background image
 
P
a
g
e
1
 
DRAFT FOR DISCUSSION JULY 2009 
HYOGO FRAMEWORK FOR ACTION 
MID-TERM REVIEW 2009-2010 
 
ANALYTIC FRAME FOR THE MTR 
The HFA includes a call for it to be “appropriately reviewed”. Thus, the approach taken for 
the mid-term review (MTR) and its scope should be organised in line with the original layout 
of the HFA
1
, and use the specific indicators of progress designed and promoted by ISDR
2
The initial baseline against which the MTR is conducted could be the situation prevailing at 
the time of the Hyogo Conference in early 2005.  
It is suggested that the MTR is conceptualised in two parts: first, a retrospective 
examination of the period 2005-2010, and second, a prospective scan of 2010-2015 and 
even perhaps towards the horizon beyond.  
As this is an interim stock-take that is barely half way through a ten-year work programme, 
the MTR should be realistic in focusing principally at the level of indicators for inputs and 
outputs
, equating roughly to the HFA structure as follows:  
-  the extent to which the “key actors” have performed the “critical tasks” they were 
requested to do in the HFA, including the extent to which the stated “general 
considerations” have informed the way implementation has taken place.  (This is 
largely a measure of “input”).   
-  the extent to which the “key activities” identified under the “priorities for action” in 
the HFA have taken place, including the extent to which the stated “cross cutting 
issues” have been incorporated.  (This is a measure of “output”) 
-  the resources that have been expended in implementing the HFA. (This is a measure 
of “input”)  
Secondarily, the MTR could exercise best judgement in relation to indicators of results and 
impact
, equating roughly to the HFA structure as follows:  
-  the extent of advancement of the “strategic goals” of HFA. (This is a measure of 
“results”) 
-  the extent of achievement of the “expected outcome” of HFA. (This is a measure of 
“impact”) 
                                                             
1
  The HFA  specifies an  overarching expected  outcome  for delivery  through  the  progression  of three strategic 
goals, realised through five priorities for action.  The associated implementation and follow-up framework sets 
out  a  multi-sectoral  and  multi-stakeholder  approach  with  recommended  actions  by  key  actors  (states,  regional 
institutions, international organisations, and ISDR partners and secretariat, with civil society included) who are 
asked  to  give  due  consideration  to  stated  cross  cutting  issues  and  critical  tasks.  There  is  additional  explicit 
emphasis on resource mobilisation. (From Summary of the HFA 2005-2015, ISDR,2005 ) 
2
Indicators of progress: Guidance on measuring the reduction of disaster risks and the implementation 
of the Hyogo Framework for Action. ISDR, 2008 
background image
 
P
a
g
e
2
 
4.5 
The criteria for assessing the extent of progress that has been made in each of the 
above dimensions could be the five-point achievement scale contained in the HFA Indicators 
Set.   
4.6 
Having measured inputs and outputs as rigorously as possible and expressed 
judgements on results and impact as best as we can, these findings will need to be 
contextualised by interpreting them against the background of the changes (eg thinking on 
climate change) that have taken place since 2005 including: 
•  advances in scientific and technical understanding;  
•  political and policy evolution;  
•  institutional developments;  
•  national, regional and international cooperation frameworks; 
•  public awareness and expectation; and, 
•  financing patterns.     
The first – retrospective - part of the MTR analysis would conclude by answering the 
following:  
 
  What has been done well and not so well? 
  What have been the gaps and constraints in delivery? 
  What improvements need to happen? 
 
The second – prospective - part of the MTR would start with an analysis of global trends 
covering the same factors as indicated earlier ie. our best judgement on anticipated trends in 
scientific knowledge, policy, institutions, cooperation frameworks, public expectation, and 
financing.  This would conclude by answering the following: 
 
 What can each of the “key actors” do to enhance HFA implementation towards 2015? 
 In particular, how can HFA strengthen practical linkages and bring convergence in 
relation to closely related issues such as climate change?  
 In particular, how can HFA resourcing be placed on a predictable and sustained 
footing?  
 And, looking beyond 2015, what could a successor framework to HFA look like and 
how should we start thinking and working towards that?   
 
MODALITIES OF THE MTR   
The HFA is founded on the basis of an intergovernmental agreement that has been widened 
by the inclusion of other groups. Accordingly, the suggested modalities for conducting the 
MTR seek to maximise participation by all HFA “key actors” and to be efficient through 
utilising existing ISDR system processes and mechanisms such as national platforms, 
regional and sub-regional forums, international organizations and meetings, supported by the 
UNISDR web facilities.  It can also draw on monitoring processes in other policy areas 
outside the ISDR system. Perhaps special consultations among key stakeholder groups may 
be needed, e.g. with donor governments in relation to financing strategies; or among 
countries sharing common exposure or vulnerability to certain hazards. It will draw on 
available information, thus interconnecting better and bringing clarity, coherence, and 
ownership of the resulting analysis.  At the same time, the MTR also provides an opportunity 
to foster honest self-reflection and to stimulate creativity and innovation in looking forward.  
This is vital to the objective of strengthening HFA commitment and delivery.  
background image
 
