background image
 
ƒ report
SIAM2 - Sustainable 
Management C4: 
Environment Risks & 
Resource Management 
Inception Report - Final 
 
 
 
 
 
background image
6060030/100  Rev A  ʄ  L2:49382 
ƒ report
SIAM2 - Sustainable 
Management C4: 
Environment Risks & 
Resource Management 
Inception Report - Final 
Prepared for 
Ministry of Natural Resources and 
Environment, and Meteorology 
By
Beca International Consultants Ltd 
May 2005 
background image
 
132 Vincent Street 
PO Box 6345, Auckland, New Zealand 
Telephone  +64-9-300 9000 
Fax  +64-9-300 9300 
www.beca.com
The Chief Executive Officer 
Ministry of Natural Resources, Environment and Meteorology 
Private Bag 
Apia 
SAMOA
 
Attn: Vitaua Peleiupa Fuatai, PCM SIAM2  
20 May 2005  
Our Ref:  6060030/100  
L2:49382-Final Inception 
Report - May 2005.DOC
Dear Sir 
SIAM2 - Sustainable Management C4: Environment Risks & Resource 
Management Inception Report - Final 
We have pleasure in enclosing the finalised Inception Report for the above project. We 
have amended the report to take into account our discussions at the Draft Inception Report 
Workshop held on 14 April 2005 and the written comments received from both MNREM 
and from the PUM Division on MWTI.  
We are still awaiting confirmation from both MNREM and MWTI that our understanding 
of our obligations under the contract consequent to the transfer of the PUM Division from 
MNREM to MWTI as set out in our letter to you dated 22 February 2005 was agreed. We 
have prepared the final Inception Report on the basis that these understandings have been 
accepted. 
The hard copies of this report will follow by courier. 
 
Yours faithfully 
Graeme Roberts  
Manager, Planning 
 
 
 
on behalf of 
Beca International Consultants Ltd 
Direct Dial: +64-9-300 9271 
Email: groberts@beca.co.nz 
 
 
 
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page i  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Revision History 
 
Revision Nº 
Prepared By 
Description
Date
Graeme Roberts 
Draft for discussion at Workshop 
April 2005 
Graeme Roberts 
Final version as amended following 
Workshop and with comments from 
MNREM & MWTI. 
20 May 2005 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Document Acceptance 
 
Action
Name
Signed
Date
Prepared by 
Graeme Roberts, Don 
Lyon, Peter Newsome, 
Michele Daly, Dave 
Brunsdon, Ted Wells 
 
 
Reviewed by 
Graeme Roberts 
 
 
Approved by 
Don Lyon 
 
 
on behalf of 
Beca International Consultants Ltd 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca Page 
ii 
 
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Table of Contents 
Executive Summary ......................................................................................... 1
1
Introduction ............................................................................................... 3
1.1
Project Description ..........................................................................................3
1.2
Purpose of Report ............................................................................................4
1.3
Structure of Report...........................................................................................4
1.4
Definitions .........................................................................................................5
2
Methodology by Workstream.................................................................. 6
2.1
Environmental Management Workstream....................................................6
2.2
Natural Risk Management Workstream ......................................................10
2.3
Natural Resource Management Workstream ............................................18
2.4
Emergency Management Workstream ......................................................24
3
Work Programme and Deliverable Outputs ......................................... 36
3.1
Introduction....................................................................................................36
3.2
Overall Work Programme .............................................................................37
3.3
Natural Risk Management Work Programme ............................................38
3.4
Emergency Management Work Programme.............................................39
3.5
CIM Plan Typical District Work Programme ................................................41
3.6
Deliverable Outputs ......................................................................................42
3.7
Anticipated Counterpart Involvement........................................................42
4
Key Performance and Progress Indicators........................................... 43
5
Risk Management Plan .......................................................................... 45
5.1
Introduction....................................................................................................45
5.2
Project Risk Plan ............................................................................................45
6
Decisions/Actions Required................................................................... 48
6.1
Organisational Changes ..............................................................................48
6.2
Natural Risk Management............................................................................48
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page iii  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Appendices
Appendix A – Description of Services Required 
Appendix B – GIS Layers held by MNREM 
Appendix C – Mapserver equipment released by SOPAC to Met Office, 
Samoa
Appendix D – Comments from MNREM & MWTI on Draft Inception Report 
Appendix E – Attendance List & Notes from Draft Inception Report 
Workshop 14 April 2005 
Appendix F – MCDEM Comments on Draft Inception Report and Inception 
Review Workshop - Letter dated 18 April 2005. 
Appendix G – List of Persons Consulted for Emergency Management 
Workstream Inception Visit 
Appendix  H – Letter from BICL to MNREM & MWTI dated 22 February 2005
Appendix I - Districts Table and District Program Map 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 1  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Executive Summary 
The Inception Report has substantially confirmed the Consultant’s proposals to undertake 
the project as per the Technical Proposal submitted with the tender with two notable 
exceptions which are outlined below. The project will be managed around the four 
workstreams, viz: 
ƒ
Environmental Management
 covering: 
EIA regulations review 
Environmental monitoring development and policy 
Completion of Codes of Environmental Practice 
Provision of further industry training and development including a contractor 
qualification scheme. 
ƒ
Natural Risk Management
 covering: 
CIM Strategy review 
CIM Plan/SMP review 
Effectiveness Survey 
Completion of CIM Plans for the remaining 28 Districts. 
ƒ
Natural Resource Management
 covering: 
Further development of the application of GIS to the management of natural 
resources. 
Preparation of a sustainable aggregate supply policy. 
ƒ
Emergency Management
 covering: 
A revised NDM Plan. 
A plan and programme for institutional and staff development. 
DMO Office and equipment specifications. 
Agency and stakeholder workshops and response plan development. 
Revised legislation. 
Community education and development. 
Disaster simulations 
Disaster Insurance review. 
 
The two areas where significant changes have been proposed are as follows: 
CIM / SMP Plans 
It has been suggested that a cautious approach be adopted in moving CIM Plans towards 
being SMP’s under the PUM legislation. This has been advocated for two principal reasons: 
ƒ
The original philosophy of the CIM Plan was that of a “partnership” between local 
villages/districts and Government. It is our belief that the ultimate success of the CIM 
Plans will derive more from the articulation of this philosophy than the more 
“regulatory” and “prescriptive” rules based approach which appear to be anticipated 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 2  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
in the SMP’s. This approach may be necessary for the urban and peri-urban areas of 
Samoa but is in our view overly complex for the vast majority of rural districts. 
ƒ
Secondly, we have real concerns about the resource implications arising from the SMP 
process.  The process set down in the legislation will require substantial professional 
and technical resources in both MWTI and the community, which to date do not 
appear to have been available or forthcoming. It would in our view be unfortunate if 
all the real advances in coastal infrastructure management and the communities 
comprehension of the underlying issues were put at risk by the adoption of a resource 
hungry approach at this point in Samoa’s development. We do however see how 
subtle amendments can be made to the CIM Strategy and CIM Plan formulation 
process to anticipate this step at an appropriate point in the future. 
Emergency Management Task Content and Timing 
The number of work tasks has been reduced from 12 to 10 by combining some tasks and 
the order of completion of tasks has been varied from that sought by the TOR. The 
reordering has been undertaken to allow for a more logical work flow and for the outcomes 
of key tasks to feed into subsequent tasks. 
One matter which has not been resolved relates to the review of the National Co-ordination 
Centre. This was not allowed for in our original proposal nor was it a specific explicit 
requirement of the TOR. The PUM Division of MWTI in a letter of 13 April 2005 providing 
comments on the Draft Inception Report (See Appendix D) suggests that the MCDEM 
Review report (July 2004) has already provided discussions on and a summary of the NCC, 
implying that it would be a relatively straightforward task to include a review of the NCC 
within the current scope of work.  MCDEM’s letter of 18 April 2005 (Appendix F), states 
that a review of the NCC is “pivotal to the effectiveness of existing or new disaster management 
arrangements and any review of the disaster management structure”
 implying that this piece of 
work has yet to be undertaken. 
We have proposed that this work be undertaken as additional items to the scope of work 
under the contract and would be pleased to provide our fee estimate for doing this. 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 3  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
1 Introduction 
1.1 Project 
Description 
The Terms of Reference for the project describe the project as follows: 
‘The Government of Samoa (The Client) requires services for: 
 
1. Environmental Management - provide assistance to: (i) finalise the EIA regulations so that 
they can be endorsed by Cabinet and passed into law (and the requirements will then 
apply to all government and private sector proponents); (ii) provide further support and 
training in environmental management practices (including the COEP) relating to physical 
works, especially targeted at the design and construction industry; and (iii) assist to embed 
the routine process of data collection for environmental monitoring and impact assessment 
as a mainstream activity within MNREM. 
 
2. Natural Risk Management - expand the CIM strategy to: (i) incorporate issues relating to 
climate change adaptation; and (ii) incorporate strategies for other types of hazards (e.g. 
flooding, landslips etc.) and to complete the CIM plans for the remaining 28 Districts of 
Samoa, incorporating coastal and other hazards. 
 
3. Natural Resource Management - train and support MNREM to better manage and provide 
policy advice to government on natural resources using GIS as an analysis tool. The specific 
activities will be identified during project implementation, but will be strongly tied to 
initiatives identified from, or that make use of, the CIM Plans and the policy development 
objectives for MNREM as specified in its corporate plan. 
 
4. Emergency Management - reform the National Emergency Management Plan (NEMP) to 
be consistent with best pacific region practice relating to emergencies, so that there is an 
emphasis on reduction as well as readiness, response and recovery. Apart from rewriting 
the NEMP, the proposed activities will include:  
(i) 
workshops to align the approach forward amongst various stakeholders;  
(ii) 
training and professional development;  
(iii) 
community and organisation awareness training (implemented in conjunction 
with the CIM Plan consultation process);  
(iv) simulations; 
 
(v) 
additional equipment;  
(vi) 
preparation of supporting legislation; and  
(vii) 
review of options for disaster management insurance. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 4  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
1.2 
Purpose of Report 
The Inception Report has the following purposes: 
ƒ
To record the investigations and discussions undertaken during the inception review 
phase of the project. 
ƒ
To review and comment upon the methodology proposed to complete the project in 
the light of those investigations and to propose any alterations thereto. 
ƒ
To provide a detailed workplan for the execution of the project. 
ƒ
To suggest key performance and progress indicators for the project and 
ƒ
To develop an initial risk assessment and risk management plan for the project. 
1.3 
Structure of Report 
Following this Introduction, the report has a further five sections: 
ƒ
Section 2 reviews the methodology proposed by workstream and identifies any 
alterations to that contained in the tender proposal document.  
ƒ
Section 3 contains the detailed work programme and deliverable outputs arising 
therefrom. 
ƒ
Section 4 suggests key performance and progress indicators. 
ƒ
Section 5 contains the initial risk management plan; and, 
ƒ
Section 6 summarises the key decisions required or actions to be taken as a result of 
this report. 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 5  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
1.4 Definitions 
The following definitions and abbreviations are used in this report: 
AusAID 
Australian Agency for International Development 
Beca 
Beca International Consultants Ltd 
CIM Plan 
Coastal Infrastructure Management Plan 
CIMS 
Coastal Infrastructure Management Strategy 
COEP 
Codes of Environmental Practice 
DMO 
Disaster Management Office (part of MNREM) 
EIA 
Environmental Impact Assessment 
GEF 
Global Environment Facility  
GIS 
Geographic Information Systems 
GoS 
Government of Samoa 
GPS 
Global Positioning System 
IAMP-1 
Infrastructure Asset Management Project – Phase 1 
IDA 
International Development Agency (World Bank) 
LAN Local 
Area 
Network 
MCDEM 
Ministry of Civil Defence and Emergency Management 
MNREM 
Ministry of Natural Resources, Environment & Meteorology 
MOF 
Ministry of Finance 
MWTI 
Ministry of Works, Transport and Infrastructure 
PAD 
Project Appraisal Document 
PCC 
Project Coordination Committee 
PMU Project 
Management 
Unit 
PUMA 
Planning and Urban Management Agency 
SOPAC 
South Pacific Applied Geoscience Commission 
SPREP 
South Pacific Regional Environment Programme 
SIAM-2 
Second Infrastructure Asset Management Project 
SMP Sustainable 
Management 
Plan 
WB World 
Bank 
 
