
 
 
Support & desalination plant 
Desalination plant 
operating effectively 
            2,000  
 
NZ Red 
Cross 
MoH to confirm if 
deslination plant still 
operating 
 
 
Interim water supply/storage for 
displaced people 
 
 50,000‐
100,000 
   
MoH to confirm if interim 
water supply is sufficient 
Telecommunications 
 
 
 
   
 
 
 
Land line to be reinstalled 
Mobile network 
operating, awaiting 
relocation decision before 
installing landline 
 
TCC 
Damage 
covered by 
insurance 
Confirm with TCC what 
equipment/materials 
required and expected 
timeline 
10 
Refuse Collection 
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
29
 
 
Remove rubbish and debris, 
front end loader & dump truck 
HMAS Canterbury 
collecting debris in one 
pile 18‐21 Oct, mostly 
completed 
       150,000  
 
 
Confirm with TDS if further 
assistance/equipment 
required to complete debris 
clearing 
11 
Airport 
 
 
 
 
 
 
 
 
Clear rocks and debris 
Completed ‐ planes able 
to land 
         20,000  
 TAL/TDS  
 
Confirm with TDS/TAL 
12 
Food Aid 
 
 
 
 
 
 
 
 
Food supply for four weeks 
Completed ‐ sufficient 
food aid has been 
received 
         10,000  
 TDS  
Community  Confirm if further food aid 
required 
13 
School material 
 
 
 
 
 
 
 
 
School boxes etc 
Sufficient school materials 
received at this stage 
            5,000  
 MEWAC  
 
 
 
 
 
 
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
30
 
Long term requirements: 
 
 
No  Items 
Status 
 Estimated cost  
 Coordinator 
from 
GoT/Tonga  
Source of 
funds 
 Required actions  
 
 
 
   
 
 
Hospital 
Waiting on 
relocation 
decision 
   
1,800,000  
 MoH  
 
MoH to prepare 
proposal for 
replacement of 
hospital, design 
requirements/options, 
identify and approach 
appropriate donor 
 
 
 
   
 
 
Water Supply (updgrading reticulation) 
Waiting on 
relocation 
decision, JICA 
confirmed 
funding 
   
200,000  
 MoH  
JICA 
MoH to prepare 
proposal for 
replacement of 
reticulation to 3 
villages 
 
 
 
   
 
 
Residential home reconstruction 
Waiting on 
relocation 
decision, 
Resettlement 
TWG is compiling 
recommendations 
for different 
housing design 
options 
   
6,075,000  
 
Resettlement 
TWG  
Habitat for 
Humanity, WB, 
Australia 
Donors requested 
outline of strategy for 
housing 
reconstruction ‐ to be 
compiled by TWG 
 
 
 
   
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
31
Government Offices 
Requested pre‐
fab buildings from 
Australia 16 Oct 
   
1,000,000  
 PMO  
 
Waiting on response 
from Aus to confirm if 
this can be received 
on HMAS Tubrok 
 
 
 
   
 
 
Government quarters 
Requested pre‐
fab buildings from 
Australia 16 Oct 
   
2,000,000  
 PMO  
 
 
 
 
   
 
 
Airport (security fence, met equip, extend 
runway) 
Requested 
assistance from 
Australia 16 
October for 
engineers to 
assist 
   
1,000,000  
 TAL/MoT  
WB (TSCP) 
Confirm damage 
assessment and 
proposal of work 
required 
 
 
 
   
 
 
Wharf (armour rods and navigation aids) 
Requested 
assistance from 
Australia 16 
October for 
engineers to 
assist 
   
200,000  
 MoT  
 
 
 
 
   
 
 
Road (4km) 
Requested 
assistance from 
Australia 16 
October for 
engineers to 
assist 
   
540,000  
 MoT  
 
 
 
 
   
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
32
Schools (7 classrooms) 
 
   
490,000  
 MEWAC  
NZAid, World 
Bank 
MEWAC to prepare 
detailed report on 
damage incurred for 
each school, staff 
housing etc. 
 