P
a
g
e
3
 
 
The following methods for harvesting information and analysis are proposed:  
 
•  Reviewing available reports from countries and agencies in relation to disaster 
reduction related reporting systems, as well as other reports in relation to 
humanitarian and development action such as progress reporting on national 
development strategies, achievement of the MDGs etc.    
•  Drawing on the analysis contained in the 2009 Global Assessment Report 
•  Commissioning national, regional, and thematic platforms to use their forthcoming or, 
if necessary, additionally arranged meetings to conduct reflection on progress 
according to a standardised checklist of questions and to produce their MTR reports 
according to a standardised format 
•  Issuing a general invitation to national, regional, and international agencies (including 
UN agencies, International Financial Institutions, Red Cross Red Crescent Movement, 
NGOs, academic bodies, and other civil society groups, to submit their reflections on 
progress according to a standardised format. This includes the agencies that are part of 
the ISDR System joint Work Programme.  
•  Commissioning special sub-studies on key topics eg on financing, and on the interface 
with climate change.  
•  Conducting special consultations with key stakeholder groups eg. donor governments 
in relation to financing strategies; or, among countries sharing common exposure to 
certain hazards; civil society and community perspectives; research bodies; financial 
and private sector.   
•  Utilising modern communications technology to hold some global e-conferencing 
through discussion forums or other equivalent means on selected topics. The intention 
here is to inform and learn, and to popularise and establish a supportive public climate 
which ultimately impacts on government policies.   
 
 
ORGANISATION OF MTR  
 
A team approach is envisaged drawing on capacities and expertise from around the globe. All 
collaborating ISDR partners (in governments and agencies) could be asked to nominate their 
focal points for the MTR through whom consultation and dialogue can be conducted. These 
focal points would together comprise the MTR Reference Panel.  A representative sample
3
 
of these focal points and a few other selected experts may be constituted as the MTR 
Steering Group. 
   Both bodies would conduct their interactions largely through electronic 
means and tele-conferencing, though meetings may be arranged as needed.   
 
A shared electronic workspace would be available through the ISDR peventionweb. The 
ISDR Secretariat is charged with managing and servicing the MTR process, and will need 
some dedicated capacity for doing so in addition to the lead consultant.   
 
TIMESCALE FOR MTR 
The MTR process started at the 2
nd
 session of the Global Platform in June 2009 and conclude 
at its 3
rd
 session in June 2011 with publication of the final set of MTR reports. The MTR 
should be a “living process” and, along the way, a series of intermediary outputs could 
                                                             
3
  Recommended that this is up to 20 people maximum so as to facilitate ease of working.   
background image
 
P
a
g
e
4
 
be expected in line with the spirit of MTR to catalyse reflections on varied aspects of the risk 
reduction agenda at all levels.  
The proposed timeline for  MTR process could be phased
4
 as follows:   
Phase  
Timing 
Output of phase 
By June 2009  at the 
Global Platform on 
DRR 
•  Scope of work for MTR discussed   
• 
Informal discussions among ISDR stakeholders 
including consultations with governments and 
agencies  
By September 2009 
•  MTR Steering Group, and ISDR Secretariat 
designated management capacity constituted 
•  Detailed TORs for MTR components drafted and 
agreed; working modalities also agreed including 
timeline for key events that will consider elements 
of the MTR 
By December 2009 
•  Tools (eg standardised templates and formats) 
agreed.  
•  Reports and special studies commissioned  
By June 2010  
•  Reports received 
•  Consultations held   
•  Sections of draft report done, to be reflected in SG 
report to GA 
By Sept 2010 
 
•  Consolidated Draft 1 produced and peer reviewed 
at regional and thematic meetings in preparation 
for 3
rd
 Global Platform (Sept-Dec 2010) 
Quarter 4 of 2010 
•  Continued consultations and analysis of reports 
•  Discussion on HFA progress and emerging MTR  
findings at UN General Assembly (side event) 
By February 2011 
•  Consolidated draft MTR report ready and peer 
reviewed by Steering Group and ISDR system 
focal points  
 
May 2011  
•  Launch of final MTR report at 3
rd
 session of the 
Global Platform on DRR and subsequent other 
launches (note: 
•   
•   
•   
•   
•   
•   
•   how will this be managed in parallel with GAR 
launches) 
                                                             
4
  The timing of these phases could be adjusted to take account of key events or other meetings.   
background image
 
P
a
g
e
5
 
July 2011 
•  MTR conclusions and recommendations also 
presented to UN General Assembly (Sept) as part 
of SG report on ISDR (July) 
10 
May-July 2011 
•  Post MTR dissemination process to ensure 
understanding and ownership of conclusions and 
messages, and rapid follow up actions.