 
fono village 
council 
komiti committee 
matai chief 
pule customary 
authority 
pulenu’u government 
village 
representative, 
village 
mayor 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 6  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Methodology by Workstream 
2.1 
Environmental Management Workstream 
2.1.1 
Introduction and Overview 
Our Inception review discussions have largely confirmed the understanding we had of the 
required actions to achieve the overall project goals in regard to this portion of the work. 
The draft EIA regulations have been being applied with varied levels of success and what 
is now required is for them to be the subject of a rigorous technical review and to then be 
promulgated under the relevant legislative framework. The recently passed PUMA Act 
2004 provides for the drafting of regulations to give effect to the EIA requirements. 
2.1.2 EIA 
Regulations 
Review 
Discussions held with relevant MNREM staff during the Inception review have confirmed 
the broad applicability of the methodology as set out in the tender proposal. This involved 
the following key steps: 
ƒ
Structured interviews with key stakeholders to assess the application of the draft 
regulations. This will include key staff in MNREM and other stakeholders including 
MWTI, EPC, SWA, SamoaTel, NGO’s and other aid donors. 
ƒ
Production of an annotated review of the current draft regulations with suggested 
areas for amendment and addition/deletion 
ƒ
Facilitation of a half-day workshop for key stakeholders to agree the technical scope of 
revised draft regulations. 
ƒ
Preparation of a Technical Paper on the scope and content of the revised draft EIA 
regulations for the guidance of the legal drafting team. 
2.1.3 
EIA Regulations Legal Drafting 
The four stage process proposed in the tender proposal is still appropriate with minor 
modifications. 
Stage 1 involved initial consultations and consideration of the MNREM principal act 
together with the PUMA Act 2004. With the transfer of the PUMA division to MWTI there 
will need to be consequential amendments to the PUMA Act to replace the responsible 
Minister amongst other matters. In addition it will be necessary to review the MWTI 
principal act and other relevant legislation. It will be necessary for confirmation to be given 
that MWTI will be responsible for the EIA regulations. We have not allowed for the 
additional work associated with changes to the PUMA Act in our tender but would be 
prepared to undertake it as a variation to the contract if required. 
The PUMA Act provides for the making of regulations under the Act to give effect to the 
provisions of the Act. EIA related matters appear to be specifically provided for in sections 
105(2)(j), (k), (s), (t) and (u) which provide for the form, content, examination and making 
available for public comment of EIA’s and statements of environmental effects. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 7  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Stages 2, 3 and 4 will proceed as outlined in the tender proposal. These are briefly 
described below. 
Stage 2 allows for a broad range of consultation both inside and outside MNREM and 
MWTI on the findings from Stage 1.  We will also consider how the Memorandum of 
Understanding between MNREM and MWTI regarding the application of the draft EIA 
regulations to Government works, developed under IAMP-1, can be accommodated in the 
new regulations.  Findings will be documented in a brief report summarising views 
collected during consultation. 
Stage 3 involves the redrafting of the regulations.  Taking the output from the Technical 
Review and any other matters identified in Stages 1 and 2, a revised set of draft regulations 
will be prepared in a content, style and format commonly used in Samoa.  These will be 
circulated to and discussed with key staff in MNREM and MWTI.  Following MWTI’s 
acceptance of the draft regulations, these will be discussed in detail with the AG’s office 
who will be responsible for the final processing of the regulations to Parliament. 
Stage 4 involves the finalisation of the draft regulations including circulation to 
stakeholders outside MWTI, conducting workshops for MWTI , MNREM and other 
stakeholders to explain the revised draft regulations and final amendment of the draft 
regulations following the workshops. 
Output will be finalised draft EIA regulations ready for submission by MWTI to Cabinet 
for approval including a supporting draft Cabinet paper. 
2.1.4 Environmental 
Monitoring 
It was not clear from Inception review discussions how this function will be split in future 
between the relocated PUMA Division in MWTI and MNREM. This matter requires early 
attention to provide the necessary clarity of functions. Overall the primary focus of the task 
will remain regardless of who will be responsible for its performance. 
The task requires an assessment of the role environmental monitoring can and should play 
in assisting MNREM/MWTI to discharge their statutory obligations and desired core 
competencies under their Corporate Plans.  We will commence this by reviewing and 
confirming with MNREM and MWTI senior management staff in a workshop what those 
key activities are, assessing where the responsibility lies for that function, where the two 
Ministries currently feels they are at and where they desire to be in the short, medium and 
long term.  Objectives and action plans will be formulated for these future positions. The 
action plans will define the who, what and how together with a consideration of the 
potential funding of these actions.  We would envisage a series of perhaps three interactive 
workshop sessions to develop the action plans with key MNREM/MWTI staff.  It will be 
important for the staff to be intimately involved in the development of the action plans as 
this will secure ownership of them. We would wish to reserve the option of seeking a 
contract variation if this involves significantly more work than envisaged before the 
relocation of the PUMA Division. 
We will review data collected to date, potential future data collection and suggest 
appropriate analytical methods and techniques to provide for the data to support desired 
policy initiatives.  Where policy initiatives are currently being pursued or are desired in 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 8  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
future, we will identify the data sets necessary to support them.  A desktop review will be 
undertaken of selected practice elsewhere in the Pacific (including NZ and Australia) and 
in other countries to draw out common good practice elements and identify areas of 
potential difficulty or limitations. 
The output from this task will be Environmental Monitoring Mentoring Workshops and 
Action Plans. 
2.1.5 COEP’s 
Review 
The interim codes, prepared by Beca in 2000, focus on road planning, design, construction 
and maintenance along with associated coastal protection works. 
The intention is to broaden the scope of the COEP’s to cover mainstream construction 
activities in general, in particular those for infrastructure works where there is the potential 
to have adverse effects on the environment.  
The main advantage of the COEP is that, if they are adopted for particular public works, 
they reduce the amount of information that needs to be provided under the EIA process.  
This has been agreed as part of a Memorandum of Understanding between MNREM and 
MWTI and has already been demonstrated on recent projects.  With respect to private 
works undertaken by other major agencies, similar positive benefits can also be realised. 
It is therefore appropriate that the COEP’s be developed into a complete set of codes and 
expanded to cover routine physical works undertaken by other infrastructure providers 
such as EPC, SamoaTel and the Samoa Water Authority.  It will also be appropriate to 
review the application of the interim COEP’s and their practical effectiveness. 
Beca prepared the original COEP’s under IAMP-1 and provided training sessions for staff 
from PWD, DLSE, Samoa Water Authority and EPC.  A presentation on the COEP’s was 
also provided to the Samoa Institution of Engineers.  As part of this process it was signalled 
to the consultant industry that it was the intention to make compliance with the COEP’s 
mandatory on Government contracts and that the possibility of requiring knowledge of the 
COEP’s would be a pre-qualification criteria for future Government works contracts. We 
will review the application of these policies on recently let Government contracts with 
selected key staff from MNREM and MWTI plus obtain information on typical works 
activities from other bodies such as EPC, Samoa Water Authority, SamoaTel and any other 
substantial works undertakers identified.  
Results of these investigations will be reported back to a workshop of relevant parties and 
recommendations will be made for new/revised COEP’s.  Draft new/revised COEP’s will 
be prepared and circulated for comment before being finalised.  A mechanism for 
approval/adoption of the COEP’s will be discussed and agreed with MWTI. 
2.1.6 
Industry Training & Development 
The objective of this portion of the project is to improve the general awareness of the 
consulting and contracting industry of the new EIA regulations and enhanced COEP’s. To 
complete this task successfully it will be necessary to identify the majority of consultants 
and contractors working in the newly developing private market. Most consultants belong 
to the Samoa Institution of Engineers and can be contacted via MWTI, MNREM and this 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 9  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
body.  For the contracting industry the situation is less clear.  We understand that at 
present there is no formal association of contractors in Samoa but that initial moves are 
underway to form such a group based around the NZ Master Builders Federation model.  
Through the Samoa Institution of Engineers, the local consulting industry and the 
combined knowledge of both MNREM and MWTI we will prepare a listing of known 
domestic consultants and contractors.  We propose that a series of workshops, probably 
three or four will be required at which the general concepts of the EIA regulations, 
environmental management procedures, and the COEP’s will be introduced.  
We would suggest that a trial period of application of the new/revised EIA Regulations 
and COEP’s be undertaken on Government works contracts under SIAM-2.  Specific 
obligations to comply with the regulations and codes will be written into the Conditions of 
Contract and their application reviewed during both contractor selection and works 
implementation.  We have assumed that the mentoring required under this task will not 
exceed 2 person weeks for the entire project. 
2.1.7 Contractor 
Qualification 
Scheme 
Our discussions with a number of consultants and contractors during the Inception review 
have confirmed our initial views that the key ingredients of a Contractor Qualification 
Scheme should be that: 
ƒ
It should be simple and easy to administer; 
ƒ
It should deliver improved environmental outcomes; 
ƒ
It should cover as many contractors as possible to ensure the pool of available 
contractors for Government projects is not unduly limited. 
Our initial thoughts are that contractors be required to attend a set number of training 
sessions, that they then complete a practical test to confirm the knowledge gained and then 
that qualification be valid for a set period of time.  We consider that the qualification 
should attach to individuals rather than firms and that there should be a self-instruction 
process to allow for additional persons to qualify after the initial courses have been 
conducted.  We would aim at developing the training materials such that they could be 
used as self-instruction programme and/or be delivered by trained personnel in MNREM 
and MWTI. 
We will develop this approach further during the initial visit for this task and will prepare 
a Technical Paper for presentation at a workshop.  Following this, we will prepare a draft 
Contractor Qualification Scheme for discussion with MWTI and stakeholders.   
A key aspect of the success of the Contractor Qualification Scheme will be the linkage to 
the mandatory requirements to construct works in accordance with the COEP’s and for the 
necessary consents to be obtained under the EIA regulations before works commence.  This 
can be achieved by additions to the Standard Conditions of Contract applying to 
Government works.  We will explore with MWTI and other stakeholders means by which 
this can be achieved for other works. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 10  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
2.2 
Natural Risk Management Workstream 
2.2.1 
NRM1.1-1.3, 2.2 CIM Strategy 
Introduction & Overview: 
Our Inception visit has confirmed that the CIM Strategy (and CIM Plans) have become well 
engrained in a diverse range of planning and management frameworks and systems since 
its adoption in 2001. In fact it was very pleasing to observe the extent to which CIMS has 
become a foundation document for most of the agencies and stakeholders active in coastal 
management.  
Accordingly, our philosophical approach is not to reinvent the wheel. Rather, for the CIM 
Strategy Review we propose to build on the success of the IAMP-1 projects and to further 
cement the role of CIMS as a foundation national policy instrument for planning, hazard 
avoidance and mitigation. 
Further, feedback from the Inception visit has identified other key strengths of CIMS which 
must be retained or enhanced through the review process. In summary these key success 
factors are: 
ƒ
A concise, attractive and easy to read format for the Strategy with detail housed in 
supporting technical background reports. 
ƒ
Clear linkages from strategy through goals, objectives, policies and implementation 
methods. 
ƒ
Adoption of the concept of a partnership between government and villages (cementing 
integration of national and local responses to management). 
ƒ
Focus on a hierarchy comprising of four core groups of tools that can achieve effective 
implementation (Information, Evaluation and Monitoring; Education and Awareness; 
Management and Use of Land and Resources; Intervention Actions). 
ƒ
Emphasis on ‘self management’ and an ethic of mutual responsibility under the 
umbrella Vision of “Resilience”. For all agencies, stakeholders and communities to be 
resilient they must be “adaptive, responsive and quick to recover”. 
One area that can be strengthened from IAMP-1 is the dissemination and adoption of CIMS 
by a wider cross section of Samoan society. This is best achieved by education and 
awareness raising and is the focus of specific attention as part of the detailed methodology 
and work plan as outlined later in this report. 
Methodology: 
Task 1.1 CIM Strategy Review
Broadening the Scope of CIMS: 
By definition CIMS mainly addresses hazards and management of the coastal environment. 
This reflects planning priorities for Samoa with over 80% of the population living in close 
proximity to the coast.  
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 11  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
CIMS and the supporting CIM Plans address coastal hazards including erosion, landslip, 
flooding and severe events including cyclones and tsunami. The existing CIM Strategy has 
also incorporated matters arising from the likely effects of sea level rise as a result of 
climate change together with the predicted increase in the number and severity of extreme 
weather events.   
Because many hazards can impact upon the same coastal areas, in practice the 
identification and mapping of coastal hazard zones undertaken during IAMP-1 has 
captured those areas of Samoa most at risk from the diverse range of hazards that exist.  By 
way of example, the Coastal Flood Hazard Zone (CFHZ) in many coastal villages will be 
very similar for a variety of event scenarios including coastal inundation by waves, 
tsunami or by overtopping of rivers and streams discharging at the coast. The appropriate 
policy responses for these hazards (as identified in CIMS) are often also similar (whether 
they be avoidance by retreat inland or mitigation perhaps by the relocation of key 
infrastructure or community assets to safer sites).  
In general therefore there is no need or justification for a substantive review of the content 
of CIMS. Emphasis should instead be directed to reviewing the utility of the existing 
policies, tools and actions and strengthening these to address the broader scope sought by 
SIAM-2.   The review will also examine current best practice around the Pacific region and 
update CIMS where appropriate to incorporate best practice.  Of note, Beca together with 
the NZ National Institute of Weather and Atmospherics (NIWA) has recently completed a 
national Planning Guidance Note for the Ministry for the Environment to provide Regional 
Councils and Territorial local authorities in NZ with practical guidance and good practice 
examples on appropriate planning responses to climate change. 
With respect to incorporating additional policy in CIMS to address inland hazards such as 
flooding, river erosion and landslides, we note that Addendum 1 to the TOR has clarified 
the scope of works required and this has been discussed further during the inception visit.   
The focus of consideration of these further hazards is primarily directed to their potential 
to adversely affect the major population areas and their associated infrastructure. Again 
these concentrations largely sit within or close to the coastal environment.   Where hazards 
or land management issues are so significant that they have national implications, they are 
to be examined on a whole of catchment basis and we envisage the need for some 
additional objectives, policies and management tools to address matters of catchment wide 
relevance.    
Aside from policy development for CIMS, we propose to develop for the CIM Plans 
additional GIS based interpretative layers to assist as necessary with the identification of 
potential hazard zones within the coastal areas beyond those already identified in IAMP-1. 
For landslips we will review the existing geological maps plus review topography, 
geology, seismic risk and develop a susceptibility classification as an additional GIS layer. 
Depending upon the availability of information such as the geological maps, this may be a 
preliminary analysis only and further detailed investigation may be required in future to 
refine the analysis in areas of dense population or perceived higher risk.  
For river and stream flooding hazards we will review basic data availability and flow 
records for identified catchments.  We understand rainfall data is available for selected sites 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 12  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
around Samoa from Meteorological Office records.  This will be reviewed to identify 
typical patterns of rainfall distribution together with any information on peak events and 
historical flood records.  We will review the rivers and watercourses data layers in the 
existing GIS to identify key catchments for review with relevant MNREM and MWTI staff.  
We are also aware of anecdotal information of flooding from past major storm events plus 
some details at the village level gathered during the CIM Plan consultation under IAMP-1.  
Further useful anecdotal evidence will emerge from the 28 additional CIM Plans.  We will 
utilise all this information to develop a GIS layer identifying locations which may be 
susceptible to flooding hazard.  Again the degree of detail possible will be limited by the 
data available, but we will indicate where further field or technical work could be 
undertaken to improve the accuracy of the output.  
One additional hazard that has been identified from discussions during the Inception Visit 
stems from river and stream bank erosion. This is particularly evident in the lower 
catchment of some waterways and hence often already falls within a Coastal Hazard Zone. 
CIMS can be strengthened by the addition of policy guidance for hazard avoidance or 
mitigation and in particular to assess proposals for waterway stop banks and walls. We 
understand PUMA is receiving increasing numbers of applications to erect training walls 
and controls structures along the margins of eroding waterways. As is often the case with 
sea walls this tends to be rather a knee jerk reaction to a perceived immediate risk rather 
than seeking to gain a fuller understanding of the root causes of the emerging hazard. A 
range of response options should be identified and evaluated before selecting a preferred 
solution. CIMS can help provide an appropriate assessment framework in this regard. 
Scope of Work (Sub Tasks):
 
ƒ
Meetings and targeted consultation with key Government staff (users of CIMS)  
ƒ
Gap Analysis 
ƒ
Desk top review of current best practice for South Pacific coastal management. 
ƒ
Technical research and mapping as appropriate of additional hazards 
ƒ
Draft revised CIM Strategy 
ƒ
Prepare material for formal CIM Strategy review Workshop   
Output: 
ƒ
Expanded draft CIM Strategy with additional content as necessary to address broader 
scope of hazards. 
ƒ
Additional hazard layer overlays for the MNREM GIS system. 
 
Task: NRM1.2 Revised CIM Strategy
We note the intention that MNREM should lead this task and are fully supportive of this 
approach – the CIM Strategy is now a Government approved national policy statement 
“owned” by MNREM.   
We suggest that the formal review process commence with a structured 3 hour workshop 
involving the Beca project team, MNREM staff and other key stakeholders involved in the 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 13  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
application of the CIM Strategy. This will principally be those involved in the initial CIM 
Plans, including key national infrastructure providers such as EPC, SWA, SamoaTel etc.  
The consultant team would be willing to facilitate the workshop if required and we have 
discussed an appropriate format and framework with key counterpart staff as part of the 
Inception Visit. 
From our Inception Visit we have also confirmed that the existing CIM Strategy is widely 
used and understood. However some stakeholders and infrastructure providers have seen 
significant staff turnover since 2001 and there are one or two new agencies of direct 
relevance (for example the Ministry of Women, Community and Social Development).  
New staff within these organisations are not so familiar with the background to CIMS or its 
application at both national and local levels. A structured workshop provides an 
opportunity to introduce newcomers to the CIM Strategy and CIM Plan preparation 
process. We recommend that the first half hour of the workshop be devoted to a short 
presentation on the philosophy of and major policy directions contained in the existing 
CIM Strategy. To ensure workshop participants come well prepared we also envisage the 
need for the Beca Project Manager to visit some of the key agencies in advance to provide a 
short introduction and any background information they made need.  
With respect to workshop structure, the focus will be on reviewing the component sections 
of the Strategy in a “step by step” manner similar to the way the initial draft of the Strategy 
was formulated. 
Whilst not mentioned in the TOR, it will be important to consider any implications for the 
CIM Strategy arising from the review of the CIM Plans and the potential actions required 
to promulgate them as SMP’s under the PUMA Act.  For completeness alone, it would be 
desirable to ensure that there is appropriate cross referencing.  We will take the output of 
Task NRM 2.1 into account in this process as they will be proceeding in parallel. 
Upon completion of the workshop and any further consultation required, we will prepare a 
revised draft of the CIM Strategy together with a draft Cabinet paper explaining the 
rationale behind the changes proposed.  We will review this with senior MNREM staff and 
adjust the draft as required to ensure it is suitable for the CEO to recommend to the 
Minister for a Cabinet discussion. 
Following cabinet adoption we recommend a wide spread publicity campaign be launched 
to highlight coastal management issues and to signal the start of another round of local and 
stakeholder consultation geared to preparation of CIM Plans for the remaining 28 Districts.  
The need to continue to “advertise” and widely advocate the use of the CIM Strategy was 
highlighted during several consultations undertaken as part of the Inception Visit. In 
general it is apparent that there is a high degree of awareness of coastal hazards associated 
with cyclones but only limited appreciation at a village level of the potential impacts and 
need to avoid or mitigate other hazards such as erosion, inundation and localised flooding.  
With respect to appropriate media, it appears that television and radio offers the best 
potential to capture a wider audience than is possible through conventional consultation 
programmes. Government staff interviewed during the Inception Visit suggested that a 
video documentary could be developed tracing the process from review of the CIM 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 14  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Strategy through to village consultation for the CIM Plans. ‘Signature projects’ highlighting 
good practice and successful outcomes from IAMP-1 can also be marketed this way. 
 The potential to highlight the SAMPII projects as part of a national education programme 
(as was done very successfully on Environment Day for the CIM Strategy in IAMP-1) 
should also be pursued.  
Beca is happy to meet with PUMA staff to assist them formulate a publicly campaign and 
can help with source material, however our contract does not currently extend to leading 
the campaign or producing material suitable for multi-media or public education 
programmes. We would be happy to lead this additional work if required. 
Scope of Work (Sub Tasks): 
ƒ
Agree attendance list and workshop protocol with the Project Component Manager 
ƒ
Pre-Workshop briefings for key participants by Beca Project Manager    
ƒ
Circulate Workshop invitations, agenda and background material to participants  
ƒ
Half-day workshop facilitated by either MNREM or Beca  
ƒ
Write up minutes and matters arising from workshop 
ƒ
Revise final draft of reviewed CIM Strategy 
ƒ
Draft Cabinet Paper and brief CEO prior to submission 
ƒ
Assist with formulating strategy for publicity campaign. 
Output: 
ƒ
Completion of CIM Strategy Review Workshop 
ƒ
Revised Draft CIM Strategy plus Cabinet paper. 
 