 
 
   
 
 
10 
Disaster management planning ‐ End to end 
review of disaster management process 
 
   NEMO  
UNDP,SOPAC, 
ISDR 
NEMO/warning 
system TWG to 
prepare 
proposal/timeline for 
review 
 
 
 
   
 
 
12 
Tafahi channel clearance 
 
   
100,000  
 MoT  
 
Confirm details of 
damage assessment 
and required 
rehabilitation 
 
 
 
   
 
 
13 
Fisheries (Block making machines) 
   
100,000  
 MAFFF  
 
 
 
 
 
   
 
 
 
TOTAL 
 
   
13,305,000  
 
 
 
 
 
 
   
 
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
33
ANNEX 2: 
Summary of indicative external assistance 
 
Indicative funding available as at 23 October 2009: 
 
 
 
 
 
 
Donor 
Amt 
Amt (TOP)  Possible Rehabilitation activity 
Source 
UNDP 
 300,000 USD            
600,000  
Coordination of recovery program, Fishing 
boats, Rebuild women's huts, Early warning 
system, Improved disaster risk reduction 
Bureau for Crisis Prevention and Recovery 
(BCPR) 
UNICEF 
     
Repair of pumps, Desalinisation, School 
materials 
  
UNFPA 
     
Drugs, Reprod Health Supplies, 'Kit 6' 
  
UN 
     
Tsunami assessment specialists 
  
WHO 
     
Health supplies, washing machine etc. 
  
World 
Bank 
250,000 USD 
   
500,000  
Disaster assessment, sector specialists in 
education and health, potentially rebuilding 
primary schools 
Emergency relief fund 250k + additional 
funds from IDA grant (possibly scale up IDA 
for tsunami relief) 
  
  
   Transport sector ‐ roads, wharf, runway 
Transport Sector Consolidation Project 
EU 
 0.9m Euro         
2,545,380  
Waiting on priorities from GoT 
B Envelope ‐ emergency recovery fund 
AusAid 
  
   Waiting on priorities from GoT, barges from 
ADF, Police station  
TPDP funding allocation for police station, 
Health program funding maybe allocation to 
Health needs ( to discuss with MOH) 
NZAid 
 1.5m NZD  
   
1,716,247  
Generator, waiting on priorities from GoT 
Tsunami relief fund 
Japan 
  
   
200,000  
Water supply system 
  
FAO 
   
20,000  
   
40,000  
Food supply, fishing boat, agricultural 
supplies 
Leftover from previous FAO project to be 
reallocated to NTT, additional funding may 
be available for agriculture/food related 
needs 
PNG 
 500,000USD  
   
1,000,000  
  
Need to provide PNG with bank account 
details 
LDS 
Church 
  
   Waiting on priorities from GoT 
  
US 
 50,000 USD  
   
100,000  
Waiting on priorities from GoT 
Suva Embassy 
Thailand 
 15,000USD  
   
30,000  
  
Thai Govt through Embassy in Wellington 
China 
  
     
  
France 
  
     
  
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
34
Donation 
 1,500AUD  
   
2,308  
25 bibles, plus building materials 
Melbourne Church of God 
TOTAL 
  
      
6,701,627  
  
  
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
35
ANNEX 3: 
Tables of estimated damages 
 
Note:  information provided by initial government assessment dated 8 October 2009. 
 
 
Immediate relief and 
reconstruction 
requirements 
 
 
  
Sector/Organisation Needs  Estimated 
  
  
  
Cost $TOP 
Water Supply 
*  Repair pumps  
 $       20,000.00  
  
  
*  Support desalination plant 
 $         2,000.00  
2 Refuse 
Collection 
*  Remove rubbish and debris to a  
dump site 
 $      150,000.00 
  
 
 
  
  
 
*  Need front end loader and dump 
truck  
  
Government Centre (240m2) 
*  Provide pre-fab building for 
    Temporary Government       Office 
 $      240,000.00  
  
  
*  Two light trucks for four  
 $       50,000.00  
  
  
    distribution and delivery 
  
Health 
*  Provide a field hospital 
 $      200,000.00  
  
  
  