Task: NRM 1.3 Revised CIM Strategy Background Report
We will develop a revised CIM Strategy Background Report to document the process, 
findings and outcome of the review process from the Task above.  This will include: 
ƒ
An outline of the review process adopted, its findings and the recommended changes 
to the strategy. 
ƒ
A record of the consultation undertaken and a summary of key views expressed plus 
the response to those views. 
ƒ
Identification of key performance indicators for monitoring purposes. 
ƒ
Any assumptions adopted. 
ƒ
Recommendations for future review and development. 
This report will be No 8 in the series of CIM Strategy Background Reports and will 
complete the reference materials developed under IAMP-1.   
Output: 
Revised CIM Strategy Background Report. 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 15  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Tasks: NRM 2.1 SMP Requirements Review& NRM2.2 Completed CIM Plans Review
Our preliminary view at the time of tender was that based on our understanding of the 
new PUMA Act, it would be possible to translate existing CIM Plans into Sustainable 
Management Plans (SMPS) on the basis of the requirements outlined in sections 12-19 of 
the Act.  
It is still our view that the Act contains sufficient flexibility to allow for the CIM Plan 
process to transition into the preparation of SMPs, however following our Inception Visit 
we now have some doubts about the wisdom of such an approach and seek to discuss and 
resolve this with key stakeholders in MWTI and MNREM as soon as possible.  
Our reservations with the relationship between the CIM Plan process and SMP process 
stem mainly from a philosophical stand point. We also note however that there are 
currently no SMPs in draft or finalised so the process to convert CIM Plans might well be 
the country’s first attempt and a bad experience now could impact on wider application of 
the SMP model later.       
It has always been the intention (and we believe is now a widely accepted principle) that 
the CIM Plan is a non statutory instrument something akin to a ‘charter’ registering a 
partnership between government, villages and other key stakeholders to improve 
community and infrastructural resilience to coastal hazards.     
The engagement process with communities has been very effective because of this 
philosophical stance. We wish to retain such a positive focus for the next 28 plans.  
Having further reviewed the PUMA Act and discussed this matter further with PUMA 
staff, we believe that there is a risk of undermining the positive process by moving the CIM 
Plan process too quickly towards a more regulated framework.  In particular we see 
significant problems with a quick conversion of the existing 15 CIM Plans, because these 
were prepared through an intensive community consultation process, in good faith, and 
without any suggestion that at some point the CIM Plans would take on a more formal and 
or regulatory function.  
Having reached this preliminary conclusion as a study team, we have seriously evaluated 
alternative ways forward. In short we envisage three alternatives: 
ƒ
Proceed to convert all CIM Plans to SMPs and take them through the prescribed 
statutory process. 
ƒ
Abandon the idea and leave the CIM Plans as stand alone planning documents 
outlining how an agreed partnership approach to improving resilience can be 
achieved. 
ƒ
Adopt a pragmatic approach which retains the spirit and intent of the CIM Plan 
process but identifies ways that some matters can be progressed through to forming 
the basis for SMPs. 
We see real risks with respect to the first option.  However it should not be necessary to 
abandon the potential to convert some or certain aspects of the CIM Plans, hence our 
preference at this stage would be to adopt the third approach.  
What we have in mind in this regard is outlined below as a series of logical steps for both 
existing and new CIM Plans 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 16  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
For existing CIM Plans  
1.  Review existing CIM Plans to identify key areas and key local recommendations 
that might be best progressed through a more formalised SMP.  Prepare a report on 
how parts of the existing CIM Plans might best be translated (if at all). 
2.  Identify elements common to all CIM Plans that might benefit from being captured 
in a generic or national coastal SMP addressing Good Practice in Coastal 
Management. What we have in mind here are basic parameters such as those listed 
below: 
ƒ natural hazard buffer and coastal habitat protection 
ƒ avoidance of new development in Coastal Hazard Zones 
ƒ safe location  policy and design guidance for life line infrastructure, key 
community buildings and emergency shelters    
ƒ standards for the location of houses with respect to roads, streams, the coast etc. 
ƒ simple environmental standards and other practical initiatives to enhance local 
sustainability. 
3.  Investigate and make recommendations on an appropriate process to consult 
Districts on whether and how some of their desired local CIM Plan outcomes might 
be introduced to the SMP Plan preparation process. 
4.  Pilot the SMP consultation process with one District to test the reactions and 
response. 
5.  Agree a way forward for the existing CIM Plans and review scope of work and 
contract accordingly. 
For new CIM Plans 
1.  Include an overview and discussion of the PUMA Act and SMP process in the first 
round of village consultations and gauge understanding and acceptance or 
otherwise of the new process. 
2.  Identify as part of the Plan preparation process matters that should or should not 
be captured by a local SMP. 
3.  Consult on the appropriateness of formalising some of the CIM Plan 
recommendations.  
4.  Draft the CIM Plan with a section on matters that could possibly be progressed 
through either a generic or local SMP and seek specific feedback.   
5.  Review the draft in light of consultation.  
6.  If appropriate (but do not make it mandatory) include a section in the completed 
and signed off CIM Plan on matters that will be progressed through either a generic 
or local SMP.   
Finally, as a general observation we would see the greater detail referenced in S32 of the 
PUMA Act (Development Standards) as being more appropriate to urban development 
such as the main centres of Apia and Salelonga.  Whilst in due course it may be necessary 
to move towards more detailed standards for the whole country, in our view a simpler 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 17  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
approach may be an appropriate first step encouraging better rural and village 
development through a more generic good practice guide as discussed earlier.  This would 
allow more resources to be focused upon the development of management plans for the 
urban area and recognises the critical need for local partnership and engagement (rather 
than regulation) at a rural and village level. 
Scope of Work (Sub Tasks): 
ƒ
As outlined in staged methodology above 
Output: 
ƒ
Report on content of existing CIM Plans and matters of relevance to PUMA Act and 
SMP’s 
ƒ
First draft of a ‘Good Practice in Coastal Management’ guide that might form the basis 
for a generic or national SMP. 
ƒ
Report on pilot conversion project recommending a way forward for the existing CIM 
Plans. 
ƒ
Section on possible SMP content in each new CIM Plan.   
 
2.2.2 
NRM2.3 CIM Plan Completion (RFP Clause 20, 21) 
Plans will be prepared by District as per the original methodology, but several districts will 
be grouped together to improve data gathering and workshop setup efficiencies.  
It is assumed that two Teams will be operating during preparation of the CIM/SMP Plans, 
but the Village and District Workshops will be staggered so that only one team is “on the 
road” at any one time. Where logistical reasons dictate and staff resources allow, however, 
two teams involving two separate Districts may operate in the field at the same time. 
In the months following the first inception workshop there will be a second workshop of all 
likely CIM Plan team members to explain the plan preparation process in detail.  This CIM 
Plan Preparation workshop will be followed by a test run involving all team members to 
prepare a plan for a single district (Si'umu). 
Beginning in July 2005, the team members involved in the Si’umu plan will then split into 
two teams and both will head for the western end of Savai’i for a second test run involving 
all three Districts in Group 2  (Vaisigano II, Falealupo and Alataua West). After that (in 
October) the two teams will then begin working independently in the same general area of 
the country. The work has been clustered around single geographic areas so that the two 
teams can share resources if necessary and make it easier to organize the orators and 
meeting venues.  
The more complex districts (involving the north coast area of Upolu around Apia) will be 
tackled in mid 2006, after the teams have had a reasonable amount of on the ground 
experience, but not at the end of the project, so there is sufficient time should these districts 
prove to take slightly longer to secure agreement. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 18  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
2.2.3 
NRM2.4, 2.5, 2.6, Public Awareness, Effectiveness Survey (RFP Clauses 
22,24,) 
The approach to this work element remains as per the original methodology. The main 
survey work will be undertaken prior to beginning the formal CIM Plan preparation (apart 
from the first “test” plan). Plan preparation procedures will be continuously monitored and 
altered if necessary to ensure that the final plans are the result of full and fair public input. 
2.3 
Natural Resource Management Workstream 
2.3.1 
Mobilisation of Consultants  
Substantive work by the international consultants in Samoa began on 17 February 2005 
with the arrival in Apia of the Team Leader (Graeme Roberts) and Project Manager (Ted 
Wells).  Peter Newsome (Natural Resource Management workstream leader) arrived for 
the period 22-25 February. The consultants’ time was mainly spent visiting, collectively and 
individually, stakeholder divisions and agencies whose activities should harmonise with 
the goals of the MNREM and who manage datasets of relevance to the project. 
2.3.2 
Inception Activities -Summary of Activities Undertaken 
Activities and tasks during the Inception review closely followed the Consultants’ 
Technical Proposal.  These included: 
(a)  Establishing the project office; confirming the TOR, financial and institutional 
arrangements; 
(b)  Discussions with the Chief Executive Officer and senior MNREM staff; 
(c)  Meetings with key individuals within MNREM and other ministries to collect 
information and compiling an inventory of available relevant spatial and non-
spatial data; 
(d)  Developing a risk management plan based on AS/NZS4360 (See Section 5 for 
details); 
(e)  Based on meetings with counterparts and key ministries revision of the work plan 
and implementation schedule. 
2.3.3 
Initial Findings - Imagery and GIS Data Layers 
a. Aerial 
Photography 
MNREM have two sets of recent digital aerial photography: 
ƒ
1:5,000 scale natural colour taken in 1999-2000 by Air Research (Australia) Ltd (who 
later went out of business though their records were taken over by ‘Fugro’). Coverage 
is of coastal areas of all islands and inland areas of Upololu in the Lepale-Alesia-Vitele 
area, the western and central cross-island roads and the O Le Pupu-Pu’e National Park, 
222 frames in total. Image resolution is 0.8m and, with each frame comprising a 
65MB.tif, total size of all frames is approximately 14GB. We are informed, but could 
not confirm that the negatives of this photography are held by the MNREM. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 19  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
ƒ
1:50,000 scale natural colour taken in 1999-2000 by Air Research (Australia) Ltd. 
Coverage is of all islands.  Frames have been tiled to equate with the current 1:50,000 
scale topographic maps of which 6 cover the country. Each tile is a 300MB.tif with total 
size of all six tiles of approximately 1.8GB. We are informed, but could not confirm that 
the negatives of this photography are held by the MNREM. 
b. Satellite 
Imagery 
IKONOS multispectral imagery has been acquired for all Samoa. These data have not yet 
been rectified. Rectification is being done by MNREM using a method advised by SOPAC 
that uses ground control points alone, and not GCPs combined with a DEM. 
c.  GIS Data Layers 
The MNREM have a respectable collection of GIS data accessible from about five GIS 
workstations (primarily MapInfo but they have one ArcGIS-9 licence). Appendix 3 presents 
a list of those data layers described in the MNREM metadatabase. The origin of these data 
layers is often obscure even in the metadatabase. Probable origins include: 
ƒ
the early 1:20,000 scale topographic maps (NZMS174) captured by tablet digitizing 
ƒ
contours derived photogrammetrically from recent aerial photography 
ƒ
screen-digitised features from digital imagery 
It is difficult to determine whether multiple occurrences of the same data layers found in 
several locations are all unaltered replicates of one undetermined original or multiple, 
different, representations of that feature layer. 
We are informed that the roads and rivers and 20m contour layers were captured by 
photogrammetry in Australia from the 1:5,000 aerial photography. 
There are three immediate issues associated with the data layers as they presently exist. 
1.  Their derivation is obscure and cannot be determined. Metadata is present but 
there are few statements about lineage, the fidelity of the data capture, its currency 
and utility. 
2.  The positional accuracy of the data layers is not evident, except by observation of 
features in relation to each other. Geometric accuracy is also difficult to judge. 
3.  There is no overall data model identifying the specification and relationship of data 
layers.   
The metadata facility used by the Ministry was created by James Atherton under IAMP1 
for the Coastal Hazard mapping and is now used by several agencies in Samoa. 
2.3.4 
Initial Findings - Other Relevant Spatial Data 
Two topographic map series exist for Samoa 
ƒ
The current 1:50,000 scale topographic maps published as six sheets using conventional 
offset printing but using the digital layers now held in the GIS database 
ƒ
The old 1:20,000 scale topographic maps compiled by the New Zealand Department of 
Lands and Survey as NZMS174. (Note: These are now obsolete) 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 20  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
It is believed, but we were unable to confirm, that SamoaTel, and possibly the Samoa Water 
Authority, have created additional digital spatial data layers on their systems, to 
complement those described above and Listed in Appendix B. 
2.3.5 
Stakeholder Agency Functions and their GIS Usage 
a. MNREM 
Mapping 
Section 
The MNREM sees itself as the prime supplier of core data to government and other 
agencies. The Mapping Section has a pricing policy for hardcopy GIS products that seems 
to be a mix of cost recovery and public good. Their policy for electronic data is considered 
more restrictive by some stakeholders. These stakeholders see the MNREM data pricing 
and cost recovery policy as a potential barrier to GIS application in nationally, and locally, 
important applications.  
The Mapping Section of the MNREM are building a tangible record of GIS applications for 
private, business, and government clients including: 
ƒ
Delineating closing lines across the mouth of bays to extend Samoan sovereignty over 
these coastal waters under international law 
ƒ
Providing map material for village consultations on biodiversity protection by the 
Environment and Conservation Division, MNREM (with GEF funding). 
ƒ
Providing map material for Environment and Conservation Division studies on 
watershed areas 
ƒ
Delineating National Park boundaries and subdivisions for Environment and 
Conservation Division 
ƒ
Digitizing new boundaries 
MNREM will now have to successfully integrate the respective GIS capabilities of the 
present Mapping Section with those of the incoming Forestry Division and Met Office. 
b.  Disaster Management Office 
The Disaster Management Office considers GIS to be key to its effectiveness in all four 
phases of disaster management namely; mitigation, preparedness, response, and recovery. 
Key to an effective disaster GIS service would be data layers of community lifelines; roads, 
electricity, communications, water etc. Also important is data of vulnerable and hazardous 
sites like low-lying areas, private, commercial and public buildings oil storage installations, 
industrial sites, reclamations, etc and refugia like schools and hospitals (although most of 
the local responsibility during emergencies is the responsibility of village authorities. The 
DMO is responsible more for mitigation, preparation and information dissemination 
during the response and recovery phases. At present, during an emergency, the authorities 
activate the National Coordination Centre, located in the Police Headquarters, Apia. The 
National Disaster Council determines priorities for response during an emergency. This 
council comprises the PM (as chair), all cabinet ministers, all ministry CEOs, Red Cross and 
the DMO (as secretariat). Disaster response is by agencies executing their normal functions 
such as, police/fire for rescue, PWD for roads, EPC for electricity, etc. DMO would like to 
acquire some basic resources for use during emergencies like communications equipment, 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 21  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
shelters, generators, tools and equipment, food and water to sustain the NCC during times 
of crisis, and a GIS to input and analyse information. 
c.  PUMA Sustainable Development Section 
The Sustainable Development Section of PUMA (working under the Planning and Urban 
Management Act 2004) is responsible for processing all development consents, evaluating 
their environmental impact and recommending approval or otherwise to the Planning and 
Urban Management Board. Activities requiring consents include: 
ƒ
Subdivision (Technical Services Division, MNREM also involved) 
ƒ
Building 
ƒ
Land clearance 
ƒ
Sand mining (Land Management Division, MNREM also involved) 
ƒ
Reclamation (Land Management Division, MNREM also involved) 
Each village has a pulenu’u or mayor who acts as an intermediary between the people and 
central government. Every month there is a meeting of pulenu’u, hosted by the Department 
of Internal Affairs. In this forum, government projects are explained (for promulgation to 
the people) and the concerns of, and issues for, villages are made known to central 
government. Many of the consents handled by the Sustainable Development section are 
vetted by pulenu’u on behalf of their villages, because of their inevitable affect on the large 
area of customary land in Samoa. 
The transfer of PUMA, including its Sustainable Development Section, to the Ministry of 
Works, Transport and Infrastructure could place their function of environmental 
assessment in conflict with the Ministry’s primary role of development. It is also 
considered that Sustainable Development’s Section function of environmental monitoring 
is well away from the core role of the MWTI. There is some speculation and optimism that 
this move might lead to subsequent restructuring to create a standalone planning and 
environmental monitoring agency. 
d.  MNREM Terrestrial Biodiversity Section 
The Terrestrial Biodiversity Section is concerned with the biodiversity of all island 
ecosystems. It undertakes monitoring of birds, bats, reptiles and forest extent. The section 
also does some limited marine monitoring. Monitoring sites and techniques are not well 
standardised yet and nor do they use GIS for storage and analysis. 
National ecosystem mapping was done by the University of Hawaii in 1991.  The NZ 
Department of Conservation also did ecological surveys in Samoa of lowland forests (1991) 
and subsequently of upland forests (date unkn). Forest cover mapping is also available for 
1954, 1989, and most recently, with FAO funding, 2004. There is potential to undertake GIS 
analyses of these data in conjunction with data on hazard and threat to assist the 
management of remaining areas of high indigenous biodivesity.  
Public awareness and education is an obstacle to successful conservation of indigenous 
ecosystems. Incursions into indigenous forest for firewood and agricultural land is constant 
and clearance of both forest and mangroves for development continues. Many still regard 
these areas as a resource to be used without consideration of their other values. Hence, 
public awareness of their fragile state, and their contribution to a healthy island 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 22  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
environment, needs to be raised through publicity and education. Two social structures are 
key to the success of any publicity/education campaign, schools (because children are both 
key to the future and a means of educating adults) and Pulunu’u with their village fono 
(because almost all remaining indigenous ecosystems are in customary ownership).  
The move by MNREM to undertake waste disposal is seen as positive and beneficial. In 
addition, limited recycling (of drink bottles) has begun as well as metallic (steel and 
aluminium cans). Large inorganic waste (appliances, cars, etc.) is also collected periodically 
in order to ensure safe disposal. 
e.  Electric Power Corporation of Samoa 
EPC presently use accounting software to maintain an inventory of assets, but would like 
to move to a GIS-based asset management package. They would be keenly interested in 
accessing reputable spatial data of buildings, road centrelines (if edges are not available), 
land imagery, and property boundaries. They anticipate having to input poles, 
transformers, underground lines junction boxes, switches, etc.  
Of the other utilities companies, SamoaTel is viewed as a maturing user, having been 
running GIS for two years, and Samoa Water Authority also have a MapInfo/ArcView 
system 
f. 
MNREM Watershed Section 
This section was part of the Forestry Division until 3 years ago and will now become part 
of the Forestry Division within MNREM. Now its focus is more on whole ecosystems (from 
the source to the sea) rather than primarily forests. Their function is advocacy in respect to 
watershed management. Data is collected by ground survey. They have a working 
relationship with Samoa Water Authority who has done some water quality monitoring – 
work that the Watershed section would like to see expanded.  
Maps and map information are tools of the trade for this section. Although their use of GIS 
has been limited to date, they foresee potential for this as a powerful tool to analyse and 
depict land use and vegetation change, to facilitate data management and storage, and as a 
medium for the integration of disparate data and disciplines in whole catchment studies. 
The section views the Vaisigano Catchment studies done with FAO funding in the mid 
1990s as a good example. They are also trying to promote the concept of watershed 
protection areas on customary land in for example the Loimata o Apoula area. 
g.  MNREM Parks and Reserves Section 
The Parks and Reserves Section have 4 salaried staff and 38 wageworkers to manage all the 
park and reserve lands in Samoa. It also has a keen interest in the state of ecosystems 
outside reserves as a barometer of condition, trend and threat to the reserve system. There 
is hope that the present reserve system may be expanded from the present single national 
park (O Le Pupu-Pu’e) to include a park around Lake Lanoto’a and perhaps some 
watershed management areas. 
A management plan is in place for the O Le Pupu-Pu’e National Park, and a management 
plan is in preparation for the whole reserve network. Samoa’s ecosystems, while not 
endangered, have suffered a slow decline in the face of shifting agriculture and 
development. Anecdotal accounts point to the incidence of drought and water shortages as 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 23  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
evidence of the reduction in the ability of shrinking forests to regulate the hydrology of the 
islands. Such assertions fuel the debate for a mid-upper slope watershed management zone 
for both Upolu and Savaii. Other threats to environmental stability include exotic pests and 
weeds. Merremia vine (M. Peltata) is of particular concern in successional vegetation and 
disturbed land. 
While not yet users of the GIS, Parks and Reserves can visualise uses for GIS in their work. 
h. MAF/MNREM 
Forestry 
Division 
Forests, mainly indigenous forests, cover 105 000 ha or 37.2 percent of the country’s total 
land area. In the 1990s, the rate of deforestation in Samoa was around 3,000 ha or 2.1 
percent per year. On the global scale, this is quite high. The main causes of deforestation 
and forest degradation are uncontrolled logging operations and conversion of forest lands 
to agricultural land uses. Currently, this is the number one forest-related issue in Samoa. 
Samoa has about 5 000 ha of forest plantations. Plantation establishment began around 
1974 with the planting of mahogany and Australian red cedar. Teak was also established 
during German colonial times. More than 90 percent of the plantation estate was destroyed 
by tropical cyclone Val in 1992. Samoa has banned the export of unprocessed logs. 
Commercial logging in natural forests on the largest island, Upolu, has also been banned. 
Samoa produces sawnwood for its domestic market. Other wood and paper products are 
imported. Much new forestry is now at the village level where Forestry Officers provide 
the first 100 seedlings free and demonstrate planting and silvercultural techniques, to 
empower landowners to plant and manage their own small woodlots. 
The Forestry Division has a fully-functioning GIS (Samoa Forest Resource Information 
System, SamFRIS) built under an FAO funded project due to end in June 2005. With the 
completion of the latest forest inventory survey in 2004 there is a convenient time series of 
spatial forest layers dating from 1954, 1987 and 2004. SamFRIS are believed to have 
digitised catchment boundaries. A significant and unwelcome cost encountered when 
setting up SamFRIS was the data charge imposed by MNREM Mapping Section for basic 
data. 
i. Meteorological 
Division 
The Meteorological Division, now a part of MNREM, undertakes weather station 
recording, daily forecasting, and modelling of extreme events like storm track prediction, 
tsunami and storm surge inundation, and flood modelling. Extension activities are 
focussed on public education and preparedness to develop a capacity for communities to 
recognize and respond to emergencies when they occur. 
The Met Division will become the host site for a Mapserver (Appendix C) being installed 
by SOPAC with EU funding. This presents both an opportunity and a challenge to the GIS 
community in Samoa. Current policies on custodianship and access will be strained as 
demand builds to populate the Mapserver with data.  
Samoa has an ICT advisor (Fuatai Percell) who reports direct to cabinet. Fuatai is strongly 
supportive of the Mapserver as a potential central hub where spatial information is 
available as a key element of e-government. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 24  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
j. 
South Pacific Regional Environment Programme (SPREP) 
SPREP have an agreed division of labour with SOPAC whereby the latter supply all 
technology services and SPREP concentrates on the applications of the data. SPREP also 
facilitates SOPAC’s training activities in the Pacific.  
SPREPs work areas include: 
ƒ
Environmental and sustainability development planning 
ƒ
Systematic integrated approach to planning (environmental/social/economic) 
ƒ
Encouraging better and wiser use of diminishing financial resources 
SPREP promotes a multi-nodal approach to data custodianship with ready access to online 
catalogues and metadata. 
2.3.6 
Resource and Disaster Management Applications of GIS 
1.  Compiling a disaster management GIS for use by the DMO for planning during 
normal times and monitoring and reporting in times of crisis (key contact Filomena 
Nelson). 
2.  Prepare a hazards atlas from existing and new survey (inc landslide, alluvial 
flooding, storm surge flooding, reclamation areas (vulnerable to liquifaction?) etc 
(key contact Fetolai’I Alama). 
3.  Digitise consents (in collaboration with C5?) (key contact Fetolai’I Alama). 
4.  Undertake a national, spatial, vulnerability analysis of remaining areas of high 
indigenous biodiversity (key contact Tepa Suaesi). 
5.  Prepare an environmental resource kit for secondary schools containing maps, 
overlays and study sheets. Would require sponsorship to offset printing cost 
(Western Union, ANZ, National Bank of Samoa, Westpac, Pacific Forum Line, 
Mobil, Fiji Bunjap?) (key contact Tepa Suaesi). 
6.  Undertake an integrated watershed management scoping study that combines the 
interests of MNREM biodiversity, watershed, sustainable development and parks 
& reserves sections 
2.4 
Emergency Management Workstream 
As a result of information learned during the Inception review visit in early March 2005, 
the methodology for the emergency management workstream has been refined and 
enhanced. These refinements are discussed below and reasons given for any departure 
from the original methodology in the technical proposal. 
The original methodology consisted of 12 separate tasks. We have combined two of these 
tasks together and have now identified 10 separate work elements which are discussed 
below. References to the original numbering in both the RFP and the original methodology 
are given alongside each work element. 
2.4.1 
DM 1 – Review Workshop & Mandate (RFP Clause 29/ Proposal ref DM 1.1) 
The emergency management review workshop is an important milestone for the project. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 25  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
The intention of this workshop is to review the scope of work and programme for this 
workstream together with recommendations arising from the MCDEM review. We would 
also like to present four discussion documents at this workshop: 
1. Options regarding changes to national disaster management structures (key committees 
and working groups, their membership and terms of reference etc), 
2. Key features and best practice principles of generic emergency management legislation, 
3. Options regarding organisational and physical location of the DMO, 
4. Key elements of agency response plans. 
 
We envisage that the outcomes of the Review Workshop to be:  
ƒ
An agreed work programme (methodology and key dates) in the form of a full 
Workshop Report 
ƒ
All departments and agencies understanding their involvements at the different stages 
of the project, their required level of inputs, and key decisions to be made and the 
associated options 
ƒ
Feedback on suggestions and options outlined in specific discussion documents 
 
The discussion documents produced, along with the associated recommendations, will be 
independent viewpoints (as required by the RFP). However the final outputs (NDMP, 
legislation and DMO fitout) will reflect the consensus views of the key agencies involved. 
In terms of format, we recommend that the Review Workshop comprise two separate 
workshops as follows:  
Day 1 (full day):  (proposed date Mon 20 June) 
Workshop involving core project participants (eg. MNREM; PUMA; DMO; Meteorological 
Division; MWTI, Ministry of Women, Community & Social Development; Ministry of 
Police, Prisons & Fire; Ministry of Health; Red Cross; NZ MCDEM; SOPAC; IDA). 
Day 2 (half day):  (proposed date Tues 21 June) 
Workshop with utility agencies (eg. EPC; Airport Authority; SamoaTel; Ports; plus DMO; 
Meteorological Division; NZ MCDEM; SOPAC) to outline their specific involvement in the 
project; discuss response co-ordination arrangements; and brief them on the agency 
response planning process, including an introduction to the key response plan interagency 
elements discussion document. 
We recommend that the Review Workshop be held during the week of 20th June 2005.  
This is two months later than the RFP requested. The main reason for this delay is the 12th 
Pacific Regional Disaster Management Meeting, to which the DMO principal officer, 
Filomena Nelson is going. This meeting is in Papua New Guinea from 6-8 June.  A number 
of themes at the meeting relate directly to the project, and we want to make sure that any 
policy frameworks or structures endorsed by the meeting are incorporated into the 
discussion documents presented at the Review Workshop.  We recommend that a member 
of the consultant team attend the PNG meeting (at our cost) and work alongside the DMO 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 26  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
principal officer and other Samoan Government representatives.  The meeting also presents 
an opportunity to spend time with SOPAC and MCDEM representatives to discuss 
emerging trends in Pacific disaster management and how these relate directly to any 
changes being recommended for Samoa. MCDEM are presenting Response Guidelines for 
Small Island Development States at the meeting, which will be of relevance to the 
development of the NDMP (component DM2).  The attendance of a member of the 
consultant team is supported by MCDEM (refer their letter dated 18 April 2005 – Appendix 
F). 
Scope of Work (Sub Tasks): 
ƒ
Develop Review Workshop approach and process. 
ƒ
Conduct Review Workshop(s) 
ƒ
Report on outcomes 
Output: 
ƒ
Review Workshop Report summarizing key outcomes of the meeting, confirmed 
project methodology and feedback on discussion documents. 
2.4.2 
DM 2 – Revised NDM Plan (RFP Clause 30/ Proposal ref DM 1.2) 
The RFP calls for a revised NDMP within 3 months of commencement of the contract (7 
May). During our inception visit, a number of agencies expressed the view that the 
arrangements in the existing Plan for the response phase need to have a fresh look and be 
more focused. Within the scope of the project proposal
this involves taking the existing Plan 
largely as is
, and focusing on those elements that need changes. 
The revised Plan needs to encompass all of the recommended structural changes to disaster 
management arrangements for Samoa. The inception interviews have identified a number 
of issues and considerations that need to be carefully worked through and widely 
consulted, including at the political level (noting the linkage with the preparation of 
legislation). Other feedback received during our inception visit indicated a preference for 
more consultation on the Plan than has occurred during the development of previous 
drafts of the NDMP. A staged approach is therefore recommended, including the 
preparation of a discussion document for consideration at the Review Workshop (DM 1) 
and at subsequent agency workshops. 
We also recommend that the structures be tested during the simulation planned for August 
(DM 9) prior to producing a draft revised NDM Plan by the end of October 2005. A more 
formal consultation process is suggested over the period November to April 2006, with a 
final NDM Plan produced by June 2006. 
We believe that the process as outlined above will result in a Plan with a greater level of 
buy-in from stakeholders and a greater level of awareness about the national disaster 
management arrangements. 
None of the agencies interviewed
1
 during the Inception visit could provide any tangible 
information in summary form relating to the hazards and consequences that Samoa faces.  
                                                        