  
Airport 
*  Clear rocks and debris 
 $       20,000.00  
Transport  
*  Barge for transportation heavy 
 $      500,000.00  
  
  
     equipment 
  
Food Aid  
*  Food supply for four weeks 
 $       10,000.00  
Replanting  
*  Seeding, material etc. 
 $       20,000.00  
Fisheries  
*  Supply fishing boats 
 $      120,000.00  
10  School Material 
*  School boxes  etc 
 $         5,000.00  
11  Insecticide and Disinfectants    *  Health spray 
 $       30,000.00  
  
Chemicals 
  
  
12  Storage Sheds (400m2) 
*  Storage relief supplies  
 $      300,000.00  
13  Telecommunication 
*  Restore communication 
 $      200,000.00  
  
  
 
  
 
 
 
 
14  Sanitation 
*provide toilets 
$      405,000.00 
  
  
  
  
  
  
  
 $2,272,000.00  
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
36
 
 
Long Term Rehabilitation Works 
No. ITEMS 
ESTIMATED COSTS 
$TOP 
Hospital 
 $         1,800,000.00  
  
(including mortuary, generator and 
  
  
 medical supplies) 
  
Telecommunications 
 $            800,000.00  
  
  
  
Water supply 
 $            200,000.00  
  
(upgrading reticulation) 
  
Airport 
 $         1,000,000.00  
  
(security fence, metrological equipment  
  
  
 and airport extension of 300m) 
  
Wharf 
 $            200,000.00  
  
(armour rods and navigation aids) 
  
  
  
  
Tafahi Channel 
 $            100,000.00  
  
(channel clearance) 
  
  
  
  
Residential Homes 
 $         6,075,000.00  
  
(135 units including water tanks) 
  
Government Offices 
 $         1,000,000.00  
  
(380 square metres) 
  
  
  
  
Government Quarters 
 $         2,000,000.00  
  
(19 quarters) 
  
  
  
  
10 
Road 
 $            540,000.00  
  
(4 km long) 
  
  
  
  
11 
Schools  
 $            490,000.00  
  
(7 classrooms) 
  
  
  
  
12 
Fisheries 
 $            100,000.00  
  
(Block making machines) 
  
  
  
  
13 
Weaving cottage sheds 
 $            240,000.00  
  
(6 sheds) 
  
  
  
  
  
TOTAL 
 $    14,545,000.00  
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
37
ANNEX 4: 
Maps of Tonga, Niuatoputapu and Tafahi 
 
Map of Tonga showing location of all islands: 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
38
 
Map of Niuatoputapu and Tafahi: 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
39
ANNEX 5: 
TEMPLATE FOR THEMATIC WORKING GROUPS (TWG) 
 
 
 
Sector: 
 
Lead Ministry: 
 
Other members of the TWG: 
 
Person in charge and contact details: 
 
Alternate person in charge and contact details: 
 
 
 
 
A. Situation analysis of sector 
-
 
Tsunami impacts 
-
 
Needs and vulnerabilities of the affected population  
-
 
Capacities available in the community 
-
 
Policy options and recommendations 
 
 
 
B. Sequence of activities with timelines 
-
 
Activities required for sector recovery, in order of priority 
 
 
C. Project proposals – as annexes 
-
 
In relation to activities listed above 
-
 
With list of items needed and detailed costing 
-
 
To submit to donors for consideration 
 
 
 
 
 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
40
 
ANNEX 6: 
NTT community survey 
 
 
NTT Information Gathering 
Ngaahi Fakamatala mei Niuatoputapu 
 
 
Niuatoputapu, Kingdom of Tonga 
Niuatoputapu, Pule’enga Tonga 
 
21 October 2009  
21 ‘Okatopa 2009 
 
Instructions for local government representatives:  
Ngaahi tu’utu’uni ki he kau Fakafofonga Pule’anga fakalotofonua: 
 
 
Please ask these questions of community members individually.   
 
Kataki ‘o ‘eke e ngaahi fehu’i ni ki he memipa takitaha ‘o e komiuniti. 
 
 
Equal numbers of men and women, boys and girls, should be given the questions. 
 
Ke tokolahi tatau ‘a e tangata mo e fefine, tamasi’i moe ta’ahine, ‘e ‘eke kiai e ngaahi 
fehuiI ni. 
 
 
Preferably interviewers should sit with people, ask questions verbally and write down 
their replies. 
 