1
 A list of persons met with is contained in Appendix G. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 27  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
We were able to locate a couple of reports relating to volcanic hazards (Savai’i) and 
flooding (Apia), however, there seem to be significant gaps for some hazards (such as 
earthquake and non-natural hazards). A basic indication of likelihood and consequence for 
the principal hazards (natural and man-made) represents base information for risk 
management and planning purposes. While a summary of these hazards suitable for 
emergency management planning (specifically the NDMP) is provided for in the proposal, 
the collection and compilation of the base information needed to put such a summary 
together is not. 
We recommend that the DMO or other staff from MNREM or MWTI (e.g. PUMA or Met 
Division staff) compile what hazard information there is available (both natural and man-
made) from existing material and historical records. This would include working with 
agencies such as the Fire Service (hazardous substances), Ministry of Agriculture, Forests 
and Fisheries (plant pests and animal diseases), Ministry of Health (epidemics) etc. To be 
useful for the development of the NDMP it will be needed by the end of August 2005. We 
can assist this process by providing a template indicating what information is required and 
how it should be presented. We suggest that a small workshop be held with the DMO, staff 
from the Meteorological Division and also some of the other agencies listed above to 
determine how the information can be compiled. This workshop could be held as part of 
the Review Workshop series of meetings during the week of 20
th
 June 2005. 
Scope of Work (Sub Tasks): 
ƒ
Review existing NDMP 
ƒ
Produce discussion document including options regarding national disaster 
management structures for June Review Workshop 
ƒ
Assist with a workshop to explore how hazard information can be collated for a hazard 
summary 
ƒ
Meetings and targeted consultation with key Government departments and 
stakeholders 
ƒ
Draft revised NDMP 
ƒ
Targeted consultation with stakeholders and public consultation 
ƒ
Revised NDMP 
Output: 
Revised NDMP with additional content as necessary and with national structures 
understood by government departments and stakeholders. 
Hazards summary suitable for emergency management planning (if hazard information is 
able to be compiled by end August 2005). 
2.4.3 
DM 3 – Legislation Review (RFP Clause 37/ Proposal ref DM 3.1) 
A discussion document summarising key features and best practice principles of generic 
EM legislation will be presented at the Review Workshop.  Development of the legislation 
will be undertaken by a specialist legal draftsperson and it is recommended that this be 
undertaken with input from MCDEM. Consultation on the proposed coverage of the 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 28  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
legislation will need to integrate with the revision of the NDMP, so that any issues that 
come up during stakeholder plan development and simulations can be addressed. 
Scope of Work (Sub Tasks): 
ƒ
Produce discussion document summarizing key features and best practice principles of 
generic emergency management legislation. 
ƒ
Develop proposed outline and coverage of legislation 
ƒ
Meetings and targeted consultation with key Government departments and 
stakeholders 
ƒ
Draft legislation and supporting cabinet paper 
Output: 
ƒ
Draft emergency management legislation. 
2.4.4 
DM 4 – Specification for DMO Office/ Equipment (RFP Clause 31/ Proposal 
ref DM 1.3) 
The RFP requires outline specifications for dedicated offices for the DMO within 3 months 
of commencement (7 May). 
However, the DMO Office arrangements need to take into account the recommended 
structural changes to disaster management arrangements for Samoa (in particular the 
relationship between the DMO and Government). This is likely to involve several options 
with various strengths and weaknesses. Analysis and consultation preferably needs to be 
undertaken in conjunction with work element DM2, and the preferred option is likely to 
become more apparent as time progresses. 
A discussion document on the various options will be presented at the Review Workshop.  
Some recommendations for immediate equipment needs will be made, which will be 
independent of the DMO physical location. We recommend that an outline fit-out not be 
finalised until September 2005. 
Material to the discussion of the location, functions and fit-out of the DMO, is the 
relationship of the DMO with the National Coordination Centre (NCC). Discussions with 
various agencies during the Inception visit highlighted the key function that the existing 
National Coordination Centre plays in the response to a disaster event. It is intended to be 
the hub of the response operation, and hosts the national emergency communications 
facilities. In discussions with agencies in which the NCC was raised, most if not all, had a 
preference that the NCC should operate as it was originally intended. Moreover, the option 
of basing the DMO in the NCC was raised in several discussions, as well as being a specific 
recommendation of the MCDEM report. 
Given that several agencies have an operational interest in this facility (the Police and 
MSA), a systematic review of how it is currently intended to operate (including 
communications arrangements) and the effectiveness of those functions would seem 
worthwhile for both DM4 and DM5. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 29  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
However as the RFP only made a passing reference to this facility within the framework we 
were requested to work within (paragraphs 29 through 40), such a review was not allowed 
for in the proposal.  
MWTI’s letter of 13 April 2005 (See Appendix D) suggests that the MCDEM Review report 
(July 2004) has already provided discussions on and a summary of the NCC, implying that 
it would be a relatively straightforward task to include a review of the NCC within the 
current scope of work.  MCDEM’s letter of 18 April 2005 (Appendix F), states that a review 
of the NCC is “pivotal to the effectiveness of existing or new disaster management arrangements 
and any review of the disaster management structure”
 implying that this piece of work has yet 
to be undertaken.  
While we can confine our review to the DMO, we would strongly recommend that the 
scope of work be extended to include consideration of the NCC and include: 
ƒ
A review of how the NCC is currently intended to operate (including 
communications), 
ƒ
A recommended fit-out for the NCC which enables it to be used for its intended 
purpose, 
ƒ
Standard operating procedures for the activation of the NCC, 
ƒ
Process for recruiting and training NCC staff. 
The additional work recommended assumes that the Government is supportive of using 
the current facility for its intended purpose, which we understand to be the case. 
Scope of Work (Sub Tasks): 
ƒ
Produce discussion document outlining physical options for DMO office 
arrangements. 
ƒ
Consultation on DMO Office arrangements with key government departments and 
stakeholders.  
Output: 
ƒ
Fit-out specifications for the DMO. 
ƒ
Fit-out specifications for the NCC (if expanded scope is approved) 
ƒ
Standard operating procedures for the activation of the NCC (if expanded scope is 
approved). 
ƒ
Process for recruiting and training NCC staff (if expanded scope is approved). 
2.4.5 
DM 5 – Communications Equipment Supply Specification (RFP Clause 32/ 
Proposal ref DM 1.4) 
The RFP requires specification of radio communications equipment within 3 months of 
commencement (7 May).  However, the RFP was not specific around the operational scope 
of the required emergency communications equipment.  The shortcomings of the current 
National Co-ordination Centre communications arrangements identified during the 
inception interviews however indicate that the national requirements need a 
comprehensive review.  This review is recommended to be undertaken as part of the 
extension to the scope of work as discussed above.  The specification is also highly 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 30  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
dependent upon physical location and decisions taken in relation to the NCC and the 
DMO, which need clarification before Consultel as technical sub-consultant become 
involved.  An early preparation of the specification and associated procurement would 
have a high associated risk of failure to meet the real needs.  For this reason we recommend 
that a final specification be prepared by the end of October, with a review of this with 
affected agencies during November 2005. 
Scope of Work (Sub Tasks): 
ƒ
Produce briefing document on communication requirements.  
ƒ
Needs analysis with respect to Pacific best practice. 
ƒ
Outline specification of radio communications equipment with options and 
recommendations.  
ƒ
Findings from simulations undertaken in August and November used to verify or 
further refine specification. 
ƒ
Review specification with affected agencies.  
Output: 
ƒ
Communications specification (operational scope to be agreed). 
2.4.6 
DM 6 – DMO Institutional & Staff Development (RFP Clause 33/ Proposal 
ref DM 2.1) 
The approach to this work element remains as per the original methodology.  The focus 
will be on a long term sustainable approach to professional development as well as 
providing mentoring by the project team for the duration of the contract. A better 
understanding of the functions of the DMO will be gained through development of the 
NDMP (DM2) and position descriptions will be developed. A training needs analysis will 
be undertaken in conjunction with SOPAC, and a professional development strategy will 
be developed which will look at opportunities for partnering arrangements with other 
emergency management organisations in NZ, Australia and elsewhere. 
The position descriptions, DMO fit-out (DM4), and professional development strategy will 
be packaged together as part of a DMO Business Plan. The development of a strategic 
component to the Business Plan has not been allowed for in the proposal. The strategic 
component involves an analysis of gaps in existing disaster management programmes and 
activities, prioritization of the gaps to be filled, and scheduling of work over a nominal (5 
year) timeframe. This would identify and justify specific resourcing and budget items 
beyond the deliverables for item DM4. We will work with the DMO, as part of the peer 
mentoring programme to enable and support the DMO to develop this strategic 
component of the Business Plan. This may only involve some adjustments to the work 
programme the DMO has already developed.  
Scope of Work (Sub Tasks): 
ƒ
Analysis of DMO functions and roles 
ƒ
Development of position descriptions 
ƒ
Consultation on DMO position descriptions with key government departments  
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 31  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
ƒ
Scope professional development requirements and identify opportunities for ongoing 
professional development. 
ƒ
Draft professional development and mentoring plan. 
ƒ
Work with DMO during mentoring sessions to develop strategic component to 
Business Plan. 
ƒ
Identify any professional development implementation issues during term of contract. 
ƒ
Review and update professional development plan at end of contract.  
Output: 
ƒ
DMO Business Plan, containing: 
ƒ
Position descriptions 
ƒ
Professional development plan 
ƒ
DMO fit-out (from DM4) 
ƒ
Strategic 5 year work programme (developed by DMO) 
2.4.7 
DM 7 – Community Education and Development (RFP Clauses 34 & 38/ 
Proposal ref DM 4.2) 
The approach to this work element remains as per the original methodology. Community 
education and awareness raising will be undertaken as part of the village level consultation 
for the CIM Plans/SMP completion under Task NRM 2.3.  A longer term education 
strategy will also be developed with the DMO.  It is intended that the delivery of education 
material during the CIM Plan consultation be undertaken by the CIM Plan teams.  It is 
strongly recommended that the DMO staff participate as team members, subject to their 
availability. This would allow the DMO staff to build up a picture of the vulnerabilities of 
the villages and districts, and contribute to their professional development. 
During our inception visit, the concept of village or district response plans was suggested 
several times. We think this concept has merit. During the preparation of materials for the 
CIM Plan workshops, we will develop an outline of what should be covered in a village 
response plan. We will work with the DMO and CIM Pan teams to investigate the 
possibility of incorporating a response plan component to the CIM Plans, or if this is not 
feasible, recommend a subsequent process for their development.  
Scope of Work (Sub Tasks): 
ƒ
Identify existing education resources and delivery methods. 
ƒ
Develop briefing materials for CIM Plan teams to deliver. 
ƒ
Consider elements of a village response plan for possible incorporation into CIM plans.  
ƒ
Participation in selected CIM plan consultation 
ƒ
Draft community education strategy 
ƒ
Consultation on education strategy with stakeholders 
Output: 
ƒ
CIM Plan briefing materials 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 32  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
ƒ
Process for the development of village response plans 
ƒ
Community Education Strategy 
2.4.8 
DM 8 – Agency Education & Response Planning (RFP Clauses 35, 36 & 38/ 
Proposal ref 2.3, 4.1) 
The approach to this work element remains as per the original methodology.  We will 
prepare a guidance document on the key elements of agency response plans, covering 
aspects such as: 
ƒ
Linkages with national DM arrangements, 
ƒ
Interagency linkages, 
ƒ
Own continuity/ operational arrangements, 
ƒ
Minimum readiness/ preparedness expectations. 
We will meet with individual agencies and also deliver combined agency workshops. The 
workshops will focus on the first two of the bullet points above, as these were the areas that 
the inception visit interviews revealed were the main vulnerabilities or gaps in agency 
planning. The workshops and meetings will also provide an opportunity to consult on the 
revised NDMP (DM2). 
Inception visit interviews also indicated that there was quite a lot of variability in terms of 
agency response plans – some seem well developed, others don’t exist, or are out of date. 
The emphasis will be on assisting agencies to review and revise their own plans. A major 
risk to the RFP requirement to have these plans ‘completed’ within 18 months, is the extent 
to which individual agencies have the commitment to ensure their plans are completed 
within the required time frame. This risk will in part be managed by involving agencies in 
combined workshops so they can be motivated by how other agency plans are developing. 
Scope of Work (Sub Tasks): 
ƒ
Prepare guidelines on the key elements of agency response plans. 
ƒ
Prepare and deliver agency workshops grouped in sectors (emergency services, 
government departments, utilities, private sector etc) 
ƒ
Hold individual meetings with agencies as both a precursor and follow-up to the 
workshops. 
ƒ
Involvement of key agencies in the simulations as part of awareness and education 
about national emergency management arrangements.  
ƒ
Follow-up on plan development and assist where needed. 
ƒ
Workshop at conclusion of process for all agencies to review progress and celebrate 
achievements. 
Output: 
ƒ
Report summarizing progress in the development of agency response plans, and 
recommending future follow-up. 
ƒ
Updated agency response plans, and greater awareness by agencies of their role in 
national emergency management arrangements. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 33  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
2.4.9 
DM 9 – Disaster Simulations (RFP Clause 39/ Proposal ref DM 5.1) 
Disaster simulations are considered an important component to several of the work 
elements, including revision of the NDMP (DM 2), development of the legislation (DM 3), 
DMO location and positioning (DM 4), Communications Specification (DM 5), and Agency 
Education (DM 8). For this reason we propose that the 2 programmed simulations be run 
early in the project, with both completed by November 2005. It is likely that additional 
simulations will be beneficial, however, we will wait until the outcomes of both 
simulations before recommending additional simulations be undertaken.  
The need for more simulations was a common theme from our inception interviews. 
Varying sized simulations (drills, tabletops exercises, regional exercises etc) were all 
identified as being critical to the development of Samoa’s disaster management capability. 
We propose that the 2 simulations planned for August and November focus on different 
hazards. The August simulation will be based around an earthquake scenario with the 
November simulation based on a cyclone in preparation for the cyclone season. 
Cyclones dominate response planning in Samoa (understandably), however, other hazards 
will occur and disaster management arrangements need to be tested in a variety of 
scenarios to ensure the will work in a variety of different circumstances.  To assist the DMO 
to develop the skills to run and debrief simulations, we propose to take the lead in the first 
simulation, with the DMO in support. For the second simulation we recommend the DMO 
take the lead and we will advise and assist where necessary. 
Pre-planning for the simulations has already begun and an outline of the objectives of each 
simulation is given below. The simulations will be discussed in more detail as part of the 
series of Review Workshop meetings during the week of 20
th
 June 2005. Both simulations 
involve the use of the National Coordination Centre (NCC), and issues around its current 
and future use will need to be resolved before the simulations can proceed as planned.  
Disaster Simulation 1:  August 2005 
Objectives 
ƒ
To exercise the activation, set up and establishment of the National Co-ordination 
Centre facilities 
ƒ
To exercise the national disaster management structures 
ƒ
To test the effectiveness of existing communications linkages and communications 
equipment 
ƒ
To provide opportunities for DMO personnel to develop skills in simulation planning 
and delivery. 
Scenario 
The scenario will be a moderate earthquake causing widespread damage and injuries.  The 
scenario impacts will necessitate the activation of the National Co-ordination Centre. 
Participants will respond to the National Co-ordination Centre, set up their working areas, 
and establish the necessary management and reporting structures.  The management 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 34  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
structure will be expected to activate, manage scenario activities, and ensure the NCC is 
operational for a full day. 
Recommended Participants 
DMO, MNREM, PUMA, Meteorological Division, NDC representation, Police, other 
selected lead response agencies. 
 