Ko e faka’amu ke tangutu fakataha e kau faka’eke’eke moe kakai, ‘o ‘eke ai e ngaahi 
fehu’i pea mo hiki ‘enau ngaahi tali.
 
 
 
Send completed papers back to Nuku’alofa with the visiting officials when they return. 
 
Ke fakafoki mai e pepa kakato ki Nuku’alofa he foki mai ‘a e kau Ofisiale ne ‘a’ahi atu. 
 
Malo ‘aupito 
 
*************************************************************************** 
Questions 
Ngaahi Fehu’i 
 
 
Indicate your age: 
Koe ha ho ta’u motu’a: 
 
Male or female: 
Tangata pe Fefine: 
 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
41
Your village: 
Kolo ‘oku ke nofo ai: 
 
Work or income source: 
Ngaue’anga pe Ma’u’anga Pa’anga: 
 
 
 
How do you consider the current situation of your sanitation, or toilets? 
‘Oku anga fefe ho’o vakai ki ho tu’unga ma’a mo haisini pe toileti? 
Good 
 okay 
 bad 
  very 
bad 
 
 
Fakafiemalie      Sai pe   
‘Ikai ke fakafiemalie 
Fu’u kovi ‘aupito 
 
 
 
 
Why is this so? 
Koe ha nai e ‘uhinga ki ho’o tali i ‘olunga? 
 
 
 
 
Where should the latrine/toilet be located?  
‘E tu’u nai e falemaloloo pe toileti i fe’ia? 
 
 
 
Any concerns about the sanitation or waste right now – please explain. 
‘Oku ‘iai nai ha ngaahi hoha’a fekau’aki moe haisini/ma’a pea moe veve he taimi ni – kataki o 
fakamatala. 
 
 
 
For your permanent house, what kind of toilet would you prefer? 
Ki ho falenofo’anga tu’upau, koeha e fa’ahinga toileti ‘oku ke fiema’u? 
 
Latrine    
 
flush toilet 
  
other 
Falemalolo Keli  
Toileti Palangi   
Ha toe fa’ahinga kehe 
 
 
 
What could be done to improve your temporary shelter?  
Koe ha nai ha me’a ‘e fai ke toe fakalelei’i ai ho nofo’anga fakataimi? 
 
 
 
Do you have any safety or security concerns?   Please explain. 
‘Oku ‘iai nai ha’o hoha’a ki he malu ho’o nofo? Kataki ‘o fakamatala. 
 
 
 
Where should your new house be located? 
background image
Tsunami Recovery Priority Plan – Niuatoputapu Tonga 2009  
 
 
42
‘E tu’u ‘i fe ho fale nofo’anga fo’ou? 
 
On the coast      
 in the mountain     
in between 
‘I he matatahi   
‘I he mo’unga   
‘I Loto fonua 
 
 
Why? 
Koe ha nai ho’o ‘uhinga kiai? 
 
 
What are the most important aspects of your future house? 
Koe ha e me’a mahu’inga taha ‘oku ke fiema’u ki ho falenofo’anga he kaha’u? 
 
 
 
Can you help to build temporary shelters or new houses?  
Teke lava ‘o tokoni ke langa ha ngaahi nofo’anga fakataimi pe fale nofo’anga fo’ou? 
 
Yes      
No  
Io   Ikai 
 
 
Any health concerns in your family?  Please explain. 
‘Oku ‘iai ha memipa ho famili ‘oku ne mo’ua ha fa’aihnga mahaki tauhi? Kataki ‘o fakamatala. 
 
 
 
 
Any problems or needs with food supply?  Please give details. 
‘Oku ‘iai ha ngaahi palopalema pe fiema’u vivili ki ha ma’u’anga me’atokoni? Kataki ‘o 
fakaikiiki. 
 
 
 
Do you have enough fresh water?  
‘Oku fe’unga pe e vai inu? 
 
Yes  
 
No 
Ikai  
Io 
 
 
Are the children in your family attending school?  
‘Oku kei ako pe longa’i fanau ‘i ho famili? 
 
Yes  
 
No 
‘Io  
 
‘Ikai 
 
 
Any additional comments?  
‘Oku toe ‘iai ha ngaahi me’a kehe ‘oku ke fie tanaki mai?