Disaster Simulation 2:  November 2005 
Objectives 
ƒ
To exercise the National Co-ordination Centre facilities 
ƒ
To test the links between NCC management structures and operational response 
agencies 
ƒ
To provide an opportunity for agencies with a role in disaster response to implement 
their response plans. 
ƒ
To exercise the Cyclone Operational Response Procedures in the early stages of the 
cyclone season 
ƒ
To provide the NDMO personnel with an opportunity to prepare for and deliver a 
simulation exercise. 
Scenario 
The scenario will be a cyclone affecting islands of Samoa causing widespread damage and 
injuries.  The NCC will have been established during the warning period prior to the 
exercise beginning, and the exercise will focus on response activities that begin shortly 
before the impact of the cyclone.  The exercise will be a mixture of operational and table-
top workshop activities. 
Recommended Participants 
DMO, MNREM, PUMA, NDC representatives, utilities, other key agencies with a disaster response 
role (e.g. those listed as part of National Disaster Management Working Group), Meteorological 
Division. 
Simulation Debriefs 
In order to ensure lessons are learned from each exercise, a series of debriefs will be held.  
On the day of the exercise participating agencies will be asked to provide their initial 
feedback on what processes worked well, and which will require more training or 
preparation.  On the day following the exercise, each agency will be given time to discuss 
the lessons they have learned as part of a full debrief. A debrief report will be prepared. 
Scope of Work (Sub Tasks): 
ƒ
Prepare outline and timing for two interagency simulations. 
ƒ
Conduct simulation and debrief in August 2005. 
ƒ
Support DMO to conduct and deliver simulation in November 2005.  
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 35  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Output: 
ƒ
Reports on both simulations, which will include debrief notes, lessons learned, and 
recommendations to any changes to procedures, linkages with other agencies, or 
national structures as a result. 
ƒ
Report recommending format and programme for future disaster simulations. 
2.4.10 
DM 10 – Disaster Insurance (RFP Clause 40/ Proposal ref DM 6.1) 
The approach to this work element remains as per the original methodology.  
Scope of Work (Sub Tasks): 
ƒ
Review findings from the joint SOPAC/ World Bank/ AusAid “Catastrophe Insurance 
Pilot Project” currently set up in Port Vila. 
ƒ
Prepare recommendations and report on preliminary review. 
Output: 
ƒ
Report on review with recommendations as to the implementation of a national 
disaster response fund or disaster management insurance. 
ƒ
Presentation of findings to key government departments and stakeholders. 
2.4.11 Decisions 
Required 
During the inception visit and consequent development of the methodology, a number of 
additional work items emerged, which we considered material to the overall success of the 
project. These were discussed in the draft Inception Report and at the Inception Workshop 
on 14
th
 April 2005.  Feedback from the workshop and also in letters from MWTI and 
MNREM (appended to this report) have clarified some matters and the methodology has 
subsequently been revised as a result.  
There remain some matters which require a decision or further clarification and these are 
discussed under the relevant sections of work above.  We look forward to your 
consideration of these items.  There is also the opportunity to discuss these further at the 
Review Workshop during the week of 20
th
 June 2005. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 36  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Work Programme and Deliverable Outputs 
3.1 Introduction 
Our work programme with the exception of the Emergency Management workstream, 
remains substantially as proposed in our Technical Proposal. We provide below a 
summary programme for the whole project and detailed programmes for the Natural Risk 
Management and Emergency Management workstreams. We also provide a generic 
detailed work programme for a typical district for the CIM Plan works under the Natural 
Risk Management workstream.
background image
S
I
A
M
-
 Sust
a
i
nabl
e Manageme
nt
 C4: En
v
i
ronment
 Ri
s
k
s
 
& Resou
rce Manageme
nt
 
I
n
cep
ti
on Rep
ort
 
6060
030/
100  
Beca
 
Page 37  
L2:
49382-
Fina
l In
c
e
p
t
ion Re
por
t
 
- M
a
y 20
05
.DOC
 
 
Rev A   20 M
a
y 20
05 
 
 
3.2 
Overall Work Programme 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
background image
S
I
A
M
-
 Sust
a
i
nabl
e Manageme
nt
 C4: En
v
i
ronment
 Ri
s
k
s
 
& Resou
rce Manageme
nt
 
I
n
cep
ti
on Rep
ort
 
6060
030/
100  
Beca
 
Page 38  
L2:
49382-
Fina
l In
c
e
p
t
ion Re
por
t
 
- M
a
y 20
05
.DOC
 
 
Rev A   20 M
a
y 20
05 
 
 
3.3 
Natural Risk Management Work Programme  
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 39  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
3.4 
Emergency Management Work Programme  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 40  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 41  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
3.5 
CIM Plan Typical District Work Programme 
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 42  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
3.6 Deliverable 
Outputs 
Deliverable outputs will be as provided for in the contract and detailed in our Technical 
Proposal. 
3.7 
Anticipated Counterpart Involvement 
Counterpart availability for the CIM Plan process has major implications for the project. On 
the one hand visible Government staff representation as part of the CIM Plan consultation 
teams in the villages is essential to reinforce the “partnership” ethos of the process. On the 
other we are only too aware of the significant strain this work can place upon scarce staff 
resources in both MWTI and MNREM. We have structured our work programme on the 
basis that a minimum of one Ministry (Could either be MWTI or MNREM or both) staff 
person is available for each CIM Plan consultation team. Our discussions with MWTI and 
MNREM staff during the Inception review period have indicated that, subject to sufficient 
prior notice and a measure of flexibility in who actually participates on the day, then this 
assumption ought to be able to be fulfilled.  
We will provide substantial advance warning of the requirement for counterpart staff 
support via the detailed work programme for the CIM Plan preparation which will be 
discussed with the MNREM PCM and other key staff in MWTI PUMA Division on a 
regular basis. 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 43  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Key Performance and Progress Indicators 
At the Inception Report workshop key stakeholders agreed that the key performance and 
progress indicators developed in the draft Inception Report were appropriate for the 
project.. These focussed upon key outcomes sought from the project, which have been 
summarised in Annex 2 of the TOR. 
The key indicators proposed cover the following key elements from each workstream: 
Environmental Management 
ƒ
Operative EIA regulations under the PUMA Act 2004.  
Measure
:  Completed  EIA regulations agreed by Cabinet. 
ƒ
Widespread application of the EIA regulations 
Measure
:  Completed  EIA regulations applied to all projects by MWTI PUM 
Division 
ƒ
Improved environmental management techniques and practices applied to 
Government and private sector construction projects. 
Measure
:  Completed COEP’s consistently applied for Government and major 
private sector works   
ƒ
Improved environmental monitoring practices and procedures with MNREM. 
Measure
:  Completion of suggested environmental monitoring practices and 
procedures.   
Natural Risk Management 
ƒ
An updated and expanded CIM Strategy to include climate change adaptation and 
other hazards. 
Measure
:  Revised and expanded CIM Strategy agreed by Cabinet.   
ƒ
Completed CIM plans for the remaining 28 districts. 
Measure
:  Completed CIM Plans incorporating the revised and expanded CIM 
Strategy   
ƒ
Use of the CIM Plans as national planning documents under the PUMA Act. 
Measure
:  CIM Plans adopted for all Districts and used to administer inter alia the 
Small Grants Scheme and other Government infrastructure investment  decisions.   
ƒ
Demonstrable wider level of awareness and acceptance of CIM Plans in the 
community. 
Measure
:  Completed awareness survey with increased knowledge in all sectors 
of the community of CIM Plans.  
Resource Management 
ƒ
Increased utilisation of GIS as an analysis tool in support of natural resources 
management policies. 
Measure
:  Completed  GIS professional development and applications 
programme in MNREM. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 44  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
ƒ
Support to other natural resources management initiatives arising from CIM Plans and 
other policy directives in MNREM’s corporate plan. 
Measure
:  Reference in MNREM’s corporate plan to the CIM Strategy and CIM 
Plans as guiding policy and implementation frameworks for Government and 
private projects.  
Emergency Management 
ƒ
An updated NEMP. 
Measure
:  Completed  NEMP  
ƒ
Training and professional development for NDMO staff. 
Measure
:  Completed training and professional development plan and 
implementation commenced during the project.  
ƒ
Awareness raising of community and organisations with respect to NEMP and EM 
generally. 
Measure
:  Completed public awareness programme  
ƒ
National disaster simulations. 
Measure
:  Two disaster simulations completed by end 2005.   
ƒ
Specification of accommodation and additional equipment. 
Measure
:  Accommodation and equipment schedule completed   
ƒ
Preparation of supporting DM legislation. 
Measure
:  Legislation drafted and presented to Cabinet.   
ƒ
Review of options for DM insurance. 
Measure
:  Completed review of Port Vila Pilot Project   
 
 
 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 45  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
Risk Management Plan 
5.1 Introduction 
The TOR for the project requires as part of the Inception Review that a  “a risk management 
plan for the project (based on AS/NZS 4360 [Risk Management]), against which the project 
progress is to be assessed and risks are to be managed.
” 
AS/NZS 4360 Risk Management 
describes risk management as “ a generic framework for 
establishing the context, identifying, analysing, evaluating, treating, monitoring and 
communicating risk.” It stresses the achievement of an appropriate balance between 
realising opportunities for gains whilst minimising losses. Risk management is an iterative 
process consisting of steps which when undertaken in sequence enable continuous 
improvement in decision-making and resultant performance. The Standard emphasises 
both the positive as well as negative outcomes of exposure to uncertainty or potential 
deviations from what was expected or planned.  
The Standard is not a prescriptive tool but rather a framework for the systematic 
identification, evaluation, treatment and monitoring of risks. In the context of this project 
we have adopted a relatively high level analysis focussing on risks which may inhibit the 
attainment of overall project objectives rather than small scale risks to the programme for 
individual tasks. These risks can and will be managed via the project work programme and 
the progress reporting schedules. 
5.2 
Project Risk Plan 
For each of the identified risks we have followed the recommended process in the 
Standard. This requires the Identification of the risk; the Analysis of the risk; the Evaluation of 
the risk and the Treatment of the risk. This process is conducted within a framework of on-
going and continuous communication/consultation (to be achieved via the risk analysis 
section of the quarterly report) and monitoring/review (to be achieved by the project 
manager’s monitoring of risks and the project programme which is also the subject of both 
monthly and quarterly reports.) 
Identification 
of the risk involves description of the item or activity that creates the risk.  
Analysis
 of the risk considers its potential to adversely impact upon attainment of the 
project objectives. This may also be a positive impact. This is about developing an 
understanding of the risk and assists with the decision as to whether the risk needs to be 
treated and what might be the most cost-effective treatment strategy. 
Evaluation
 of the risk is all about assessing which risks need to be treated and treatment 
priorities. 
Treatment 
of the risk involves the application of treatment methods which may include 
avoidance, changing the likelihood of the risk, changing the consequences, sharing the risk 
or retaining and accepting the risk. 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 46  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
In the following Table  we set out our suggested structure for the assessment of the major 
project risks by workstream together with appropriate risk management strategies for each 
risk. 
 
Table 5.1 - Risk Management Schedule 
 
The Risk
Risk Level 
Responsibility 
Risk Management
Environmental 
Management 
Inability to secure 
Ministerial & Cabinet 
support for proposed 
EIA regulations 
 
 
Low 
 
 
MNREM & law draftsman 
 
 
Briefing of Minister & 
Cabinet at regular intervals 
prior to draft being 
presented.  
COEP’s not adopted 
by industry 
 
Moderate 
 
MNREM & MWTI 
 
Both Ministries to publicly 
notify of requirements to 
adopt and of their intention 
to enforce. 
 
 
 
 
Nat Risk Management 
Inability to secure 
Ministerial & Cabinet 
support for proposed 
CIM Strategy revisions 
 
Moderate 
 
MNREM & project team 
 
Briefing of Minister & 
Cabinet at regular intervals 
prior to draft being 
presented. 
Inability to complete 
CIM Plans for 
remaining 28 districts 
within project 
timeframe 
 
Moderate 
to High 
 
Project Team, MNREM & 
MWTI 
 
Regular monitoring of work 
programme and resource 
availability 
 
 
 
 
Nat Resource 
Management: 
Natural Events 
Fire and/or water 
damage to materials 
and data crucial for 
achieving project 
outcomes, e.g. 
orthophotography, GIS 
data etc. 
 
Moderate 
to High 
 
MNREM 
 
MNREM & project team 
Maintain backups on and 
offsite.  
 
Share project directories and 
layers between MNREM and 
project team 
Nat Resource 
Management: 
Technology and 
Technical Issues 
Applications 
recommended poorly 
focused and 
inappropriate 
 
 
  
Low 
 
 
 
 
Consultant project team 
 
 
 
Ongoing dialogue between 
consultants and counterparts  
 
Applications are appropriate 
to MNREM and other 
relevant agency needs 
 
Technical interventions are 
sound and based on: 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 47  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
The Risk
Risk Level 
Responsibility 
Risk Management
In-depth needs analysis 
Stakeholder input 
 
Senior consultants, 
counterparts and agency 
representatives develop 
project plans with ongoing 
progress reports to monitor 
appropriateness of 
applications 
Poor uptake of GIS 
technology 
 
Low 
MNREM & Consultant 
project team 
Senior consultants and 
counterparts agree on 
training content and format 
based on joint needs analysis 
 
Targeted 
training/familiarization 
programmes in place with 
stakeholder commitment 
Data unavailable to 
project 
 
Low CEO, 
MNREM 
Establish protocols with data 
suppliers re ownership, use 
and intellectual property 
Emergency 
Management  
Lack of commitment 
and buy-in by agencies 
to revising their 
response plans or to 
the draft NDMP 
 
 
Low 
 
 
Consultant Project Team 
and CEO/MNREM 
 
 
Managed by: 
ƒ
alerting agencies well in 
advance to the 
consultation process   
ƒ
working with agencies 
on a one-on-one basis 
ƒ
encouraging agencies to 
show-case their plans 
with others (peer 
mentoring)  
ƒ
alerting MNREM early 
in the process if 
particular agencies are 
reluctant to participate 
Lack of support for 
revised national 
disaster management 
arrangements by 
MCDEM and/or 
SOPAC 
Low 
Consultant Project Team 
and CEO/MNREM 
Managed by: 
ƒ
involvement of MDCEM 
and SOPAC at the 
Inception Workshop 
stage, the Review 
Workshop stage and at 
other relevant parts of 
the project (e.g. 
invitations to 
simulations; requests to 
review discussion 
documents and draft 
reports) 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 48  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
6 Decisions/Actions 
Required 
6.1 Organisational 
Changes 
During the Inception visit the project team was advised of the recent decision by Cabinet to 
relocate the PUMA division of MNREM to MWTI. The PUMA division has a key role to 
play in the project being intimately involved in the Natural Risk Management workstream 
– this produces the revised CIM Strategy and completes the CIM Plans for the remaining 
districts of the country.  This workstream consumes approximately 75% of the manpower 
resources of the entire contract. 
There are several issues arising from this relocation both of a practical and more 
conceptual/philosophical nature. 
ƒ
The contribution of counterpart support staff from the PUMA Division will require the 
agreement of the CEO of MWTI who is not a signatory to the contract for this 
component. 
ƒ
Similarly MNREM counterpart staff support for this workstream will be to a function 
for which they no longer have an organisational responsibility. 
ƒ
The integration of an increased awareness of the emergency management function into 
the CIM plan process will be made more difficult as will its continuous 
implementation via the planning process. 
ƒ
As the primary environmental regulating authority under the PUMA legislation, the 
PUMA division within MWTI may find itself in a conflict of interest situation with 
other more works related divisions of MWTI. 
ƒ
The CIM Plans will need to be signed by the Minister responsible for MWTI rather 
than that for MNREM. 
We have initiated an exchange of correspondence to address some of these issues and look 
forward to further feedback as a result of this report. We are still awaiting confirmation of 
our understandings from MNREM & MWTI – a copy of our letter dated 22 February 2005 
to MNREM is contained in Appendix H.  
6.2 
Natural Risk Management 
It is essential that the project have access to digital (MapInfo or ArcView) maps of the 
country. 
The Preparation of the remaining CIM/SMP plans will be a very “hands-on” learning 
experience for all those involved, including both Government Staff and local village 
participants. Much of the data collection work will take place in the field, and the speed 
and accuracy of map reproduction and modification will be critical to the successful 
completion of the project.  
While it is crucial that the existing government mapping system retains its integrity and 
independence, it is essential that this project has a copy of all the base map layers of 
relevance to the preparation of the CIM plans. The following layers are considered 
background image
SIAM2 - Sustainable Management C4: Environment Risks & Resource Management Inception Report 
6060030/100  
Beca 
Page 49  
L2:49382-Final Inception Report - May 2005.DOC 
 
Rev A   20 May 2005 
 
 
essential: coastlines, reefs, topography (contour lines), roads, paths, buildings, bridges, 
coastal hazards, land resource inventory information and (where mapped), utilities. 
These map layers will be updated as necessary in the field and new layers will be created 
as they are developed (e.g. aggregate resources, cyclone “safe areas”, possible future 
locations for public facilities, etc.). All layers, whether modified or not will be kept separate 
from the Government database until/unless the new/revised information is desired by the 
government offices. 
During the Draft Inception Report Workshop on 14 April 2005, MNREM Mapping Division 
indicated that they would give further consideration to the Consultant Team’s request for 
direct access to the necessary data layers to enable the production of the consultation maps 
for the CIM Plan preparation direct by the consultant. We still await conformation of this 
access. 
 
background image
 
 
ƒ Appendix A 
Description of Services 
Required
background image
 
 
Description Of Services Required
Environmental Management 
 
1.
EIA Regulations:  Based on discussion and feedback from MNREM, finalise the 
draft EIA Regulation to be camera ready for submission by the Minister of Natural 
Resources and Environment to Cabinet for approval.  The EIA requirements were originally 
drafted to be regulations under the Lands, Surveys and Environments Act, 1989.  The draft 
regulations will need to be upgraded to be compatible with the empowering legislation for 
MNREM, the draft PUMA Act, and administration improvements identified through the 
application of the draft regulations during the implementation under IAM-1.   
2.
Environmental Monitoring:  Advise MNREM on environmental monitoring good 
practice, and in particular, how to make best use of environmental monitoring data collected 
to-date for national monitoring purposes, trend analysis, development and use of 
environmental monitoring indicators, and the development of policy and management 
initiatives based on, or drawing from, this data.  This advice is likely to be delivered 
through workshops involving senior members of MNREM, and through mentoring of key 
staff within MNREM who can champion this initiative. 
3.
Upgrade/Extend COEP:  Review and expand the Codes of Environmental Practice 
(COEP) to cover for other routine physical works undertaken by infrastructure providers 
such as EPC, Samoa Telecommunication and Water Authority. 
4.
Industry Training and Development:  Develop and provide training to 
engineering consultants and contractors on: (i) procedures and obligations under the EIA 
Regulation; (ii) details, application, and obligations under the COEP; (iii) application of, 
and obligations to meet, environmental management procedures in contract management 
and implementation of physical works; and (iv) the principles of economic evaluation 
applied to infrastructure development project evaluation (including coastal hazard 
mitigation systems).  It is expected that the training will be delivered through seminars and 
workshops with some mentoring (i.e. hands-on) support through immersion of the 
Consultant’s staff with the consultant’s/contractor’s staff during key project 
preparation/implementation periods. 
5. 
Provide similar, possibly concurrent, training to the MWTI, to build on the training 
provided under IAM-1. 
6. 
The above training and industry development shall be arranged with the assistance 
of MWTI and MNREM and will also involve staff from these agencies, in order to raise 
awareness and understanding of good environmental management practices, and to improve 
compliance with requirements. 
7.
Contractor Qualification Scheme:  Design and assist MWTI implement a 
mandatory qualification scheme in environmental management and the application of the 
COEP on construction works for contractors as a pre-requisite for eligibility to tender for 
government projects.  
background image
 
 
Natural Risk Management 
 
8.
Expand Scope of CIM Strategy:  Expand the existing CIM Strategy to incorporate 
issues relating to climate change adaptation, and to include strategies for other, relevant, 
inland hazards such as flooding and landslides.  In preparing the revised CIM Strategy, the 
consultant shall develop and agree with the MNREM the extent and approach to any 
additional consultation required to finalise the strategy.  Consultation shall be lead by 
PUMA, but shall closely involve the consultant as an expert advisor in a supporting role. 
9. 
Taking account of feedback from the consultation, the Consultant shall prepare a 
final draft of the revised CIM Strategy acceptable to, and suitable for, the Minister of 
Natural Resources and Environment to take to Cabinet for approval and endorsement as an 
official, updated strategy framework for the Government of Samoa. 
10. 
The Consultant shall prepare a background report on the update to the CIM 
Strategy.  This report shall be an addendum to the background report prepared as part of the 
original CIM Strategy development, and shall outline the approach taken in developing the 
additions to the Strategy, the underlying thinking and reasoning, consultation activities 
undertaken and conclusions drawn from them, key performance indicators for the additional 
elements of the strategy, critical assumptions, and any other observations on the approach. 
11.
Implement CIM Plans for Remaining 28 Districts:  Implement CIM Plans for 28 
Districts, namely:  
Vaimauga West,  Faleata East, Faleata West, Sagaga le Falefa,  Sagaga le Usoga, Siumu, 
Aana Alofi II, Aana Alofi III, Lotofaga,  Lepa, Aleipata Itupa i Luga,, Aleipata Itupa i Lalo, 
Anoamaa East, Faasaleleaga II, Faasaleleaga III, Faasaleleaga IV, Leauvaa, Gagaemauga I, 
Gagaemauga II, Gagaemauga III, Gagaifomauga I,  Gagaifomauga III, Vaisigano West,  
Falealupo, Alataua West, Palauli West,Palauli le Falefa, Satupaitea 
 
These plans are to: 
x
Implement the provisions of the updated CIM Strategy (including the expanded 
scope of hazards to be considered); 
x
Be of the style, cover the scope, and be developed in a similar manner as the 
plans for the 15 Districts completed under IAM-1; 
x
Be published in both Samoan and English; 
x
Be consistent with, and be able to be implemented as, Sustainable Management 
Plans under the draft PUMA Act, or as Management Plans under the existing 
Lands, Surveys and Environment Act, 1989; 
x
Be substantially accepted, and be seen as effective, by the relevant villages. 
x
Be prepared as user-friendly The order of implementation of plans in 
documents (in Samoan and English) issued in the name of MNREM (and the 
District concerned) in a format suitable for publishing including supporting 
diagrams, maps and photographs as appropriate. 
 
12. 
The order that CIM Plans will be implemented in Districts is to be determined in 
consultation with PUMA.  Consultation with village and District representatives is to follow 
background image
 
 
the protocols developed for the project under IAM-1 (O’Meara, 1998), but also take account 
of the findings and recommendations from the SIAM-2 implementation review
2
.
13. 
During the course of development of the CIM Strategy and CIM Plans the 
Consultant will also be involved in assisting MNREM design and implement: 
x
Public awareness raising activities concerning the CIM Strategy and CIM Plans 
and related environmental issues in general, including the use of television, 
radio, newspapers, and public meetings; 
x
Preparation of advertising, educational material, brochures and booklets. 
 
14.
Sustainable Management Plans under the PUMA Act:  Assist PUMA to adapt 
the CIM Plans completed, under IAM-1 and under this contract, into Sustainable 
Management Plans (SMPs) under the PUMA Act.  Assistance shall take the form of re-
drafting of the CIM Plans into a suitable format for SMPs (§12 – 15 and §19 of the PUMA 
Bill), advising and assisting on any additional consultation required above that already 
undertaken in the preparation of the CIM Plans (§17 – 18 of the PUMA Bill), and providing 
advice on issues relating to Development Standards (§32 of the PUMA Bill) and Samoa
Planning Provisions
 (§33 of the PUMA Bill). 
15.
Effectiveness Survey:  Design, conduct and report on opinion surveys on the public 
understanding, support for, and effectiveness of the CIM Strategy and CIM Plans.  These 
surveys must cover report on cultural groups such recognised village representative and 
speakers, Women’s Committee members, untitled adults and mature youths.  Key 
government agencies (e.g. MWTI) and private sector agencies (e.g. contractors involved in 
sand extraction) are also to be assessed and reported.  The survey may involve interactive 
interviews, questionnaires and use of focus groups as appropriate and must involve a 
sample size sufficient to ensure that results are statistically significant.  It is expected that 
the survey will be conducted largely in the Samoan language. 
Resource Management 
 
16.
GIS Applications to Natural Resources Management:  The Consultant shall 
identify and agree with the Chief Executive Officer, MNREM, suitable activities in which 
GIS can be used as a primary or supporting tool to develop policy and apply, conduct 
investigations, and implement mitigation programmes relating to environmental, resource 
and risk management consistent with the aims of SIAM-2 and MNREM’s strategic 
objectives.  The Consultant shall then: 
x
Help MNREM design implementation programmes for these activities than will 
form part of MNREM’s plan of annual activities; 
x
Act as an advisor, facilitator, mentor and occasional hands-on assistance to 
MNREM staff in practices and approaches to implementing the agreed 
programmes.  The advice and direction is expected to cover not only practical 
                                                        
2
 In particular, two aspects that need strengthening in relation to the CIMP Plan consultation processes 
are: (i) ensuring that views are sought and taken into account from parts of the community who, due 
to customary practice, do not necessarily participate in the community consultation processes; and 
(ii) providing improved village level access to information and resources on the CIM Plans. 
background image
 
 
technical practices but also best practice on how to develop and use information 
from GIS systems to support policy and programme management. 
x
Provide additional on site and classroom based training on implementation of 
GIS and supporting computer systems. 
 
17. 
Monitor and report on progress of implementation of the tasks identified from 
above.  Provide ongoing support, training and mentoring to MLSNR staff to achieve the 
specific task objectives. 
18.
Sustainable Aggregate Supply Policy:  At present, management of private and 
commercial extraction of aggregate taken from the coastal zone (i.e. beaches and the 
foreshore) is limited.  In may places, aggregate extraction is unsustainable, leading to 
coastal erosion and adverse impacts on coastal hazards mitigation works, including sand 
nourishment schemes.  The Consultant shall assist MNREM investigate the nature and scale 
of the problem (drawing largely on existing studies and opinions), and then to develop, and 
provide advice on how to implement, a policy on the extraction and supply of aggregate 
from the coastal zone. 
Emergency Management 
 
19. 
The New Zealand Ministry of Civil Defence and Emergency Management 
(MCDEM) will be undertaking a field visit and review of the existing Samoa DMO 
institutional, management and operational arrangements (covering all aspects relating to 
reduction, readiness, response and recovery) under a bilateral arrangement.  The MCDEM 
will make recommendations to allow the DMO to operate under best pacific practice, 
providing a template for improvements to all relevant areas including inter alia: legislative 
mandate, funding, disaster mitigation practices, warning systems, awareness and education, 
departmental planning, DMO structure and staffing, control and committee processes, and 
the effectiveness of the national emergency operation centre.  The Consultant’s role will be 
to implement this template of improvement under the framework outlines below.  The 
Consultant will continue to liaise and consult with MCDEM throughout this phase of the 
project.  MCDEM in collaboration with MNREM will maintain a governance oversight of 
the Emergency Management component, reporting to MNREM PCM. 
20.
Review Workshop and Mandate:  Develop and conduct a Review Workshop (in 
association with the MCDEM).  The approach to the workshop, and facilitation processes to 
be employed, are to be planned and reviewed by the Implementing Agency and IDA prior 
to the workshop. 
21.
Revised National Disaster Management Plan:  Lead the development of a revised 
National Disaster Management Plan (in association with the MCDEM).  This plan, although 
based on the existing plan, is to reflect best Pacific practice, and incorporate appropriate 
responsibilities and processes for all aspects of emergency management covering inter alia
risk reduction (including community, government agency and private sector responsibilities 
and implementation of initiative identified under the CIM Plans), readiness, response and 
recovery. 
22.
Specification for DMO Office/Equipment:  Advise MNREM on requirements, 
and prepare outline specifications, for the fit out of dedicated offices for the DMO.  
Facilities are expected to incorporate office space, storage space for equipment, and a 
background image
 
 
training room.  Note that a cyclone resistant emergency command centre already exists at 
the Police Head Quarters. 
23.
Equipment Supply:  Specification of radio communications equipment, within an 
approved budget, to supplement equipment being provided by Emergency Management 
Australia (EMA) (the procurement will be done by the PMU). 
24.
Institutional and Staff Development on EDMO Practices:  The Emergency and 
Disaster Management Office has only recently been integrated into PUMA.  An 
appointment to the position of Principal Officer (Emergency and Disaster Management) has 
recently been made.  Establishment of, and appointments to, supporting staff positions 
(potentially up to two persons) is still to be done.  The Consultant shall undertake or arrange 
the following institutional and staff development delating to the Emergency and Disaster 
Management Office and staff: 
1.  Advise on the key functions of EDMO staff, covering the Principal and supporting 
staff, mapping out the skills and competencies required by each staff member to 
undertake their respective roles and responsibilities.  Prepare positions descriptions 
for these positions. 
2.   
Prepare a consolidated professional development plan including 
implementation strategies and monitoring/evaluation processes. 
3.  Scope professional development requirements, and identify appropriate 
development opportunities.  Such development opportunities may include short 
secondment arrangements with developed country Pacific Emergency and Disaster 
organisations, and programmes available through the SOPAC Community Risk 
Program. Consider the widest possible range of development including formal 
courses, work assignments and mentoring. 
4.  Monitor staff development and progress, and provide ongoing mentoring assistance 
and advice throughout the contract period. 
 
25.
Implementation Workshops/Consultation:  Assist the DMO with the 
development and implementation of agency and selected community/stakeholder (including 
relevant NGO) awareness raising programmes.  This is expected to be delivered in the form 
of interactive workshops and site visits.  The purpose of the workshops/consultation is the 
outline the propose and benefits of reforms to emergency management, to introduce key 
people involved, identify agency/community counterparts, share experiences and opinions, 
outline proposed implementation programmes, and to solicit feedback on issues that will 
help ensure the implemented practices will be effective sustainable. 
26.
Agency Response Planning:  Assist agencies with the development of 
implementation plans for business continuity plans and emergency response plans.  
Agencies are:  MoP, Telecom, EPC, MoH, MWTI, NGO’s, Private Sector 
27. 
Implementation workshops and mentoring covering all agencies.  Review of 
existing plan.  Models for new plans.  DMO would be responsible for identifying 
counterparts within each agency. 
28.
Legislation Review:  Carry out (in association with the Implementing Agency, 
Solicitor General and the Crown Law Office) and make recommendations regarding 
structure and powers of the DMO and related requirements of other government 
background image
 
 
departments, crown owned entities, and private organisations.  Prepare a draft of the 
proposed legislation. 
29.
Agency and Community Education and Development:  Assist the DMO with the 
development and implementation of agency and community awareness raising programmes.  
This is likely to involve consultation meetings with Districts and village fonos.  The 
Consultant shall provide leadership and assistance to the DMO with the development and 
implementation of community work programmes for disaster preparedness and response 
that can be taken back, developed further and applied by village communities. 
30.
Disaster Simulations:  Assist the DMO with developing an initial programme of 
emergency and disaster simulations to assess the efficacy of revised disaster and business 
continuity plans.  Observe, evaluate and provide feedback and recommendations on 
emergency and disaster simulations (in association with the MCDEM). 
31. 
Disaster Insurance:  Conduct and report on a preliminary review of the feasibility 
of, and mechanisms for, implementing a national disaster response fund or disaster 
management insurance. This evaluation should consider any analysis and findings from the 
joint SOPAC/ World Bank/ AusAID “Catastrophe Insurance Pilot Project” currently set up 
in Port Vila. 
background image
 
 
ƒ Appendix B 
GIS layers held by 
MNREM
background image
 
 
GIS layers held by MNREM 
Feature 
Coverage 
Feature Type  Attributes 
Geology National 
polygon 
classes 
Drains Apia 
line 
Drainage 
type 
Political Districts 
National 
polygon 
District area 
Population (2001) 
Political Districts 
National 
polygon 
District code 
Faipule district name 
Political district 
Population (1999) 
Conservation Areas 
National 
polygon 
Conservation areas 
National Parks 
Reserves 
Watershed areas 
Protection forest 
Ecology National 
polygon 
Terrestrial 
ecosystem 
class 
Coastal Hazard Zone 
National 
polygon 
Flood 
Erosion 
Landslip 
Sensitive area 
IKONOS Multispectral 
image 
National raster 
 
Land Cover 1999 
National 
polygon 
Land cover class 
Built up area 
National 
polygon 
Feature name  
Building National 
point? 
Feature 
name 
Contour (20m) 
National 
line 
Elevation  
Text (feature name & labels)  National 
annotation 
 
Cultivation National 
polygon 
 
Fuel Tank 
National 
point? 
 
Hydrology 
National 
line? 
Feature type, name 
Built up type 
National 
polygon 
Feature type, name 
Offshore 
National 
line? 
“Sea baseline”?, coast 
Road 
National 
line 
road, track  
Structures National 
point? 
Feature 
code 
Feature type, name 
Use 
Water tanks 
National 
point 
 
Transmission lines 
Afulilo 
line 
 
Land Capability 
National 
polygon 
Prim?, Suit?, Class? 
Soil? 
Land Use Capability? 
Forest Cover 1954 
National 
polygon 
 
background image
 
 
Forest Cover 1989 
National 
polygon 
 
Land Use 
National 
polygon 
Land use class 
Land tenure 
National 
polygon 
Land tenure class 
Orthophotography 1:50k 
National 
raster 
Natural colour 
Orthophotography 1:5k 
Coastal & selected 
inland 
raster Natural 
colour 
 
background image
 
 
ƒ Appendix C 
Mapserver equipment 
released by SOPAC to 
Met Office, Samoa 
background image
 
 
Mapserver equipment released by SOPAC to 
Met Office, Samoa 
HP Compaq DL380 Server 
72GB HOT Swap Raid Drives 
Modempak Q Series Cabinet 
Planet 16 port 10/100 ethernet switch 
24 port CAT5e patch panel 
MGE UPS Pulsar Extreme 1000c UPS 
MGE UPS ellipse 500 UPS 
CMT 3.2GHz Desktop PC with DVD-Rom and DVD+R/+RW 
Nvidia GeForce 4T Graphic Card 
HP Flat panel TFT display L1702 17” 
HP colour inkjet printer 1700d 
Mapinfo Professional 7.8 SN# MIPWEU0780010303 
MapBasic SN# MBUWEU0780010062 
Vertical Mapper v3.1 SN# VM300-02-11873 ID: 74880-38271-45286 
Erdas Imagine Essential 8.7 
HP Colour Inkjet Printer CP1700D 
background image
 
 
ƒ Appendix D 
Comments from MNREM 
& MWTI on Draft 
Inception Report 
background image
background image
background image
background image
background image
background image
background image
background image
 
 
ƒ Appendix E 
Attendance List & Notes 
from Draft Inception 
Report Workshop 14 
April 2005 
background image
 
 
SIAM2 - Sustainable Management C4: 
Environment Risks & Resource Management 
Inception Report - Final 
Location: 
Conference Room, MNRE offices, Matautu 
Date: 
 
14 April 2005 
Time:  
9.30am 
 
Attendees List 
Name
Organisation
Address/Contact
Vitaoa Pele Fuatai 
MNREM 
pfuatai@lesamoa.net
 
2 Cedric 
Schuster 
PECL 
cschuster@conservation.ws
 
3 Don 
Lyon 
Beca 
don.lyon@beca.com
 
John McFarlane 
PMU (IPA Ltd) 
johnmcf@ipa.com.ws
 
Jude Kohlhase 
MWTI (PUMA) 
jude.kohlhase@mnre.gov.ws
 
6 Ted 
Wells 
Beca 
ted.wells@ipa.com.ws
 
7 Keith 
Frentz 
Beca 
keith.frentz@beca.com
 
Natalie Mitchell 
MWTI  (PUMA) 
natalie.mitchell@mnre.gov.ws
 
Fiona Sapatu 
MWTI  (PUMA) 
fiona.sapatua@mnre.gov.ws
 
10 
Fetoloai Yandall-Alama 
MWTI  (PUMA) 
fetoloai.alama@mnre.gov.ws
 
11 Debbie 
Cunningham  Beca/Kestrel 
dc@kestrel.co.nz
 
12 
Simon Chambers 
MCDEM, NZ 
Simon.chambers@dia.govt.nz
 
13 
Mueiagatele Joe Reti 
PECL 
joereti@conservation.ws
 
14 Michele 
Daly 
Beca/Kestrel 
md@kestrel.co.nz
 
15 Graeme 
Roberts 
Beca 
graeme.roberts@beca.com
 
16 Leo’o 
Polutea 
MNRE 
leo’o.polutea@mnre.gov.ws
 
17 Filomena 
Nelson 
MNRE 
filomena.nelson@mnre.gov.ws
 
18 
Kirisimasi Seumanutafa 
MWTI  (PUMA)  
kirisimasi.seumanutafa@mnre.gov.ws
 
19  
 
 
20  
 
 
21  
 
 
22  
 
 
23  
 
 
24  
 
 
 
background image
 
 
SIAM 2 Inception Report Workshop 
14 April 2005 
Meeting Notes 
Issue 1: 
PUM Act 
ƒ
Uncertainty of the scope of the task of reviewing the PUM Act along with the change 
of the PUM Authority to MWTI.  This is likely to result in the need to review other 
legislation to ensure that the statutory base remains valid. 
Resolution: 
Review PUM Act as per TOR and identify other reviews that should be undertaken 
either as an extension to the contract or by others. 
Issue 2: 
CIM Strategy  
ƒ
CIM Strategy and Plans have a Coastal focus and while most of the population and 
infrastructure is in this band they are not management tools for the whole of Samoa. 
ƒ
Need to build on the strengths of the CIM Strategy including: 
Easy to read 
Concise 
Partnership between Village and Government 
Provides for integrated management from Strategy to Policy to Implementation 
Applies to everyone 
ƒ
Acknowledge need to incorporate “whole of catchment” inputs/outcomes as they 
affect the Coastal margin: 
Resolution: 
Prepare an update to the CIM Strategy including a new section on inland/whole of 
catchment issues and related policies and actions supported by an associated technical report within 
the scope of the present contract. 
Issue 3: 
CIM Plans  
ƒ
Can CIM Plans be adapted to be SMPs 
Different focus from partnership between Government/village to regulatory 
CIM Plans focused on coastal issues not broad land use issues encompassed by 
SMPs 
Not envisaged that CIM Plans be extended to cover another 35 villages inland. 
Human resource management issues within PUMA/MWTI  
Elements of CIM Plans in an SMP but not a whole SMP in itself 
Villages not ready for regulatory approach of SMPs 
Resolution:  
Prepare a relationship diagram/structure incorporating National/Local planning mechanisms and 
effects based mechanisms.  E.g., National Policy and Regulatory Statements, Local implementation 
guidelines, Coastal Strategy and Plans and Land-use Plans.  The relationships of these Strategies, 
background image
 
 
Plans and Guidelines are vertical and horizontal incorporating social and physical elements within 
the scope of the present contract. 
Prepare a National Coastal Sustainable Management Plan as an example of a National Policy and 
Implementation Guideline within the scope of the present contract. 
 
ƒ
What is the appropriate form of Planning structure for Apia? 
Key issues are land use 
Beach and coast largely protected (sea wall) 
Infrastructure highly resilient as has stood the test of time. 
Resolution:  
Consider amending the scope of the project in the Apia urban area to prepare an SMP as an 
extension to the contract.  Coastal issues incorporated into the SMP but mainly dealing with Land-
use and network infrastructure issues. 
Consider relevance of Structure Planning in some areas e.g., Vaitele (presentation to be provided to 
PUMA on Structure Planning as a development management tool). 
Issue 4: 
Provision of Aerial Photography and mapping layers 
ƒ
Difficulties in resourcing the provision of aerial photographs and hazard data used in 
consultation from both Beca and MNRE point of view. 
Long lead time to obtain aerials  
No A1 laminator in Samoa (need to send to Auckland) 
Extensive drain on MNRE resources 
Acknowledges MNRE concern that unauthorized use may occur beyond the 
scope of the project. 
Resolution: 
To make aerial photographs and associated topographic, hazard and text layers 
available in Mapinfo format for the project use.  To be installed on a password protected, secure 
system accessed by named personnel and returned (including updates provided as a result of the 
project) as a deliverable at the end of the project. 
Issue 5: 
Emergency Management  
ƒ
Longer timeframe for some components required to fully incorporate the project 
requirements 
ƒ
The strategic (longer term) element of the Business Plan not included in TOR but 
should be included as part of Business Plan. 
ƒ
The extent to which consideration of the National Coordination Centre (in terms of fit-
out, establishing operational capability etc) as part of the TOR needs clarification – also 
the relationship of the National Coordination Centre with other Emergency 
Management activities – Police, Fire etc., and who has responsibility for the facility. 
ƒ
Preparing a summary of hazards for the NDMP is a part of the methodology, however, 
the collection and review of hazards information as an input to the summary is beyond 
the scope of the TOR.  
background image
 
 
ƒ
Attendance at the SOPAC regional meeting in June by one of the consultant team. 
ƒ
Provision of an inventory of Disaster Management assets including physical and 
intellectual as an extension to the TOR. 
Resolution:  
Complete project as per TOR and identify further work that should be undertaken either as an 
extension to the contract or by others.  
Clarification of the status of the NCC (who is responsible for the facility; ability to use the current 
facility for its intended purpose etc) to be provided. 
 
Suggested Way Forward 
To confirm the above resolutions 
 
background image
 
 
ƒ Appendix F 
MCDEM Comments on 
Draft Inception Report 
and Inception Review 
Workshop - Letter Dated 
18 April 2005 
background image
background image
 
 
ƒ Appendix G 
List of Persons Consulted 
for Emergency 
Management
Workstream Inception 
Visit
background image
 
 
Persons met with during the Inception Visits (March and April 2005) for the Emergency 
Management Workstream
 
 
 
1. Paul Brennan 
Police Institutional Strengthening Project, AusAid 
 
2. Levaopolo Tupae Esera, CEO,  
Ministry of Education, Sports & Culture 
 
3. Namulauulu Tautala Mauala, Secretary-General,  
Samoa Red Cross Society 
 
4. Tony Hill, Assistant Fire Chief 
Ministry of Police, Prison and Fire Services. 
 
5. Assistant Police Commissioner 
(Tour of National Co-ordination Centre (NCC)) 
 
6. Muaausa Joseph Walters CEO, and Sam Unutoa, Safety Training Officer 
Electric Power Corporation 
 
7. Alefosio Matulino, Acting General Manager 
Airport Authority 
 
8. Michael Johnston, CEO  
SamoaTel 
 
9. Luagalau Foisaga Eteuati Shon, CEO,  
Ministry of Women, Community & Social Development 
 
10. Mulipola Ausetalia Titimaea, Assistant CEO plus several staff 
Meteorology Division 
 
11. Papali’i Lorenesse Neru, Police Commissioner 
Ministry of Police, Prison and Fire Services. 
 
12. Taulapapa Captain, Maselino Tominiko, Asst CEO Maritime 
Ministry of Works, Transport & Infrastructure 
 
13. J. Saufoi Moors, Director – Asset Management, Buildings 
Ministry of Works, Transport & Infrastructure 
 
14. Barry Wilson, Police Institutional Strengthening Project, AusAid 
 
background image
 
 
15. Lt Cmdr Andy Schroder, Maritime Surveillance Adviser 
Royal Australian Navy, Samoa Police, Prisons & Fire Service 
 
16. Palanitina (Tina) Toelupe, CEO, Ministry of Health 
 
17. Philip Hewitt, NZAID Manager (First Secretary), NZ Consulate, Samoa 
 
18. Mavaega Mupo, Port Authority 
background image
 
 
ƒ Appendix H 
Letter from BICL to 
MNREM & MWTI dated 22 
February 2005 
background image
 
 
 
Ministry of Natural Resources & Environment 
Private Bag 
APIA 
SAMOA 
 
Attention:  Tu’u’u Dr Ieti Taulealo 
22 February 2005 
Our Ref:  6060030/100  
Final Inception Report - 
May 2005.DOC 
Dear Sir 
SIAM2 - Sustainable Management C4: Environment Risks & 
Resource Management Inception Report - Final
We refer to our meeting in your offices earlier today regarding the above contract. At that 
meeting we discussed the potential impacts upon the project, both practical and 
contractual, arising from the recent decision of Cabinet to undertake some restructuring of 
functions between MNRE and MWTI. It was agreed that we write to you setting down our 
understanding of these changes and the practical and contractual implications for the 
project.  
We understand that the following changes are to occur: 
ƒ
The transfer of the Planning and Urban Management Agency (PUMA) from MNRE to 
MWTI, including the responsibility for the preparation of the CIM Plans for the 
remaining 26 districts under the above project, the review and amendments to the CIM 
Strategy and any consequential changes to the CIM Plans already completed under 
Phase 1 of the project.  
ƒ
We also understand that the responsibility for the drafting of the amended EIA 
regulations, to be promulgated under the PUMA Act, will also be transferred to MWTI. 
ƒ
The NDMO is to remain within MNRE under the Meteorology Division which is to be 
transferred to MNRE from the Ministry of Agriculture Forests, Fisheries and 
Meteorology. 
 
We understand and seek your confirmation of the following with regard to our obligations 
under the contract for the above project: 
ƒ
That the PUMA Division within MWTI will continue to have the lead responsibility for 
Government inputs to the preparation of the CIM plans and the review of the CIM 
Strategy in close consultation with MNRE. Final approval of the CIM Plans is to be by 
the Minister of Works, Transport and Infrastructure. 
ƒ
That the counterpart staff support arrangements, which were developed under Phase 1 
of the Project, whereby Government staff were provided to be a part of the village and 
background image
 
 
district consultation teams will continue for the duration of this project. Such provision 
to be mutually agreed and programmed in advance of the consultation occurring. 
ƒ
The review of current draft EIA regulations and the drafting of amended legislation is 
to be undertaken for MWTI in close consultation with MNRE, the Attorney General’s 
office and other stakeholders. Final approval of the draft regulations to be by the 
Minister of Works, Transport and Infrastructure. 
ƒ
The provision of all other services under the contract to remain with MNRE with final 
approval of deliverable items to rest with the Minister of Natural Resources and 
Environment. 
ƒ
In the event of any disagreement regarding the matters set out above, in the first 
instance this be resolved under the auspices of the IAMP Steering Committee. 
 
As we discussed, whilst we have some concerns that our contract will be with MNRE and 
yet a substantial proportion of the deliverable items will now be for MWTI, we would be 
comfortable with this being recorded in an exchange of correspondence. 
We are looking forward to working with you and your staff again on this project. We are 
confident that with a continuation of the goodwill and professionalism exhibited by all 
parties, as was the case in Phase 1 of the project, a similar positive outcome is assured for 
this phase.  
 
Yours faithfully 
Beca International Consultants Ltd 
 
 
 
Graeme Roberts  
Project Director 
Direct Dial: +64-9-300 9271 
Email: 
graeme.roberts@beca.com
 
 
 
cc: Vaaelua Nofo Vaaelua CEO, MWTI. 
 John Macfarlane, PMU 
background image
 
 
ƒ Appendix I 
Districts Table and 
District Program Map 
background image
6060030/100 
Beca Page 
26 
 
L2:54484-Final Inception Report - May 2005.DOC 
 
20 May 2005  
 
 
SIAM2 - Sustainable Management C4: 
Environment Risks & Resource Management 
Inception Report - Final 
Political District 
Number
Villages
Date
Completed
Order
Start Date 
Aiga I Le Tai, Satuimalufilufi 
10 
11 
07/2001 
 
 
Vaisigano I 
33 
10/2001 
 
 
Palauli (East) 
40 
11/2001 
 
 
Falealili 15 
12 
12/2001 
 
 
Vaimauga East 
02/2002 
 
 
Falelatai/Samatau 11 
02/2002 
 
 
Anoama'a West 
22 
02/2002 
 
 
Lefaga/Falese'ela 12 
06/2002 
 
 
Gagaifomauga I 
30 
06/2002 
 
 
Salega 37 
06/2002 
 
 
Gagaemauga II 
28a & b 
07/2002 
 
 
A'ana Alofi I 
7a 
07/2002 
 
 
Va'a o Fonoti, Saletele, Sauano 
20 
08/2002 
 
 
Safata 13 
08/2002 
 
 
Fa'asalele'aga I 
23 
08/2002 
 
 
Si'umu 14 
 
05-06/2005 
Vaisigano II 
34 
 
07-09/2005 
Falealupo 35 
 
07-09/2005 
Alataua West 
36 
 
07-09/2005 
Lotofaga 16 
 
10-12/2005 
Lepa 17 
15 
 
10-12/2005 
Aleipata Itupa I Luga 
18 
 
10-12/2005 
Aleipata Itupa I Lala 
19 
 
10-12/2005 
Fa'asalele'aga II 
24 
11 
 
01-03/2006 
Fa'asalele'aga III 
25 
 
01-03/2006 
Fa'asalele'aga IV 
26 
 
01-03/2006 
Gagaemauga I 
27a 
 
01-03/2006 
Sagaga Le Falefa 
12 
 
04-06/2006 
Sagaga Le Usoga 
 
04-06/2006 
Gagaemauga I 
27b 
 
04-06/2006 
Faleata East 
 
07-09/2006 
Faleata West 
 
07-09/2006 
Vaimauga West 
17 
 
07-09/2006 
Gagaemauga III 
29 
 
10-12/2006 
Gagaifomauga II 
31 
10 
 
10-12/2006 
Gagaifomauga III 
32 
 
10-12/2006 
Palauli West 
38 
11 
 
01-03/2007 
Satupa'itea 39 
 
01-03/2007 
Palauli Le Falefa 
41 
 
01-03/2007 
A'ana Alofi II 
 
04-06/2007 
background image
6060030/100 
Beca Page 
27 
 
L2:54484-Final Inception Report - May 2005.DOC 
 
20 May 2005  
 
 
Political District 
Number
Villages
Date
Completed
Order
Start Date 
A'ana Alofi III 
9a 
 
04-06/2007 
Anoama'a East (Falefa, 
Lufilufi) 
21 2   9 
04-06/2008